Letter Sequence Other |
---|
|
|
MONTHYEARML20247D3371989-05-19019 May 1989 Advises That Util 890303 Proposed Alternate Schedule for Completing Item 1.b to NRC Bulletin 88-011 Not Approved.Nrc Expects That Efforts Will Be Accelerated to Meet Completion Dates as Committed to by Westinghouse Owners Group Project stage: Other ML20059M0411990-09-25025 September 1990 Identifies No short-term Safety Concerns Re Thermal Stratification,Per 890531 Response to NRC Bulletin 88-011, Presurizer Surge Line Thermal Stratification Project stage: Other ML20065U3141990-12-18018 December 1990 Requests Extension of Analysis Completion Date Until 910501 Per Item 1.d of NRC Bulletin 88-011, Pressurizer Surge Line Thermal Stratification Project stage: Other ML20081G6511991-06-0707 June 1991 Discusses Plant Specific Thermal Stratification Analysis Results & Completion Date Extension Request for Completion of Action Item 1.d of NRC Bulletin 88-011 Project stage: Request 1990-12-18
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARNPL-99-0564, Forwards Response to NRC Request During 990720 Meeting,To Provide Addl Details to Several Questions Re Amend Currently Under Review by Staff Pertaining to CR Habitability1999-10-19019 October 1999 Forwards Response to NRC Request During 990720 Meeting,To Provide Addl Details to Several Questions Re Amend Currently Under Review by Staff Pertaining to CR Habitability ML20217A5911999-09-30030 September 1999 Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC with Feedback on Any Planned Insps Which May Conflict with Plant Activities.Plant Issues Matrix Encl 05000266/LER-1999-007, Forwards LER 99-007-00 for Point Beach Nuclear Plant,Unit 1. Condition Would Be Outside App R Design Basis for Plant.New Commitments within Rept Indicated in Italics1999-09-30030 September 1999 Forwards LER 99-007-00 for Point Beach Nuclear Plant,Unit 1. Condition Would Be Outside App R Design Basis for Plant.New Commitments within Rept Indicated in Italics ML20212J7431999-09-30030 September 1999 Forwards Insp Repts 50-266/99-15 & 50-301/99-15 on 990830- 0903.No Violations Noted.Inspectors Concluded That Util Licensed Operator Requalification Training Program Satisfactorily Implemented NPL-99-0555, Discusses Rev 1,suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Calculation That Provides Evaluation of New Surveillance Data for Assessing Integrity of Unit 1 Reactor Vessel1999-09-29029 September 1999 Discusses Rev 1,suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Calculation That Provides Evaluation of New Surveillance Data for Assessing Integrity of Unit 1 Reactor Vessel ML20212K7651999-09-29029 September 1999 Forwards Insp Repts 50-266/99-13 & 50-301/99-13 on 990714-0830.No Violations Noted.Operators Responded Well to Problems with Unit 1 Instrument Air Leak & Unit 2 Turbine Governor Valve Position Fluctuation ML20212D5771999-09-15015 September 1999 Discusses Review of Response to GL 88-20,suppl 4,requesting All Licensees to Perform Ipeee.Ser,Ter & Supplemental TER Encl ML20211Q6451999-09-0808 September 1999 Forwards Operator Licensing Exam Repts 50-266/99-301OL & 50-301/99-301OL for Exams Conducted on 990726-0802 at Point Beach Npp.All Nine Applicants Passed All Sections of Exam ML20211Q4171999-09-0606 September 1999 Responds to VA Kaminskas by Informing That NRC Tentatively Scheduled Initial Licensing Exam for Operator License Applicants During Weeks of 001016 & 23.Validation of Exam Will Occur at Station During Wk of 000925 05000266/LER-1999-004, Forwards LER 99-004-01,re Fuel Oil Transfer Pump Cable in AFW Pump Room Being Outside App R Design Basis.Suppl to LER Provides Corrective Actions to Address Concerns Re Fire Disrupting Electrical Power to Fuel Oil Transfer Pump1999-09-0202 September 1999 Forwards LER 99-004-01,re Fuel Oil Transfer Pump Cable in AFW Pump Room Being Outside App R Design Basis.Suppl to LER Provides Corrective Actions to Address Concerns Re Fire Disrupting Electrical Power to Fuel Oil Transfer Pump ML20211K5261999-08-31031 August 1999 Forwards Insp Repts 50-266/99-14 & 50-301/99-14 on 990726- 30.Areas Examined within Secutity Program Identified in Rept.No Violations Noted ML20211F6941999-08-27027 August 1999 Provides Individual Exam Results for Applicants That Took Initial License Exam in July & August of 1999.Completed ES-501-2,copy of Each Individual License,Ol Exam Rept, ES-303-1,ES-303-2 & ES-401-8 Encl.Without Encl NPL-99-0473, Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months1999-08-27027 August 1999 Informs of Change Being Made to Plan Third 10-year Interval ISI Long Term Plan.Change Extends Interval from Current End Date of 001130 to 020831,due to Operating Cycle Being Increased from 12 to 18 Months ML20211E8791999-08-24024 August 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, for Point Beach Nuclear Power Plant,Units 1 & 2.Licensees Provided Requested