Forwards IE Inspec Rept 50-317/78-26 & 50-318/78-20 on 780912-15 & Notice of Violation
ML20062C963
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 10/06/1978
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML20062C957 List:
References
NUDOCS 7811150272
Download: ML20062C963 (2)


See also: IR 05000317/1978026

Text

.. .

,

-y -

    • "'4tg UNITED STATES

fg NUCLEAR REGULATORY COMMISSION

y 3( )e(

-

S REGION I

j 631 PARK AVENUE

?

g KING OF PRUSSI A. PENN5YLVANI A 19404

0,N'Q*....f

Docket Nos. 50-317

50-318 6 OCT 1978

Baltimore Gas and Electric Company

ATTN: Mr. A. E. Lundvall, Jr.

Vice President

P. O. Box 1475 c

Baltimore, Maryland 21203

Gentlemen:

Subject: Inspection 50-317/78-26, 50-318/78-20

This refers to the inspection conducted by Mr. D. Johnson of this office

on September 12-15, 1978, of activities authorized by NRC License No.

DPR-53 and DPR-69 at Calvert Cliffs Nuclear Power Plant, Units land 2,

Lusby, Maryland, and to the discussions of our findings held by Mr. Johnson

with Mr. L. Russell of your staff at the conclusion of the inspection,

and to a subsequent telephone discussion between Mr. Johnson and Mr.

Russell on September 18, 1978.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Based on the results of this inspection, it appears that one of your

activities was not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix

A. This item of noncompliance has been categorized into the levels as

described in our correspondence to you dated December 31, 1974. This

notice is sent to jou pursuant to the provisions of Section 2.201 of the

NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office, within twenty (20)

days of your receipt of this notice, a written statement or explanation

in reply including: (1) corrective steps which have been taken by you

and the results achieved; (2) corrective steps which will be taken to

avoid further items of noncompliance; and (3) the date when full compli-

ance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and

i

l

l

'2811150x13-

. .

.

Baltimore Gas and Electric Company

2 6 0CT 1978

the enclosures will be placed in the NRC's Public Document Room. If

this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of

Section 2.790. The information sought to be withheld shall be incorporated

as far as possible into a separate part of the affidavit. If we do not v

hear from you in this regard within the specified period, the report

will be placed in the Public Document Room.

Should yau have any questions concerning this inspection, we will be

pleased :o discuss them with you.

Sincerely,

j

9 _e

E dond,Brunner, Chief

Reactor Operations and Nuclear

Support Branch

Enclosure:

1. Appendix A, Notice of iolation

2. Office of Inspection 1 Enforcement Inspection

,

'

Report Number 50-317, 18-26, 50-318/78-20

cc w/ enc 1:

R. W. Davies, Manager, Quality Assurance

,

R. M. Douglass, Chief Engineer

W. Gibson, Supervisor Operational QA