MONTHYEARML20039F1501981-12-10010 December 1981 Requests Listed Info Be Provided Re Fuel Failures & Iodine Spiking,Prior to Start of Cycle 5 Operation.Info Relates to Investigation Into Cause of Previous Fuel Failures,Proposed Remedy & Notification If Addl Fuel Failures Occur Project stage: Other ML20064N3021983-02-0707 February 1983 Confirms Discussions W/Nrc Re Starting Date & Expected Duration for Refuel 4 & Establishes Schedule for Refuel 5. Refuel 4 Scheduled for 830319.Planned Mods Require 16 Wks. Cycle 5 Begins Approx 830709 Project stage: Other ML20073F5301983-03-31031 March 1983 Proposed Tech Specs Re Cycle 5 Operation W/Reactor Coolant Pump Power Monitors & 2-yr Cycle Impact Project stage: Other ML20073F5111983-03-31031 March 1983 Application for Amend to License DPR-72,consisting of Tech Spec Change Request 82 Re Cycle 5 Operation W/Reactor Coolant Pump Power Monitors (BAW-1767) & 2-yr Cycle Impact. Certificate of Svc Encl Project stage: Request ML20073F5751983-03-31031 March 1983 3,Cycle 5 Reload Rept Project stage: Other ML20072D9801983-06-17017 June 1983 Submits Addl Info Supporting 830331 Tech Spec Change Request 82 Re Cycle 5 Operation W/Reactor Coolant Pump Power Monitors.Response Time for Pump Status Based on Reactor Coolant Power Pump Monitor Trip Should Be 1.44 Project stage: Other ML20099B4181983-06-22022 June 1983 Application for Tech Spec Change Request 82 to License DPR-72,amending Shutdown Margin.Attachments C & E Encl,Per 830331 Submittal.W/Certificate of Svc Project stage: Request ML20099B4241983-06-22022 June 1983 Proposed Tech Spec Changes Re Shutdown Margin Project stage: Other ML20024B8181983-07-0606 July 1983 Forwards Addl Info in Support of Tech Spec Change Request 82 Re Cycle 5 Operation W/Reactor Coolant Pump Power Monitors (Rcppm) Per 830701 Request.Testing of All Rcppm Strings Prior to Startup Will Consist of Checking Time Delays Project stage: Other ML20076M4991983-07-12012 July 1983 Safety Evaluation Supporting Amend 64 to License DPR-72 Project stage: Approval ML20076M4921983-07-12012 July 1983 Amend 64 to License DPR-72,extending 18-month Surveillance Requirements to 24 Months to Correspond to Extended Core Lifetime for Cycle 5 Project stage: Other ML20078H2301983-07-31031 July 1983 Reactor Containment Bldg Integrated Leak Rate Test, Jul 1983 Project stage: Other ML20105B8631983-09-0606 September 1983 Provides Results of Review of NSHC Package Re Cycle 5 Reload.Justification for Denial Needed Project stage: Approval ML20078H2241983-10-11011 October 1983 Forwards Reactor Containment Bldg Integrated Leak Rate Test, Jul 1983 Project stage: Other 1983-06-17
[Table View] |
Text
r 3
[erm'o SOW ng's I
em;pp Power
- " Ve'iduary 7,1983 3F-0283-02 Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Licensing Branch No. 4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555
Subject:
Crystal River Unit 3 Docket No. 50-302 Operating License No. DPR-72 Crystal River Unit 3 Refueling Outage Schedule
Dear Sir:
This letter confirms discussions with members of your staff concerning the starting date and expected duration for RefuelIV, and establishes the timetable for Refuel V.
The starting date for RefuelIV is scheduled for March 19, 1983.
Planned plant modifications will require a 16-week outage. Therefore, Cycle 5 will begin on or about July 9,1983. Florida Power Corporation will submit the Cycle 5 Reload Report for your review on April 1,1983.
Because of the increased length of RefuelIV, Cycle 5 is scheduled to be an extended length fuel cycle. Therefore, Refuel V is scheduled to begin in the Spring of 1985.
Sincerely, Al G. R. Westafer Manager Nuclear Licensing and Fuel Management TSW:mm cc: