Forwards Rev 2 to Plan for Partial Release of Stop Work Action 10 Refueling Bellows Nde
ML20072A783
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/14/1983
From: Hall D
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20072A784 List:
References
NUDOCS 8301240128
Download: ML20072A783 (1)


Text

. ._ .

s ILLIN0/8 POWER COMPANY CLINTON POWER STATION, P.O. BOX 678. CLINTON, ILLINOIS 61727 January 14, 1983 Docket 50-461 Mr. James G. Keppler Regional Administrator .

Region III '

U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

SUBJECT:

Stop Work Action #10 Refueling Bellows

Dear Mr. Keppler:

i Your letter dated December 2, 1982 provided cuncurrence with our plan for action on a limited resumption of work on the refueling bellows. Illinois Power Company's letter of November 23, 1982 comnitted to developing a more detailed plan for disposition r the refueling bellows.

The attachment is a copy of Revision 2 of the Plan for Partial Release of SWA 10 Refueling Bellows dated January 11, 1983 which provides additional details and estimates of scheduled implementation of disposition of the refueling bellows. This plan is being implemented through Sargent and Lundy engineering analysis.

We trust this presents our plan for continued action on the subject.

Si rel yours, l

. . Hall Vice President DPH/jb attachment cc: NRC Resident Inspector Manager-Quality Assurance Director-0ffice of I & E, US NRC, Washington, DC 20555 Illinois Department of Nuclear Safety i

~

~'