Info & Responses Required by GL 96-01 ML20211F1501999-08-24024 August 1999 Submits Summary of Meeting Held on 990729,in Region III Office with Util Re Proposed Revs to Plant Emergency Action Level Criteria Used in Classifying Emergencies & Results of Recent Improvement Initiatives in Emergency Preparedness 05000266/LER-1999-006, Forwards LER 99-006-00 Which Describes Discovery That Postulated Fire in Central Zone of Primary Auxiliary Bldg Could Result in Spurious Operation of Pressurizer Porv. New Commitments within Rept Are Indicated in Italics1999-08-19019 August 1999 Forwards LER 99-006-00 Which Describes Discovery That Postulated Fire in Central Zone of Primary Auxiliary Bldg Could Result in Spurious Operation of Pressurizer Porv. New Commitments within Rept Are Indicated in Italics NPL-99-0477, Forwards Revised Procedures to Point Beach Nuclear Plant Epips.Revised Procedures Dtd 990723,should Be Filed in NRC Copies of Manual IAW Attached Instructions1999-08-18018 August 1999 Forwards Revised Procedures to Point Beach Nuclear Plant Epips.Revised Procedures Dtd 990723,should Be Filed in NRC Copies of Manual IAW Attached Instructions NPL-99-0426, Requests Relief from Section II of ASME B&PV Code, Nuclear Vessels, 1965 Edition,No Addenda.Detailed Info Attached1999-08-16016 August 1999 Requests Relief from Section II of ASME B&PV Code, Nuclear Vessels, 1965 Edition,No Addenda.Detailed Info Attached ML20210L9141999-08-0404 August 1999 Informs That Versions of Info Re WCAP-14787,submitted in 990622 Application for Amend,Marked Proprietary,Will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954,as Amended ML20210K5221999-08-0404 August 1999 Discusses Point Beach Nuclear Plant,Units 1 & 2 Response to Request for Info in GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity NPL-99-0436, Forwards fitness-for-duty Performance Data for six-month Period Ending 9906301999-08-0202 August 1999 Forwards fitness-for-duty Performance Data for six-month Period Ending 990630 ML20210G6011999-07-30030 July 1999 Discusses 990415 Complaint OSHA Received from Employee of Wisconsin Electric Power Co Alleging That Employee Received Lower Performance Appraisal for 1998 Because Employee Raised Safety Concerns While Performing Duties at Point Beach NPL-99-0406, Provides Response to NRC GL 99-02, Lab Testing of Nuclear- Grade Activated Charcoal1999-07-29029 July 1999 Provides Response to NRC GL 99-02, Lab Testing of Nuclear- Grade Activated Charcoal ML20210H0211999-07-28028 July 1999 Forwards Insp Repts 50-266/99-09 & 50-301/99-09 on 990528-0713.Two Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210G2441999-07-26026 July 1999 Discusses 990714 Meeting with PRA Staff to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PRA Staff NPL-99-0408, Forwards Pbnps,Units 1 & 2 Plant Simulation Four-Yr Rept, IAW 10CFR55.45(b)(5)(ii).Rept Describes Certification Program Tests Conducted from 1996-1999,identifies Test Discrepancies Still Outstanding & Schedules for 2000-20031999-07-15015 July 1999 Forwards Pbnps,Units 1 & 2 Plant Simulation Four-Yr Rept, IAW 10CFR55.45(b)(5)(ii).Rept Describes Certification Program Tests Conducted from 1996-1999,identifies Test Discrepancies Still Outstanding & Schedules for 2000-2003 ML20209H5471999-07-14014 July 1999 Forwards Insp Repts 50-266/99-12 & 50-301/99-12 on 990614-18.One Violation Noted,But Being Treated as non-cited violation.Long-term MOV Program Not Sufficiently Established to close-out NRC Review of Program,Per GL 89-10 NPL-99-0395, Forwards Partial Response to NRC 990512 RAI Re TS Change 204 Re Control Room Habitability.Meeting Is Planned with NRC to Discuss Issues Related to Control Room & Primary Auxiliary Bldg Ventilation Sys Modifications1999-07-12012 July 1999 Forwards Partial Response to NRC 990512 RAI Re TS Change 204 Re Control Room Habitability.Meeting Is Planned with NRC to Discuss Issues Related to Control Room & Primary Auxiliary Bldg Ventilation Sys Modifications NPL-99-0390, Projects Listed Major near-term License Amend Requests That Could Be Expected to Impact Staff Resources Into Fiscal Years 2000 & 2001,in Response to Administrative Ltr 99-021999-07-0808 July 1999 Projects Listed Major near-term License Amend Requests That Could Be Expected to Impact Staff Resources Into Fiscal Years 2000 & 2001,in Response to Administrative Ltr 99-02 NPL-99-0388, Forwards MORs for June 1999 & Revised MORs for May 1999 for Pbnps,Units 1 & 21999-07-0707 July 1999 Forwards MORs for June 1999 & Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0381, Submits Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants. GL 98-01 Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML20196J4161999-06-30030 June 1999 Discusses Relief Requests Submitted by Wisconsin Electric on 980930 for Pump & Valve Inservice Testing Program,Rev 5. Safety Evaluation Authorizing Relief Requests VRR-01,VRR-02, PRR-01 & ROJ-16 Encl NPL-99-0379, Documents Telcon with Hg Ashar of NRC Re Licensee Intentions & Basis for Reselection of Control Tendons in Pbnps Containment Structures.Plants Are Currently Completing 28th Year Tendon Surveillance During Summer of 19991999-06-29029 June 1999 Documents Telcon with Hg Ashar of NRC Re Licensee Intentions & Basis for Reselection of Control Tendons in Pbnps Containment Structures.Plants Are Currently Completing 28th Year Tendon Surveillance During Summer of 1999 NPL-99-0376, Forwards Errata to Pbnp 1998 Annual Monitoring Rept, Originally Submitted by Ltr Dtd 990427.List of Corrections, Provided1999-06-28028 June 1999 Forwards Errata to Pbnp 1998 Annual Monitoring Rept, Originally Submitted by Ltr Dtd 990427.List of Corrections, Provided NPL-99-0353, Forwards June 1999 Rev to FSAR for Point Beach Nuclear Plant,Units 1 & 2, IAW Requirements of 10CFR50.71(e).Each Package Contains Revised FSAR Pages That Are to Be Inserted IAW Instructions1999-06-23023 June 1999 Forwards June 1999 Rev to FSAR for Point Beach Nuclear Plant,Units 1 & 2, IAW Requirements of 10CFR50.71(e).Each Package Contains Revised FSAR Pages That Are to Be Inserted IAW Instructions ML20196D4931999-06-18018 June 1999 Forwards Insp Repts 50-266/99-08 & 50-301/99-08 on 990411- 0527.No Violations Noted.Operator Crew Response to Equipment Induced Challenges Generally Good.Handling of Steam Plume in Unit 1 Turbine Bldg Particularly Good ML20195J9471999-06-16016 June 1999 Discusses Ltr from NRC ,re Arrangements Made to Finalized Initial Licensed Operator Exam to Be Administered at Point Beach Nuclear Plant During Week of 990726 ML20196A2931999-06-16016 June 1999 Ack Receipt of Transmitting Changes to Listed Sections of Point Beach Nuclear Plant Security Plan & ISFSI Security Plan,Submitted IAW 10CFR50.54(p).No NRC Approval Is Required Since Changes Do Not Decrease Effectiveness ML20195J9251999-06-14014 June 1999 Discusses 990610 Telcon Between Wp Walker & D Mcneil Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at Point Beach Nuclear Power Plant for Week of 990816 05000266/LER-1999-005, Forwards LER 99-005-00,re Failure of Shell of 4B FW Heater Which Resulted in Significant Steam Leak & Manual Trip. New Commitments within Rept Are Indicated in Italics1999-06-11011 June 1999 Forwards LER 99-005-00,re Failure of Shell of 4B FW Heater Which Resulted in Significant Steam Leak & Manual Trip. New Commitments within Rept Are Indicated in Italics NPL-99-0336, Forwards Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1, IAW ASME Section Xi,Subsection IWA-62301999-06-10010 June 1999 Forwards Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1, IAW ASME Section Xi,Subsection IWA-6230 NPL-99-0330, Forwards Revs to Pbnp Security Plan Sections 2.1,2.4,3.1, Figures A,D & T & Pbnp ISFSI Security Plan Section 2.0, Dtd 990604.Plans Withheld1999-06-0404 June 1999 Forwards Revs to Pbnp Security Plan Sections 2.1,2.4,3.1, Figures A,D & T & Pbnp ISFSI Security Plan Section 2.0, Dtd 990604.Plans Withheld 05000301/LER-1999-003, Forwards LER 99-003-00 for Point Beach Nuclear Plant,Unit 2. Rept Is Provided in Accordance with 10CFR50.73(a)(2)(i)(B), as Any Operation or Condition Prohibited by Plant Tech Specs1999-05-28028 May 1999 Forwards LER 99-003-00 for Point Beach Nuclear Plant,Unit 2. Rept Is Provided in Accordance with 10CFR50.73(a)(2)(i)(B), as Any Operation or Condition Prohibited by Plant Tech Specs NPL-99-0319, Provides Main Control Board Wiring Separation Project Status Update Rept for Pbnps,Units 1 & 21999-05-28028 May 1999 Provides Main Control Board Wiring Separation Project Status Update Rept for Pbnps,Units 1 & 2 ML20206T3691999-05-17017 May 1999 Ltr Contract,Task Order 242 Entitled, Review Point Beach 1 & 2 Conversion of Current TS for Electrical Power Systems to Improved TS Based on Standard TS, Under Contract NRC-03-95-026 ML20206N5561999-05-13013 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Cm Craig Will Be Section Chief for Point Beach Npp.Organization Chart Encl ML20206P2551999-05-12012 May 1999 Forwards Handout Provided to NRC by Wisconsin Electric at 990504 Meeting Which Discussed Several Recent Operational Issues & Results of Recent Improvement Initiatives in Engineering ML20206N5331999-05-12012 May 1999 Forwards RAI Re & Suppl by Oral Presentation During 980604 Meeting,Requesting Amend for Plant,Units 1 & 2 to Revise TSs 15.3.12 & 15.4.11 ML20196F3211999-05-11011 May 1999 Requests Proprietary WCAP-14787, W Revised Thermal Design Procedure Instrument Uncertainty Methodology for Wepc Point Beach Units 1 & 2 (Fuel Upgrade & Uprate to 1656 Mwt-NSSS Power), Be Withheld from Public Disclosure ML20206K0391999-05-0707 May 1999 Forwards Insp Repts 50-266/99-06 & 50-301/99-06 on 990223- 0410.Ten Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy 1999-09-08
[Table view] Category:NRC TO UTILITY
MONTHYEARML20062F1301990-11-14014 November 1990 Forwards SE Supporting Util Responses to Generic Ltr 83-28, Item 1.2 Re post-trip Review - Data & Info Capability ML20058G2701990-11-0505 November 1990 Advises That Requalification Program Evaluation Scheduled for Wk of 910311.Facility Should Furnish Approved Items Listed in Ref Matl Requirements. One Employee Should Be Designated as Member of Joint NRC-facility Exam Team ML20058H1001990-10-30030 October 1990 Forwards Safety Insp Repts 50-266/90-19 & 50-301/90-19 on 900905-1015 & Notice of Violation ML20058D7831990-10-30030 October 1990 Forwards Initial SALP Repts 50-266/90-01 & 50-301/90-01 Covering Apr 1989 to Aug 1990.Category 1 Rating Sustained for Maint/Surveillance & Plant Operations Performance Improved from Category 2 to Category 1 ML20058E7141990-10-30030 October 1990 Forwards Exam Forms & Answer Keys,Grading Results & Individual Answer Sheets for Each Applicant ML20059P0761990-10-16016 October 1990 Confirms Plans for 901025 Mgt Meeting in Milwaukee,Wi to Discuss Plant Activities & Other Items of Mutual Interest ML20059N9791990-10-12012 October 1990 Forwards Enforcement Conference Insp Repts 50-266/90-21 & 50-301/90-21 on 901004 ML20059M0971990-09-27027 September 1990 Forwards Safety Insp Repts 50-266/90-18 & 50-301/90-18 on 900820-24.Violations Noted.Licensee Will Be Notified by Separate Correspondence Re Enforcement Actions ML20059M2101990-09-25025 September 1990 Forwards Info Re Generic Fundamentals Exam Section of Operator Licensing Written Exams to Be Administered on 901010,including Map of Area Where Exams Will Be Taken, Preliminary Instructions for Exam & Equation Sheet ML20059M0411990-09-25025 September 1990 Identifies No short-term Safety Concerns Re Thermal Stratification,Per 890531 Response to NRC Bulletin 88-011, Presurizer Surge Line Thermal Stratification ML20059J7541990-09-12012 September 1990 Forwards Requalification Exam Rept 50-266/OL-90-02 Administered on 900823 ML20059B6391990-08-20020 August 1990 Forwards Safety Insp Repts 50-266/90-17 & 50-301/90-17 on 900813-17.No Violations Noted ML20058N2071990-08-10010 August 1990 Advises That 900619 Changes to QA Program Description Meet 10CFR50,App B Requirements & Acceptable ML20058Q2411990-08-10010 August 1990 Forwards Safety Insp Repts 50-266/90-14 & 50-301/90-14 on 900616-0731.No Violations Noted ML20058M6141990-08-0707 August 1990 Forwards Sample Registration Ltr for 901010 Generic Fundamentals Section of Written Operator Licensing Exam. Registration Ltr Listing Names of Candidates Taking Exam Should Be Submitted to Region 30 Days Prior to Exam Date ML20055H2131990-07-20020 July 1990 Confirms Plans for 900724 Meeting in Glen Ellyn,Il to Discuss Plant Activities & Items of Mutual Interest ML20055G2811990-07-13013 July 1990 Forwards Safeguards Insp Repts 50-266/90-13 & 50-301/90-13 on 900618-22 & Notice of Violation.Notice of Violation Withheld (Ref 10CFR73.21) ML20055D0581990-06-28028 June 1990 Confirms Plans for Mgt Meeting on 900702 in Two Rivers,Wi to Discuss Plant Activities & Other Items of Mutual Interest ML20055D1831990-06-26026 June 1990 Forwards Safety Insp Repts 50-266/90-10 & 50-301/90-10 on 900501-0615.No Violations Noted ML20059M8891990-06-13013 June 1990 Forwards NRC Performance Indicators for First Quarter 1990. W/O Encl ML20055J3731990-06-0808 June 1990 Forwards Enforcement Conference Repts 50-266/90-12 & 50-301/90-12 on 900525 & Notice of Violation.Nrc Plans to Increase Insp Frequency in Order to Better Evaluate Continued Performance in Radiation Protection Area ML20247P6431989-09-18018 September 1989 Forwards Safety Evaluation Supporting Util 860724 Request to Qualify Containment Liner Leak Chase Channels as Integral Part of Containment Liner Plate ML20247K9181989-09-15015 September 1989 Forwards Safety Insp Repts 50-266/89-24 & 50-301/89-23 on 890716-0831.No Violations Noted ML20247N6831989-09-14014 September 1989 Advises That Rev 26 to Emergency Plan 4.0,Rev 31 to Emergency Plan 5.0 & Rev 29 to Emergency Plan 6.0 Consistent W/Requirements of 10CFR50.54(q) & Acceptable ML20247K4461989-09-14014 September 1989 Confirms Plans to Conduct Mgt Meeting Between J Zach & Eg Greenman at Site on 890922 to Discuss Routine Events of Interest ML20247G0091989-09-13013 September 1989 Forwards Safety Insp Repts 50-266/89-26 & 50-301/89-25 on 890828-0901.No Violations Noted IR 05000266/19890211989-08-30030 August 1989 Forwards Safety Insp Repts 50-266/89-21 & 50-301/89-21 on 890725-0824.Violations Noted ML20246L3221989-08-29029 August 1989 Confirms Plans to Conduct Enforcement Conference on 890906 in Glen Ellyn,Il to Discuss post-accident Sampling Capability at Plant,Per J Zach & R Greger Discussion ML20246C4731989-08-17017 August 1989 Confirms Mgt Meeting Between J Zach & Eg Greenman at Plant on 890824 to Discuss Routine Events of Interest as Agreed at SALP 7 Meeting ML20245L6231989-08-14014 August 1989 Forwards Safety Insp Repts 50-266/89-23 & 50-301/89-22 on 890710-14 & 0803.No Violations Noted ML20245J8961989-08-0808 August 1989 Ack Receipt of Providing Addl Info Re Changes to 890126 Plant Security Plan & Requests Addl Info.Response Must Be Provided within 30 Days from Receipt of Ltr ML20248D1911989-08-0404 August 1989 Forwards Safety Insp Repts 50-266/89-19 & 50-301/89-18 on 890619-30.No Violation Issued for Violation Re Failure to Provide Control Over Emergency Operating Procedures Since Util Identified Concern in Recent Internal Audit ML20247P6721989-07-31031 July 1989 Confirms Dates of 890815-18 for Review of Backup Documentation Supporting Response to Station Blackout Rule, 10CFR50.63,for plant.NUMARC-8700 Guidelines Will Be Used to Evaluate Station Blackout Assessment ML20247R8471989-07-28028 July 1989 Forwards Safety Insp Repts 50-266/89-20 & 50-301/89-19 on 890601-0715.Some Issues Unresolved ML20247L3411989-07-27027 July 1989 Advises That 890630 Revs to Section 1.8 of QA Program Consistent W/Provisions of App B to 10CFR50 & Acceptable ML20247H4951989-07-24024 July 1989 Forwards App to SALP 7 Repts 50-266/89-01 & 50-301/89-01 for Oct 1987 Through Mar 1989.Conclusions Presented in App Based on in-depth Discussions During 890627 Meeting & Review of Util of Repsonse ML20246M9431989-07-14014 July 1989 Forwards Exam Rept 50-266/OL-89-03 of Exam Administered During Wk of 890626 ML20246K6341989-07-12012 July 1989 Provides Comments on Util Response to Generic Ltr 88-17 W/ Respect to Expeditious Actions for Loss of DHR for Plants. Response Appears to Meet Intent of Generic Ltr However,Util Should Consider Observations to Assure Actions Adequate ML20246G9951989-07-0707 July 1989 Forwards Safety Evaluation Accepting Util Response to NRC Bulletin 88-002, Rapidly Propagating Fatigue Cracks in Steam Generator Tubes ML20246G9331989-07-0707 July 1989 Forwards Exam Repts 50-266/OL-89-04 & 50-301/OL-89-04 Administered During Wk of 890626.Operator May Be Returned to Licensed Duties ML20245G7571989-06-21021 June 1989 Forwards Safety Insp Repts 50-266/89-15 & 50-301/89-14 on 890401-0531 & Notice of Violation ML20245G9081989-06-21021 June 1989 Forwards Safety Insp Repts 50-266/89-13 & 50-301/89-12 on 890522-25 & 0614.No Violations Noted.Concerns Raised Re Exercise Weaknesses from 890315 Exercise & Training Program. Corrective Actions Requested within 45 Days ML20245B0261989-06-14014 June 1989 Forwards Safety Evaluation Accepting Licensee 831107 & 860411 Responses to Generic Ltr 83-28,Item 4.5.3, Reactor Trip Sys Reliability - On-Line Functional Testing of Reactor Trip Sys ML20244B6801989-06-0707 June 1989 Confirms Discussion Re Plans for Meeting on 890627 Onsite to Present SALP 7 Rept for Plant ML20244C1671989-06-0606 June 1989 Forwards Safety Insp Repts 50-266/89-12 & 50-301/89-11 on 890425-28 & 0510-12.No Violations Noted IR 05000266/19890161989-05-31031 May 1989 Forwards Safety Insp Repts 50-266/89-16 & 50-301/89-15 on 890301-0512.Violations Noted.Util Will Be Notified by Separate Correspondence of NRC Decision Re Enforcement Action Based on Findings ML20244C0161989-05-26026 May 1989 Forwards Safeguards Insp Repts 50-266/89-17 & 50-301/89-16 on 890509-12 & Notice of Violation.Notice of Violation & Rept Details Withheld (Ref 10CFR73.21) ML20247K3741989-05-25025 May 1989 Informs That Emergency Operating Procedures Insp Will Be Conducted on 890619-30.Preliminary Insp Schedule Encl. Required Documents,Per Encl 1,requested by 890605 ML20247N5201989-05-24024 May 1989 Forwards Answer Key for NRC Requalification Makeup Exam Re Exam Repts 50-266/OL-89-02 & 50-301/OL-89-02 ML20247K4591989-05-24024 May 1989 Confirms 890602 Enforcement Conference in Glen Ellyn,Il to Discuss Recent Issues Re Station Batteries 1990-09-27
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217A5911999-09-30030 September 1999 Advises of NRC Plans for Future Insp Activities at Facility for Licensee to Have Opportunity to Prepare for Insps & to Provide NRC with Feedback on Any Planned Insps Which May Conflict with Plant Activities.Plant Issues Matrix Encl ML20212J7431999-09-30030 September 1999 Forwards Insp Repts 50-266/99-15 & 50-301/99-15 on 990830- 0903.No Violations Noted.Inspectors Concluded That Util Licensed Operator Requalification Training Program Satisfactorily Implemented ML20212K7651999-09-29029 September 1999 Forwards Insp Repts 50-266/99-13 & 50-301/99-13 on 990714-0830.No Violations Noted.Operators Responded Well to Problems with Unit 1 Instrument Air Leak & Unit 2 Turbine Governor Valve Position Fluctuation ML20212D5771999-09-15015 September 1999 Discusses Review of Response to GL 88-20,suppl 4,requesting All Licensees to Perform Ipeee.Ser,Ter & Supplemental TER Encl ML20211Q6451999-09-0808 September 1999 Forwards Operator Licensing Exam Repts 50-266/99-301OL & 50-301/99-301OL for Exams Conducted on 990726-0802 at Point Beach Npp.All Nine Applicants Passed All Sections of Exam ML20211Q4171999-09-0606 September 1999 Responds to VA Kaminskas by Informing That NRC Tentatively Scheduled Initial Licensing Exam for Operator License Applicants During Weeks of 001016 & 23.Validation of Exam Will Occur at Station During Wk of 000925 ML20211K5261999-08-31031 August 1999 Forwards Insp Repts 50-266/99-14 & 50-301/99-14 on 990726- 30.Areas Examined within Secutity Program Identified in Rept.No Violations Noted ML20211F6941999-08-27027 August 1999 Provides Individual Exam Results for Applicants That Took Initial License Exam in July & August of 1999.Completed ES-501-2,copy of Each Individual License,Ol Exam Rept, ES-303-1,ES-303-2 & ES-401-8 Encl.Without Encl ML20211F1501999-08-24024 August 1999 Submits Summary of Meeting Held on 990729,in Region III Office with Util Re Proposed Revs to Plant Emergency Action Level Criteria Used in Classifying Emergencies & Results of Recent Improvement Initiatives in Emergency Preparedness ML20211E8791999-08-24024 August 1999 Discusses Completion of Licensing Action for GL 96-01, Testing of Safety-Related Logic Circuits, for Point Beach Nuclear Power Plant,Units 1 & 2.Licensees Provided Requested Info & Responses Required by GL 96-01 ML20210K5221999-08-0404 August 1999 Discusses Point Beach Nuclear Plant,Units 1 & 2 Response to Request for Info in GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity ML20210L9141999-08-0404 August 1999 Informs That Versions of Info Re WCAP-14787,submitted in 990622 Application for Amend,Marked Proprietary,Will Be Withheld from Public Disclosure,Per 10CFR2.790(b)(5) & Section 103(b) of AEA of 1954,as Amended ML20210G6011999-07-30030 July 1999 Discusses 990415 Complaint OSHA Received from Employee of Wisconsin Electric Power Co Alleging That Employee Received Lower Performance Appraisal for 1998 Because Employee Raised Safety Concerns While Performing Duties at Point Beach ML20210H0211999-07-28028 July 1999 Forwards Insp Repts 50-266/99-09 & 50-301/99-09 on 990528-0713.Two Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy ML20210G2441999-07-26026 July 1999 Discusses 990714 Meeting with PRA Staff to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PRA Staff ML20209H5471999-07-14014 July 1999 Forwards Insp Repts 50-266/99-12 & 50-301/99-12 on 990614-18.One Violation Noted,But Being Treated as non-cited violation.Long-term MOV Program Not Sufficiently Established to close-out NRC Review of Program,Per GL 89-10 ML20196J4161999-06-30030 June 1999 Discusses Relief Requests Submitted by Wisconsin Electric on 980930 for Pump & Valve Inservice Testing Program,Rev 5. Safety Evaluation Authorizing Relief Requests VRR-01,VRR-02, PRR-01 & ROJ-16 Encl ML20196D4931999-06-18018 June 1999 Forwards Insp Repts 50-266/99-08 & 50-301/99-08 on 990411- 0527.No Violations Noted.Operator Crew Response to Equipment Induced Challenges Generally Good.Handling of Steam Plume in Unit 1 Turbine Bldg Particularly Good ML20196A2931999-06-16016 June 1999 Ack Receipt of Transmitting Changes to Listed Sections of Point Beach Nuclear Plant Security Plan & ISFSI Security Plan,Submitted IAW 10CFR50.54(p).No NRC Approval Is Required Since Changes Do Not Decrease Effectiveness ML20195J9471999-06-16016 June 1999 Discusses Ltr from NRC ,re Arrangements Made to Finalized Initial Licensed Operator Exam to Be Administered at Point Beach Nuclear Plant During Week of 990726 ML20195J9251999-06-14014 June 1999 Discusses 990610 Telcon Between Wp Walker & D Mcneil Re Arrangements for NRC to Inspect Licensed Operator Requalification Program at Point Beach Nuclear Power Plant for Week of 990816 ML20206T3691999-05-17017 May 1999 Ltr Contract,Task Order 242 Entitled, Review Point Beach 1 & 2 Conversion of Current TS for Electrical Power Systems to Improved TS Based on Standard TS, Under Contract NRC-03-95-026 ML20206N5561999-05-13013 May 1999 Informs That NRC Office of Nuclear Reactor Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Cm Craig Will Be Section Chief for Point Beach Npp.Organization Chart Encl ML20206N5331999-05-12012 May 1999 Forwards RAI Re & Suppl by Oral Presentation During 980604 Meeting,Requesting Amend for Plant,Units 1 & 2 to Revise TSs 15.3.12 & 15.4.11 ML20206P2551999-05-12012 May 1999 Forwards Handout Provided to NRC by Wisconsin Electric at 990504 Meeting Which Discussed Several Recent Operational Issues & Results of Recent Improvement Initiatives in Engineering ML20206K0391999-05-0707 May 1999 Forwards Insp Repts 50-266/99-06 & 50-301/99-06 on 990223- 0410.Ten Violations of NRC Requirements Occurred & Being Treated as non-cited Violations,Consistent with App C of Enforcement Policy IR 05000266/19990041999-04-28028 April 1999 Discusses Insp Rept 50-266/99-04 on 990105-0222 & Forwards NOV Re Failure to Ack Validity of Temp Alarm & Appreciate Significance of Low Temp Readings for Unit 1 SI Pumps Min Flow Line ML20206B8121999-04-23023 April 1999 Forwards FEMA Evaluation Rept for 981103 Emergency Preparedness Exercise at Point Beach Nuclear Power Plant. Deficiency Identified for Manitowoc County as Result of Exercise.County Corrected Deficiency Immediately ML20205S7041999-04-20020 April 1999 Forwards Insp Repts 50-266/99-05 & 50-301/99-05 on 990222-0312.One Violation Noted & Being Treated as Non-Cited Violation.Expresses Concern Re Timeliness of C/As ML20205R4651999-04-19019 April 1999 Forwards Insp Repts 50-266/99-10 & 50-301/99-10 on 990329- 0401.No Violations Noted.During Insp NRC Observation of Licensee Activities Showed Emergency Preparedness Program to Be Adequately Implemented ML20205R6081999-04-19019 April 1999 Confirms of NRC Routine Mgt 990504 Meeting in Lisle,Il to Discuss Progress in Implementation of Improvement Initiatives in Engineering Area,As Well as to Discuss Challenges Faced by Operators ML20205P0311999-04-13013 April 1999 Refers to Various Changes Received by Region III in Jan 1999 to Portions of Point Beach NPP Emergency Plan.Informs That NRC Approval Not Required Based on Determinations That Changes Do Not Decrease Effectiveness of Emergency Plan ML20205N4221999-04-12012 April 1999 Discusses 990326 Predecisional Enforcement Conference with Util Re Apparent Violation Concerning Operator Response to Low Temp Alarm for Minimum Flow Recirculation Line for Unit 1 Safety Injection Sys.Handouts Provided by Util Encl ML20205C4701999-03-26026 March 1999 Discusses Review of Various Changes to Portions of Plant Emergency Plan.Informs That Revision Was Submitted Under Provisions of 10CFR50.54(q) ML20196K8731999-03-26026 March 1999 Advises of Licensee Planned Insp Effort Resulting from Plant Ppr.Plant Issues Matrix & Insp Plan for Next 6 Months Encl ML20204E5561999-03-16016 March 1999 Forwards Insp Repts 50-266/99-07 & 50-301/99-07 on 990216-19.No Violations Noted.Three Weaknesses Re Chemistry Program Were Identified ML20204D8161999-03-12012 March 1999 Forwards Insp Rept 50-266/99-04 on 990105-0222.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation,Consistent with App C of Enforcement Policy ML20207L9191999-03-11011 March 1999 Discusses from Util Informing NRC That Bases References for TS 15.4.4 Revised to Correct References to Point Beach Nuclear Plant FSAR Related to Reactor Containment Design.Revised Bases Page 15.4.4-7 Encl ML20207L1161999-03-10010 March 1999 Forwards Insp Repts 50-266/99-02 & 50-301/99-02 on 990105- 0222 & Nov.One Violation Associated with Program for Implementing Abnormal & Eops.Other Two Violations non-cited Violations ML20207H8661999-03-0808 March 1999 Ack Receipt of ,Which Transmitted Changes to Pbnp Security Sections 1.2,1.3,2.1,2.4,6.1,B-2.0,B-3.0 & Figure T,Per 10CFR50.54(p).No NRC Approval Is Required,Since Util Determined That Changes Do Not Decrease Effectiveness ML20207D6661999-02-22022 February 1999 Forwards Assessment of Design of Restraints on Main Steam Piping & Primary Loop Auxiliary Piping Systems at Point Beach Nuclear Plant.Staff Concludes That WE Unable to Retrieve Original Analyses That May Have Been Performed ML20203F2541999-02-10010 February 1999 Informs That Beginning 990216,DE Hills Will Be Chief of Operations Branch Which Includes Operator Licensing Function ML20202H6601999-02-0101 February 1999 Discusses Evaluation of Wisconsin Electric Power Co Response to NRC GL 97-05, Steam Generator Tube Insp Techniques ML20206U2981999-02-0101 February 1999 Informs That by 980811 & 1223 Ltrs,Nrc Responded to WOG Positions Re Corrective Actions to Address Generic Aspects of part-length Control Rod Drive Mechanism Housing Issue Resulting from Leak at Prairie Island,Unit 2 on 980123 ML20202G5321999-02-0101 February 1999 Forwards Insp Repts 50-266/99-03 & 50-301/99-03 on 990111-15.No Violations Noted.Cooperation,Communication & Effectiveness of Security & Maint Staff to Ensure Equipment Effectiveness Has Been Successful ML20199H5491999-01-15015 January 1999 Forwards Insp Repts 50-266/98-21 & 50-301/98-21 on 981121- 990104 & Notice of Violation.Violation Being Cited Because of Repetitive Nature & That Violation Could Reasonably Have Been Prevented by C/A for Previous Finding ML20206R8891999-01-13013 January 1999 Forwards SER Accepting Util 981116 & 30 Proposed Revs to Nuclear Quality Assurance Program Implemented at Point Beach Nuclear Plant Units 1 & 2 ML20199D7751999-01-0808 January 1999 Documents 990105 Telcon Issuing Notice of Enforcement Discrection for Wisconsin Electric Re Point Beach,Unit 1 ML20198K6911998-12-24024 December 1998 Forwards Insp Repts 50-266/98-22 & 50-301/98-22 on 981208-10.No Violations Noted.Concludes That Licensee Carried Out Properly Addressed Findings of Maint Rule Baseline Insp ML20198J6061998-12-22022 December 1998 Discusses Plant,Units 1 & 2 Licensed Operator Staffing Requirements 1999-09-08
[Table view] |
Text
. _ . . .
