FLORIDA POWER & LIGHT COMPANY ST. LUCIE UNIT 2 CONSTRUCTION / START-UP t

d MONTHLY STATUS REPORT CURRENT PERIOD:

JANUARY 1983 SCHEDULE STATUS:

OVERALL PROJECT Percent complete not applicable at CONSTRUCTION / START-UP this stage of project CRITICAL PATH VARIANCE 21.0 TARGET FUEL LOAD DATE 10/28/82 (Original Schedule)

A re-evaluation of the project schedule, completed December 1982, places the current fue. load date at March 23, 1983 MAJOR WORK HIGHLIGHTS:

SCHEDULED ACTUAL 1.

Begin construction of Radiation, Control Access Bldg.

01/01/83 01/03/83 2.

Complete interior painting of Dry Storage Warehouse 02/01/83 01/04/83 3.

Work on eleven (11) PTO's and ten (10) CTO's, in N/A N/A support of core load, was corapleted and turned over to FP&L this period. Systems included were the re-fueling machine, communications and security.

4.

The Diesel Generator Building and the Component N/A N/A-Cooling Building were turned over to Plant Operations this period.

BULK QUANTITY STATUS:

AVERAGE MONTHLY INST. RATE (Quantities include items (QTY /MO) 10%-90%

required after Core Load)

TOTAL QTY QTY PERCENT CURRENT 10/28 INSTALLED COMPLETE MONTH TO DATE FORECASTED TO DATE TO DATE Concrete (cy) 141,045 99.8 217 ESSENTIALLY COMPLETE Large Bore Piping (lf) 79,985 99.6 60 ESSENTIALLY COMPLETE l

Small Bore Piping (if) 92,465 96.4 50 ESSENTIALLY COMPLETE Instrument Tubing (lf) 116,004 94.9 205 ESSENTIALLY COMPLETE Large Bore Hangers (ea) 4,160 94.5 42 ESSENTIALLY COMPLETE I

Whipping Restraints 548 95.1 9

ESSENTIALLY COMPLETE Cable Tray (lf) 40,058 99.0 130 ESSENTIALLY COMPLETE Conduit (Exp., Emb., U/D) (1f) 417,120 96.3 6,988 ESSENTIALLY COMPLETE Lighting Conduit 117,174 98.1 3,666 ESSENTIALLY COMPLETE Power Cable Pull (lf) 537,784 97.7 14,623 ESSENTIALLY COMPLETE i

l Control Cable Pull (Inc.

Comm.) (if) 2,167,862 97.3 63,578 ESSENTIALLY COMPLETE l

Signal Cable Pull (lf) 1,277,848 95,9 68,451 ESSENTIALLY COMPLETE ESSENTIALLY COMPLETE Terms - Pwr Hi (ea) 483 97.8 l

Terms - Pwr Io (ea) 12,302 95.4 216 ESSENTIALLY COMPLETE Terms - Control (ea) 58,998 90.7 2,301 ESSENTIALLY COMPLETE Terms - Signal (ea) 32,593 95.9 3,904 ESSENTIALLY COMPLETE START-UP PROGRAM STATUS:

SCHEDULED COMPLETED SCHEDULED CURRENT TOTAL TO DATE TO DATE PER MONTH MONTH REQUIRED System Turnover (FTO) 323 323 27 12*

327 System Turnover (CTO) 162 145 28 12*

167 Preoperational Test Procedures 229 228 1

0 229 Preoperarional Test Performed 229 76 154 17/87**

229 I

  1. NOTE:

INFORMATION CURRENT AS OF PROJECT SCHEDULE DATED 01/31/83

  • NOTE:

INCLUDES PACKAGES IN SIGN-OFF CIRCUIT

    • NOTE:

INCLUDES PREOPERATIONAL TESTS IN PROGRESS, 125 PREOPERATIONAL TESTS WERE PERFORMED DURING THE HOT OPS MILESTONE. SOME OF THESE ARE WAITING ON CLEARING UP EXCEPTIONS TO TOTALLY CLOSE OUT THE PREOP.

SPECIAL TEAM ASSIGNED TO START-UP TO CLEAR UP EXCEPTIONS TO CLOSE OUT THE PRE-OPS BY CORE LOAD.