ML20062K306

From kanterella
Jump to navigation Jump to search
Insp Repts 50-313/93-29 & 50-368/93-29 on 931129-1203.No Violations Noted.Major Areas Inspected:Licensee Actions in Response to Items Identified During Electrical Distribution Sys Functional Insps (Edsfis)
ML20062K306
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 12/14/1993
From: Howell A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20062K304 List:
References
50-313-93-29, 50-368-93-29, NUDOCS 9312220015
Download: ML20062K306 (17)


See also: IR 05000313/1993029

Text

_. _. ._ . . . _ _ _

,

I

APPENDIX

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Inspection Report: 50-313/93-29; 50-368/93-29

Operating Licenses: DRP-51; NPF-6

Licensee: Entergy Operations, Inc.

Route 3, Box 137G

Russellville, Arkansas 72801

Facility Name: Arkansas Nuclear One, Units 1 and 2

Inspection At: Russellville, Arkansas

Inspection Conducted: November 29 through December 3, 1993

. Inspectors: Paula Goldberg, Reactor Inspector, Engineering Section

Division of Reactor Safety

Charles Paulk, Reactor Inspector, Engineering Section

Division of Reactor Safety

Philip Wagner, Team Leader, Division of Reactor Safety

Approved: jh 011(/Yi, & (4 93

' Art.1ur T.' Howell, Deputy Director, Division of Date

k._,r Reactor Safety

Inspection Summary

Areas Inspected (Units 1 & 21: Routine, announced followup inspection of

licensee actions in response to previously identified and reported issues.

Results (Units 1 & 21:

  • The licensee's actions in response to the previously identified items-

-

were found to be good.

  • The licensee's proposed additional improvement to the sources of offsite

power and additional' distribution system evaluations were considered to

be indicative of a proactive corrective action program.

  • The licensee's engineering documentation was found to provide a thorough

and easy to understand design basis.

9312220015

DR 931215

ADOCK 05000313

PDR3

q

4

.

-2-

Summary of Inspection Findings: ,

  • The following inspection followup items were closed:

313/9010-01

313/9011-01

313/9216-01

313/9216-03

313/9216-04

313/9216-05

313/9216-06

313/9313-03

313/9313-10

313/9313-11

368/9102-02

368/9102-03

368/9102-04

368/9102-06

368/9102-08

368/9102-09

368/9102-10 -

368/9102-11

368/9313-03

368/9313-10

368/9313-11

  • The following unresolved items were closed:

313/9102-01

368/9102-01

368/9102-05

Violation 313/9216-07 was closed

  • The following licensee event reports were closed:

313/91-007 ,

313/91-009

313/91-010 '

.

313/91-011

313/93-002

368/01-011

368/91-014

368/92-006

  • Inspection followup ' item 313/9216-02 remains open (paragraph 2.12)

,

Attachment: Persons Contacted and Exit Meeting

l

.

.

. __ . . _ _ _ _ _ _ _ _ _ _ _ _ ___.______m - .w . , e ei. - - - - e < . -

_

-

1

1

l

DETAI(S

1 INTRODUCTION 1

An inspection of the licensee's actions in response to items identified during

the Electrical Distribution System Functional Inspections (EDSFIs) was

conducted from November 29 through December 3,1993. The Unit 2 (ANO-2) EDSFI

was documented in NRC Inspection Report 50-313/91-02; 50-368/91-02, and the

Unit 1 (ANO-1) EDSFI was documented in NRC Inspection Report 50-313/92-16;

50-368/92-16. The inspectors used the guidance of Temporary

Instruction 2515/111, " Electrical Distribution System Followup Inspection"

while conducting this inspection.

The inspectors also evaluated the licensee's actions in response to EDSFI

related issues that were describet ;n Licensee Event Reports and some other

findings and reports that were not related to an EDSFI.

2 ELECTRICAL DISTRIBUTION SYSTEM FOLLOWUP INSPECTION (TI 2515/111)

2.1 (Closed) Unresolved Item 313/9102-01: 368/9102-01: Acceptability of

161kV Offsite Power Supply

During the AN0-2 EDSFI, the licensee determined that adequate voltage levels

from one of the two offsite electrical power supplies could not be assured

under all operating conditions. The licensee provided detailed information of

this condition in Licensee Event Report ?!3/91-010. Addizional information

and proposed corrective actions were provided in the licensee's letter dated

July 24, 1320.

By letter dated May 24, 1993, the NLC notified the licensee that the condition

that had existed was a violation of General Design Criteria 17. The letter

also stated that the NRC found the licensee's corrective actions to be timely

and acceptable. Therefore, based on the licensee's actions in response to the

problem, the NRC decided that enforcement discretion was warranted.

By letter dated May 28, 1993, the licensee provided the details of additional

improvement to both of the sources of offsite power to each unit. The

inspectors found these additional actions to be indicative of a proactive

corrective action program.

2.2 (Closed) Inspection Followup Item 368/9102-02: AC System Voltaae Droo

Study

The ANO-2 EDSFI identified a concern with excessive voltage drops to various

motor control centers. The licensee committed to reevaluate the voltage

regulation conditions for the motor control centers and to replace any control

power transformers that were determined to be undersized. By letter dated

,

'

-

July 30, 1993, the licensee informed the NRC that the calculations had been

completed and the control power transformers had been upgraded as necessary.

The licensee also stated that a similar evaluation and control power

transformer upgrade had been completed on the ANO-1 electrical system.

i

,

-2-

Tha inspectors verified that the voltage drop study had been completed and

that the control power transformers had been replaced as necessary. The

,

inspectors also verified that the ANO-1 control power transformers had been

l upgraded. The inspectors found the voltage drop calculations to be thorough

I

and easy to understand. The licensee's self-assessment of the ANO-1

electrical system was considered to be indicative of a proactive corrective

action program.

2.3 (Closed) Insoection Followup Item 368/9102-03: AC System Short Circuit

Study

The EDSFI noted shortcomings in the licensee's short circuit calculations.

The licensee had identified similar problems and had initiated steps to

correct the calculations. The licensee's program was provided in a letter

dated December 20, 1991.

The inspectors reviewed Calculations 92-E-0037-02, " Cable AC Impedance," dated

April 9,1993, and 92-E-0037-03, "AN0 AC Equipment Models for Short Circuit

and Load Flow Studies," dated riay 28, 1993. These calculations were found to

be acceptable and were verified to have been used as inputs into the short

circuit calculation. Calculation 02-E-0037-05, "AND Unit 2 Short Circuit

Study," dated October 1,1993, was performed using the computer programs

DAPPER and AFAULT. The inspectors found the assumptions and methodology to be

acceptable.

The inspectors also reviewed Calculation 92-E-0037-08, "ANO Unit 2 Equipment

Short Circuit Rating Study," dated October 21, 1993. This calculation

verified the adequacy of the momentary withstand and the interrupt capability

of all of the involved electrical equipment with the exception of the 6.9kV

feeder circuit breakers. Since these were nonsafety-related circuits that

were verified to not effect the safety-related circuits, the inspectors found

the equipment to be acceptable.

2.4 (Closedl Inspection Followup Item 368/9102-04: Voltaae Droo Study

During the EDSFI, the licensee was in the process of upgrading the dc system

voltage drop studies.

During this inspection, Calculations 92-E-0072-01, "ANO Unit 2, Class lE,

125VDC, Train 1, DC Voltage Drop Study," Revision 0, and 92-E-0072-02, "ANO

Unit 2, Class lE, 125VDC, Train 2, DC Voltage Drop Study," Revision 0 were

reviewed. The inspectors found the methodology used in these calculations to

be consistent with industry practices and acceptable. The inspectors also

reviewed Calculation 91-E-0093-01, "120V Vital AC System Voltage Drop,"

Revision 0, and found the methodology to also be consistent with industry

practices and acceptable.

4

-3-

2.5 (Closed) Unresolved Item 368/9102-05: Acceptability of Removing the

Power Supply to Certain Postaccident Monitoring Instruments

During the EDSFI, the team noted that the licensee postulated load shedding

one of the two safety-related inverters on each of the batteries. The load

shedding was necessary under loss of all ac power conditions to maintain

adequate battery voltage and capacity for other critical loads. The team was

concerned, however, because some of the loads being shed included certain

postaccident monitoring instruments. Following the EDSFI, the licensee

conducted a further review of the design and qualification criteria for

postaccident monitoring instrumentation. By letter dated July 24, 1992, the

licensee provided the results of the review the NP,C. The licensee's submittal

discussed the team's concern of removing power to certain instruments and

provided a justification for those proposed actions.

By letter dated August 23, 1993, the results of the NRC review were sent to

the licensee. The NRC found the ANO-1 and -2, design to be in conformance

with, or justified in deviating from, the guidance of Regulatory Guide 1.97,

" Instrumentation for Light Water Cooled Nuclear Power Plants To Assess Plant

And Environs Conditions During And Following An Accident," Revision 3.

2.6 (Closed) Inspection Followup Item 368/9102-06: Emergency Diesel

Generator (EDG) Fuel Oil S_ystem Modifications

During the ANO-2 EDSFI, the team found that the licensee's self-assessment had

identified a lack of measurement instrumeniation for the differenthi prenura

across the fuel oil transfer pump suction strainer. The self-assessment had

also identified that there was no control room indication of the fuel oil

storage tank level other than an alarm when the volume dropped below

22,500 gallons.

The licensee evaluated the two concerns and determined that modifications were

not needed to improve the reliability of the system. The licensee's

determination that it was not necessary to measure the differential pressure

across the strainers was based on the facts that the strainers were cleaned

each refueling outage and there was no work history of the strainers becoming

clogged. In addition, fine filters were installed on the inlets of the

storage tanks, downstream cross-connects were provided to facilitate cross-

connecting the EDG fuel oil systems in an emergency, and a differential

pressure alarm was located across each transfer pump.

The licensee determined that the fuel oil storage tank low level alarm was not

( required because the fuel oil transfer pump differential pressure would alarm

if the differential pressure increased to 25 psid. This alarm would come in

if the EDG fuel oil storage tank level was low or the strainer was clogged.

The inspectors reviewed Calculation ll-E-0107-11, "EDG Transfer Pump Delta

Pressure Alarm or low Fuel Oil," Revision 0. This calculation determined that

the transfer pump had at least 55 minutes of running time left, after the

pump's differential pressure alarm came in, prior to exceeding the pumping

requirements.

_- - _ _ _ _ _ .__ __ _ -_ _ _ _ - . - _ _ - __ _ _ _ - _ _ _ _ _ _ _ _ _ _

. .

.

l

-4-

l

The inspectors concluded that the 55 minutes of running time allowed 1

sufficient time for operator action and that the licensee had met all

regulatory requirements.

2.7 (Closed) Inspection Followup Item 368/9102-08: Evaluation of Ambient

Temperature Effects on Electrical Components Located in the EDG Rooms ,

The EDSFI noted that electrical components located in the EDG rooms were

qualified for 40 years of normal use in environments up to 55*C (131 F). The

EDSFI also noted that the licensee had calculated that the temperatures the

components could experience under worst case conditions could exceed the

qualified temperatures.

During this inspection, the licensee's actions were reviewed. The licensee

determined that the components would have to be subjected to 65 C (149 F) for

a relatively long period to significantly reduce the qualified life. The

inspectors determined that the electrical components were not normally

subjected to temperatures in excess of their design and, therefore, their

qualified lives would not be adversely affected.

2.8 (Closed) Inspection Followup Item 368/9102-09: Battery Room Ventilation

During the AN0-2 EDSFI, the licensee identified a shortcoming in the circuitry

design for the low ventilation flow alarm of a battery room. . A loss of power

to the battery room exhaust fan would also. disable the low flow alarm because

the alarm circuitry was powered from the fan's control power.

Design Change Package 88-2111, "AN0 Annunciator Upgrade Phase II (Unit 2),"

modified the circuit for the battery room exhaust fan. The circuit

modification replaced the time delay energized alarm relay with a time delay

de-energized alarm relay and rewired components to support the logic changes.

This modification provided for an alarm upon loss of power to' the exhaust fan

-

or low air flow. The modification was completed during Refueling Outage.2R9,

September 4 through October 21, 1992. The inspectors determined that the

modification had corrected the problem.

l 2.9 (Closed) Inspection Followup Item 368/9102-10: Fuse Control Program

o During the EDSFI, the team noted that the licensee ~ did not have 'a formal fuse

l control program.

l

The inspectors reviewed Procedure 1025.056, " Fuse Control,". Revision 0. The

procedure required fuses to be replaced in accordance with the fuse-lists in

the procedure or "like-for .like" if the fuse was not listed. The inspectors

were informed that the fuse' lists represented approximately 40 percent of the - ,

fuses in_both units. The licensee had performed a physical ;nspection of

approximately 4 percent of the fuses on the fuse lists. The licentee found

several discrepancies during their inspections, however, no operability

i concerns were identified.

-

. . . . .

- . . - . - _ . _ - .

'I

-5-

2.10 (Closed) Inspection Followup Item 368/9102-11: Boric Acid Pipino in

EDG Room

'

During the ANO-2 EDSFI, the team found that there were boric acid transfer:

pumps, riping, and valves located within the "A" EDG room. The team also

noted tt there were no physical barriers between the boric acid piping.and

EDG to tre /ent damage to the EDG equipment from potential leaks 'and the spray -

of boric acid. The licensee initiated Licensing Information Request

(LIR) L91-0293 to eval'uate if boric acid spray shields were_ necessary in the .

EDG A room.

The inspectors reviewed Letter AN0-93-00646 dated March 25, 1993, which stated

that, from a safety analysis basis, licensing basis, and risk basis, the

addition of boric acid shields was not-required. In addition, the' inspectors

reviewed Calculation 92-E-0076-01, " Boric Acid Pumps 2P-39A and 2P-39B Spray

Shields to Protect EDG Control Panel 2C11 and Flood Alarm Switch 2LS-2803,"

Revision 1, dated July 15,'1993. The purpose of the calculation was to

determine if it was prudent to install boric acid spray shields-in the EDG A

room. The conclusion of the calculation was that it was not prudent to

install the shields since the boric acid system had been designed in seismic

Class I, and EDG B would be available to supply the power demand if EDG A was >

,

not available due to boric acid spray.

The inspectors concluded that the licensee had met all regulatory

requirements.

2.11 (cioaO, Inmction F911cem Uw 313/0716-0).+ Agr a pth ilit LoL Startup

Transformer Surge Protection

,

The ANO-1 EDSFI noted that an analyses of the startup transformer's surge ,

protection was not available. By letter dated August 3, 1992, the licensee

committed to perform an evaluation to verify the adequacy of the surge

c protection.

During this inspection, Calculation 93-E 'J027-01, " Surge Protection," dated

June 21, 1993, was reviewed and found to. be acceptable.

2.12 (0 pen) Inspection Followup:ltem 313/9216-02: Adequacy of Protective

Devices of the Containment Electrical Penetration Assemblies (EPAs)

. The EDSFI team noted that the licensee had not conducted a formal evaluation

of the thermal and mechanical protection for the EPAs. The ANO-1 design

~

predated the guidance contained in Regulatory Guide 1.63, " Electrical l

Penetration Assemblies in Containment Structures for Water-Cooled Nuclear

'

,

Power Plants." However, the licensee had initiated Engineering Assistance

Request 92-285 on May 15, 1992, to perform an evaluation. I

!

'.

During the NRC staff review of the ANO-2 de system overcurrent protective

features, concerns were raised about the protective devices for the ANO-2-

.

EPAs. The licensee provided an initial response to the concerns by letter. l

l

I

-l

. . _ _

_

>

.

1

-6-

dated April 30, 1993. The staff reviewed the licensee's submittal and

transmitted a request for additional information to the licensee by letter

,

dated June 18, 1993. By letter dated August 20, 1993, the licensee responded

to the latest staff questions. The response was under review at the time of

this inspection.

The licensee's April 30, 1993, letter also informed the NRC that the AN0-1 EPA

evaluation would be deferred until April 29, 1994, to allow time to complete

an evaluation that considered all of the aspects being considered for the

ANO-2 EPAs. This item remains open pending completion of the licensee's

evaluation.

2.13 LClosed) Inspection Followup Item 313/9216-03: EDG Loading

Considerations

The AN0-1 EDSFI noted several problems with the licensee's EDG loading

calculations. By letter dated August 3,1992, the licensee committed to

recalculate the EDG loading and evaluate conditions that would occur during

potential load sequencing overlaps.

The inspectors reviewed Calculation 86-E-0002-01, " Diesel Generator Load

Study," Revision 6 dated November 8, 1993. Attachment 1 to the calculation

contained a tabulation of EDG loads. The total loads on the EDGs were

determined to be within the EDG load ratings for the period that the loads

would be connected to the EDG. The concerns with frequency dips when starting

the auxiliary feedwater pump had been resolved by changing the loading

sequence. The load sequencing overlap concerns had, for the most part, been

resuhed by ti,e replacastnt of pr.cumatic tfeers with more accurate solid state

timers. The potential for containment spray pump and containment fan coolers <

to overlap had been evaluated and determined to only be problem under a. unique

reactor coolant system break size. The licensee concluded that the unlikely

occurrence of the unique break size would result in the loss of only one of

the EDGs and was, therefore, acceptable. The inspectors found the licensee's

calculation and associated evaluations to be acceptable.

2.14 (Closed) Inspection Followup Item 313/9216-04: Unit 1 DC System Voltage

Drop Study

During the EDSFI, the team noted that the licensee had identified the lack of

adequate dc voltage drop calculations.

The inspectors reviewed Calculation 92-E-0021-06, " Unit 1, Class 1E,120 Volt

Vital AC System Voltage Drop Analysis," Revision 0. The inspectors found the

methodology to be the same as that used for ANO-2 (see paragraph 2.4) and

considered this calculation to be acceptable also. The licensee had not

completed Calculation 92-E-0021-08, "AN0 Unit 1, Class 1E,125V de, Train 1,

Voltage Drop Study," or Calculation 92-E-0021-09, "ANO Unit 1, Class 1E,125 V

dc, Train 2, Voltage Drop Study." However, the inspectors noted that'the

methodology was the same as used for the ANO-2 dc voltage drop study and found

it acceptable.

~ .

.

-7-

2.15 (Closed) Inspection Followup Item 313/9216-05: EDG Fuel Oil System

Improvements

The AN0-1 EDSFI found that the EDG day tanks were not protected against

accidental overfill as recommended by ANSI N195-1976. The EDSFI also found

that a single level switch on each day tank controlled the operation of the

fuel oil transfer pump and the low level alarm. The licensee had identified -

that the EDG day tank vent pipes were subjact to possible " pinch off" by

tornado missiles. In addition, the licensee identified a lack of measurement

instrumentation for the differential pressure across the fuel-oil transfer

pump suction Y-strainers.

The inspectors reviewed Letter AN0-93-00796, dated May 21, 1993, from the

design engineering department.to the licensing department. The subject of the

letter was the resolution of the ANO-1 EDG day tank vent vulnerability from a

tornado missile. The letter stated that a modification could be performed at

a relatively low cost; however, the relative benefit would not justify the-

expenditure. The resolution of the issue was administrative actions to

address vent damage after a tornado. The inspectors reviewed _

.

Procedure 1203.025, " Natural Emergencies," Revision 11, which added followup

actions requiring the EDG day tank vents to be inspected for damage and, if

damage was found, to initiate corrective action to clear the damage as quickly

as possible.

The inspectors reviewed LIR L92-0233, dated August 8, 1992, and the response

dated February 5,1993, concerning modifications to the fuel oil day tank low

level switch and the addition of a high level alarm. The response stated that

no appreciable pl:nt safety tr.provcm ats would ba schicved by a,dding a high

level alarm to the day tanks. The response stated that the only risk involved

would be during manual fuel oil transfer operation. The inspectors reviewed

Procedure 1104.036, " Emergency Diesel Generator Operation," Revision 32,-which

added a caution note that manual operation of the fuel oil transfer pump _ could

cause day tank overflow. In addition, the response to LIR L92-0233 stated

that the existing day tank level control and alarm scheme met the requirements

of all pertinent ANO design criteria. The response also stated that ANO-1 was

not committed to meet the requirements of ANSI N195-1976.

The inspectors reviewed Letter AN0-93-00546, datr.d February 15, 1993,

concerning the lack of differential pressure measurement across the fuel oil

transfer pump suction strainers. The letter stated that differential pressure

measurement was not required because monthly tests were conducted to ensure

that the transfer pumps were performing adequately and monthly fuel oil

samples were analyzed. The licensee stated that, if the filters became

clogged, the EDG day tank low level alarm, located on the local panel in the

EDG rooms, would alert the operator of a problem. The action in response to

this alarm was for the operator to verify that the transfer pump was-

operating. If the level continued to drop, the operator was referred to

Procedure 1104.036 for emergency cross-connecting of the fuel oil systems.

The cause of low flow would be determined after flow was restored through

cross-connection of the fuel oil systems.

i

L

t

, ,

.- _ . .-

.

.

-8-

The inspectors concluded that the licensee had met all regulatory

requirements.

2.16 (Closed) Inspection Followup Item 313/9216-06: EDG Air Exhaust

Vent Stacks Tornado Missile Protection

During the ANO-1 EDSFI, the team found that the EDG exhaust piping extended '

above the concrete barriers for tornado missile protection. The team was

concerned that the exhaust pipes and associated exhaust hoods could become

crimped and limit the EDG's capability.

The inspectors reviewed LIRs L91-0231, dated August 6, 1992, and L92-0334,

dated December 17, 1992, for AN0-1 and -2, which requested tornado missile

studies to evaluate the actions required in the event of an on-site tornado.

The responses to both LIRs stated that abnormal operating procedures should be.

revised to require inspection and clearing of any damage to the exhaust piping

after a tornado.

The inspectors reviewed ANO-1 Procedure 1203-025, " Natural Emergencies,"

Revision 11, Change PC-2. The procedure was revised to include statements to

inspect the exhaust piping for damage and clear the piping as quickly as

possible, if damaged. The inspectors noted that AND-2 Procedure 2203.008,

" Natural Emergencies," Revision 4, Change PC-1 was also revised to clear the

EDG exhaust piping as quickly as possible if damaged by a tornado.

The inspectors concluded that the licensee had met all regulatory

requirements.

.

2.17 (Closed) Violation 313/9216-07: Failure to Properly Update Plant

Procedures

During the EDSFI, the team identified two procedures that had not been made

inactive after biennial reviews indicated revisions were necessary. This was

determined to have been in violation of the licensee's procedures.

The licensee acknowledged the violation by letter dated August 3, 1992. The

inspectors verified that the actions described in the response letter had been

completed. The inspectors also noted that the licensee cancelled the

procedure for biennial review of procedures as a result of receiving

permission from the NRC to reduce the commitment to ANSI N18.7-1976. The

. licensee placed administrative requirements for biennial review of station

administrative and engineering administrative procedures in

Procedure 1000.006, " Procedure Control," Revision 37, Change PC-2.

3 ADDITIONAL EDSFI IDENTIFIED ISSUES (2515/111)

Paragraph 2.2.2, " Coordination and Protective Relays," of the NRC ANO-2 EDSFI

Inspection Report (50-368/91-02) discussed a concern with the separation of

non-Class IE loads from Class 1E dc distribution panels. As stated in the

.

'

-9-

report, this issue was referred to the NRC Office of Nuclear Reactor

Regulation for further review.

By letter dated June 18, 1992, the licensee was informed that the existing

configuration would not impact the safe operation of the facility. However,

to preclude future misunderstandings, the licensee was requested to revise

Section 8.3.2.1.4, " Distribution Panels," of the Updated Safety Analysis

Report. The inspectors verified the text had been modified to discuss the

remote possibility that an inadvertent battery discharge could result if a

fault on a non-Class IE distribution panel coincided with the failure of the

Class IE circuit breaker protecting the faulted circuit.

4 ONSITE REVIEW OF LICENSEE EVENT REPORTS (92700)

4.1 (Closed) Licensee Event Report 313/91-007: Inadeauate Fuse / Circuit

Breaker Coordination

On June 14, 1991, the licensee identified that the fuses between the emergency

batteries of both ANO-1 and -2 and their associated de control centers were

not fully coordinated with the control center's load circuit breakers. The

licensee determined that this condition would occur only at the upper range of

available fault current and could, under certain conditions, result in the

loss of the entire control center before the affected load circuit breaker

would trip. The cause of the problem was design inadequacies related to

design changes made in 1984 and 1986.

The inspectors verified that the licensee had revised the design' change

program such that these problems should be eliminated. The inspectors also

verified that the correct fuses were installed by reviewing work packages

J0 847774 and 847775 (ANO-1) and JO 847396 and 847397 (ANO-2).

4.2 (Closed) Licensee Event Reoort 313/91-009: 480V Load Centers in

Nonseismic Confiauration

During the ANO-2 EDSFI, the team identified that 480V Load Centers 2B5 and 2B6

were not in a seismically qualified configuration. The licensee investigated

ANO-1 and found that Load Centers 85 and B6 were in the same configuration as

the AN0-2 load centers. Lifting trolleys used to aid in installation and

removal of circuit breakers were found mounted on their guide rails and were -

not secured in place. The licensee determined that the load center vendor had

not seismically qualified the equipment with the trolleys on their guide rails

in place.

The licensee's initial corrective action was to remove the lifting trolleys

and rails from the load centers and store them in a remote area.' The

inspectors reviewed the job orders that removed the trolleys. In addition to

removing the lifting trolleys and rails, the licensee performed a walkdown of

both units which determined that no other safety-related load centers were

affected by this condition.

.- . . - - . .

.

-10-

The licensee prepared Limited Change Packages 92-5001, " Seismic Restraint of

Jib Trolley for Load Centers B5 and B6," Revision 1, for Unit 1 and 92-6003,

" Seismic Restraint of Jib Trolley for Load Centers 2B5, 286, and 287,"

Revision 0, for Unit 2. The inspectors reviewed these modifications and found

that two separate anchoring devices were used to anchor the lifting trolley

assemblies to the load centers. By implementing these modifications, the

lifting trolleys were seismically qualified in a stowed position. The ANO-1

modification was installed during Refueling Outage IR10 and the ANO-2

modification during Refueling Outage 2R9.

'

The licensee issued Procedure 5220.002, " Equipment / Component Seismic

Evaluation," Revision 0, which provided the method for evaluating equipment

and components for seismic qualification. The inspectors reviewed the

procedure and concluded that clear and specific instructions were.provided.

The inspectors reviewed Memorandum ESU-91-00348, dated October 16, 1991, which

provided interim guidance to design engineering personnel concerning the

review of vendor documentation for seismic qualification requirements. The-

memorandum stressed careful review of any documents that could effect seismic

qualification.

.

The inspectors also reviewed a training plan that was presented to the AN0

technical staff during the fourth quarter of 1991 and found that it discussed

the configuration control problem for the load centers.

The inspectors concluded that the licensee had implemented complete and

thorough corrective actions for this issue.

4.3 (Closed) Licensee Event Report 310/91-010: Adeauacy of Offsite Power

Supply

The licensee's actions in response to this issue are discussed in

paragraph 2.1.

4.4 (Closed) Licensee Event Report 313/91-011: Inadecuate procedure for

Setting Lube Oil Pressure Control Valve

On October 9, 1991, following an. overhaul of High Pressure Injection

Pump P36A, the licensee observed an oil leak of approximately 236 ml/ min

(8 oz/ min) from the outboard pump bearing area. The licensee noted a similar

condition on Pump P36C. The licensee determined that this condition rendered

the pumps inoperable.

The inspectors reviewed the licensee's root cause evaluation and corrective

actions. The inspectors found the proposed actions to have been adequate and

completed as described in the event report.

. __ _ . _ _ - . _ _ _ _ . _

.

4

-11-

4.5 (Closed) Licensee Event Report 368/91-011: Reactor Trio During

Surveillance Testinq

On April 15,. 1991, during the performance of surveillance testing, an

automatic reactor protective system trip occurred. The licensee contributed

the cause of the trip '.o a procedural inadequacy.

The inspectors reviewe the licensee's evaluation and proposed corrective

actions. The inspectors icund the corrective actions to have been adequate

4

and complete as stated in the event report.

4.6 (Closed) Licensee Event Report 368/91-014: 4160V Circuit Breakers in

Nonseismic Configuration

The licensee determined that four circuit breakers routinely positioned in the

racked-down position were not seismically qualified in that position. The

licensee determined that the root cause of the condition was incomplete

information concerning seismic qualification in the licensing basis documents.

The. licensee immediately removed all of the breakers in the switchgear rooms

that were in the racked-down position and stored them in another area.

The inspectors reviewed System Operating Procedure 2107.002, "ESF Electrical

System Operation," Revision 7, Change PC-2. The inspectors determined that

this procedure was revised to delete the requirement for maintaining the

circuit breakers in the racked-down position.

The licensee conducted an evaluation to determine if additional procedural

guidance w?S necessary for performing maintenance activities with circuit  :

breakers in a racked-down position. The inspectors reviewed the evaluation,

which stated that the circuit breakers were operable in the racked-down u

position for maintenance purposes only if racked-down and then racked-up-by 1

inch above the floor. Calculation 91-E-0089-01, Revision 0, qualified the

circuit breakers for this condition. The inspectors verified that the

maintenance and operating procedures had been revised to specify when and for

how long the circuit breakers could be kept in the racked-down position. i

1

'

4.7 (Closed) Licensee Event Report 368/92-006: Inadvertent Start of EDG

)

During the replacement of a relay in the engineered safety features actuation

system of ANO-2 on September 9,1992, in accordance with a special work plan, i

four other_ relays were deenergized. J

!

The inspectors reviewed _the circumstances of this event and found that the i'

licensee utilized technicians to develop the work instructions for the task.

The technicians were not familiar with the equipment and the wiring

information from the vendor. This unfamiliarity led to the technicians '

missing the " daisy chain" of connections. As a-corrective action, the

licensee required an engineering evaluation prior to performing any additional

relay replacements. The inspectors considered these actions to be acceptable

due to the uniqueness of the special work being performed.

l

I

_. . - . _-

.

.

-12-

4.8 (Closed) Licensee Event Report 313/93-002: Automatic Start of an EDG

On March 9, 1993, ANO-1 was operating at 100 percent power when a 4160 volt

engineered safeguards bus was deenergized during the transfer of power sources

from an off-site supplied startup transformer to the unit auxiliary

transformer. The circuit breakers from the startup transformer and the unit

auxiliary transformer did not operate properly during the transfer.

During this inspection, the inspectors reviewed the licensee's corrective

actions and found them acceptable.

5 FOLLOWUP (91701)

The inspectors also reviewed the licensee's actions in response to previously

identified findings that were not related to the EDSFIs.

5.1 (Closed) Isspection Followup Item 313/9010-01: Service Water Structure

Ventilst'e

Problems with the ventilation system for the ANO-1 service water structure

were identified in Condition Report 1-89-453. The ventilation systems for

both unit's service water structures was subsequently included in the

licensee's service water integrity plan.

During this inspection, the inspectors reviewed the licensee's actions in-

response to Condition Report 1-89-453 and the additional licensee evaluations.

The licensee had implemented acceptable interim corrective actions in response

to the condition report,. The licensea iMtiated I.imited Change Pachoe 93-

5015 on July 8, 1993, to upgrade the ventilation systems for both structures.

The change package provided instructions for replacing the solid security

doors with doors containing manually operated dampers and other enhancements

to improve structure cooling. The inspectors found the proposed changes to be

acceptable. The inspectors observed portions of the in-progress work and were

informed that the changes were scheduled to be completed by December 20, 1993.

5.2 (Closed) Inspection Followup Item 313/9011-01: Battery Testino

Reauirements

The battery testing requirements contained in the ANO-1 Technical

Specifications were found to be inconsistent with the actual testing being

conducted at the facility and were less than currently considered acceptable.

The licensee was in the process of revising the battery testing requirements

contained in the ANO-2 Technical _ Specifications and committed to upgrade the

ANO-1 requirements to be consistent with the ANO-2 requirements when they were

finalized.

During this inspection, the licensee's Technical Specification Change

Request 1-91-25 was reviewed and found to satisfy the inspection concern.

Since the change request will be reviewed as part of a licensing action to

-. - - ~

.

.

-13-

ensure that the latest staff guidance has been incorporated, the inspectors

had no further questions on this item.

5.3 (Closed) Inspection Followup Item 313: 368/9313-03: Sprina Pack Test

'

Device Accurac_y

>

During an inspection of the licensee's motor-operated valve program, it was

noted that the licensee did not compensate for the inaccuracies associated

with the spring pack tester.

'

During this inspection, the inspectors reviewed the licensee's actions to

address this issue. The inspectors found that the licensee did not have

information related to the accuracy of the spring pack tester and had ,

requested the information from the vendor. The vendor informed the licensee

that there was no formal data relating to the accuracy of the tester; however,

the vendor provided informal data to the licensee. Although the value

provided for the accuracy of the tester was extremely small (0.28 percent),

the inspectors verified that the licensee had incorporated the information

into the motor-operated valve testing program.

5.4 (Closed) Inspection Followup Item 313: 368/9313-10: Placement of Open

Toraue Switch Bypass

During an inspection of the licensee's motor-operated valve program, it was

noted that the torque switch bypass settings for ANO-1 motor-aperated valves

were' typically set at lower opening positions than those in ANO-2.

Purir,g this inspect!99., the inspectcri verified that the licenscu had reviewed

the settings of. all valves in the motor-operated valve program at ANO for

consistent and conservative settings. The inspectors noted that the licensee

did not identify any valves with a nonconservative bypass setting. The

inspectors also found that the licensee was consistent in the methodology used

for setting the bypass switches.

5.5 (Closed) Inspection Followup Item 313: 368/9313-11: Review of Diagnostic

Traces by Second Engineer

During an inspection of the licensee's motor-operated valve program, concerns

were identified regarding the licensee's control of the diagnostic testing

process. The concerns were based on two instances where a presumed

differential pressure was little more than a static test and one instance

where the test data was severely scattered. As a result of those concerns,

the licensee committed to review all of the other differential pressure traces

to identify any similar problems. The licensee also committed to initiate a

second engineer's review of diagnostic traces.

The inspectors verified that the licensee had revised the procedures to

require a second engineer's review of the diagnostic traces to ensure the data

was valid. The inspectors also verified that the licensee reviewed all motor-

operated valve test data during differential pressure testing to ensure all

-_

,. . . .- _ - . - - _ . .- .. .- - _ - . . ,.

. .

.

-14-

traces were marked correctly and conservatively. The inspectors found that

the licensee had paid particular attention to points for flow initiation and

flow cutoff. The licensee changed the marks on 36 of the 46 differential

pressure tests as a result of the review. The licensee also eliminated three

tests due to questionable data. The licensee was in the process of completing

the engineering reviews and no problems had been identified.

,

i

,

!-

l

-

h

- . .. . ._ .

.

-- - . ..

.

.

ATTACHMENT 1

1 PERSONS CONTACTED

1.1 Licensee Personnel

  • S. Bennett, Supervisor, Licensing
  • M. Cooper, Licensing Specialist
  • G. Dobbs, Design Engineering Supervisor
  • R. Edington, Plant Manager, Unit 2
  • B. Greeson, Acting Manager, Design Engineering
  • R. Howerton, Manager, Engineering Support
  • D. Macphee, Senior Engineer
  • T. Ott, Design Engineering Supervisor
  • M. Stroud, Design Engineering Acting Manager
  • C. Turk, Engineer
  • J. Vandergrift, Plant Manager, Unit 1

,

1.2 NRC Personnel

  • S. Campbell, Resident Inspector
  • J. Helfi, Resident Inspector
  • L. Smith, Senior Resident Inspector

K. Weaver, Resident Inspector, Co-Op

In addition to the personnel listed above, the inspectors contacted other

personnel during this inspection period.

  • Denotes personnel that attended the exit meeting. .

2 EXIT MEETING

An exit meeting was conducted on December 3, 1993. During this meeting, the

inspectors reviewed the scope and findings of the inspection. The licensee

did not express a position on the inspection findings documented in this

report. The licensee did not identify as proprietary, any information

provided to, or reviewed by the inspectors.

l

l-

!

!

l'

l

.

-