September 25, 1990 Docket Nos. 50-266 DISTRIBUTION:
and 50-301 Docket: Files! NRC & Local PDRs POIII-3 r/f DCrutchfield JZwolinski JHannon RSamworth PKreutzer Mr. C. W. Fay, Vice President- OGC-WF1 ACRS(10)
Nuclear Power Department EJordan PDIII-3 Gray Wisconsin Electric Power Company 231 West Michigan Street, Room 308 Milwaukee, Wisconsin 53201
Dear Mr. Fay:
SUBJECT:
NRC BULLETIN N 98-11. " PRESSURIZER SURGE LINE THERMAL STRATIFICATION"
- EVALUATION Ot h.STINGHOUSE DWNERS GROUP BOUNDING ANALYSIS (TAC NOS. 72155 /cHD 72156)
By letter dated May 31, 1989, Wisconsin Electric Power Company responded to
/
Item 1.b of NRC Bulletin No. 88-11. " Pressurizer Surge Line Thermal Stratifi-cation." The letter stated that a bounding analysis performed by the Westing-house Owners Group (WOG) which is applicable to the Point Beach Nuclear. Plant Units' I and 2 indicated that the pressurizer surge line (PSL) may not satisfy the ASME Section III Code criteria for the life of the plant, taking into account the effects of thermal stratification. The analysis did, however, state that the integrity of the PSL was adequate to justify continued operation of the facility for several years.
The staff has completed its review of the WOG bounding analysis and concludes that there are no short-term safety concerns associated with the thermal stratification effects for a duration of ten additional heatup/cooldown cycles of continued plant operation. A copy of the evaluation that was sent to the WOG is enclosed for your information.
The staff will assess the conformance of the PSL to applicable Codes and regulatory requirements for 40 year plant life when the WOG report regarding Item 1.d of the Bulletin is submitted.
Sincerely, OriginalSigned By:
Robert B. Samworth, Project Manager Project Directorate III-3 Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated.
cc w/ enclosure:
See next page DOCUMENT NAME: 0 W si h215s But. 88-11 Of fice: PD/ D II-3 n
LA/P4 I-3 Surname: 'PXpeu zer / /g M/P0lII-3 {
RSamworth/tg JHannon f()
.Date: t) /j3 /90 7/tfl90 9010030002 900925 f/)f/90 i\\
PDR ADOCK 05000266 \'
Q PDC
l,,
E
. .' September 25, 1990 Docket Nos. 50-266 DISTRIBUTION:
T. and 50-301 Docket Files NRC & Local PDRs 9 PDIll-3 r/f DCrutchfield JZwolinski JHannon RSamworth PKreutzer Mr.-C. W. Fay, Vice President OGC-WF1 ACRS(10)
Nuclear Power Department EJordan PDIII-3 Gray Wisconsin Electric Power Company 231 West Michigan Street, Room 308 Milwaukee, Wisconsin 53201
Dear Mr. Fay:
SUBJECT:
NRC BULLETIN NO. 88-11. " PRESSURIZER SURGE LINE THERMAL STRATIFICATION"
- EVALUATION OF WESTINGHOUSE OWNERS GROUP BOUNDING ANALYSIS (TAC NOS 72155 AND 72156)
By letter dated May 31, 1989, Wisconsin Electric Power Company responded to Item 1.b of NRC Bulletin No. 88-11. " Pressurizer Surge Line Thermal Stratifi-cation." The letter stated that a bounding analysis performed by the Westing-house Owners Group (WOG) which is applicable to the Point Beach Nuclear Plant Units I and 2 indicated that the pressurizer surge line (PSL) may not satisfy the ASME Section III Code criteria foe the life of the plant, taking inte account the effects of thermal stratification. The analysis did, however, state that the integrity of the PSL was adequate to just'.fy continued operation of the facility for several years.
Tha staff has completed its review of the WOG bounding analysis and concludes that there are no short-term safety concerns associated with the. thermal 1 stratification effects for a duration of ten additional heatup/cooldown cycles 1 of continued plant operation. A copy of the evaluation that was sent to the .
WOG is enclosed for your information.
- i The staff will-assess the conformance of the PSL to-applicable Codes and regulatory requirements for 40 year plant life when the WOG report regarding l Item 1.d of the Bulletin is submitted. 1 1
Sincerely, OrbinalSigned By: j Robert B. Samworth, Project Manager Project Directorate III-3 Division of Reactor Projects - III, IV,.V and Special Projects Office of Nuclear' Reactor Regulation
Enclosure:
As stated cc w/ enclosure: b See'next page DOCUMENT NAME: 72155/72156 BUL. 88-11 Office: LA/PQI41-3 M/PDIII-3 PD/ DIII-3 i Surname: 'PKr6uiz'er RSamworth/tg JHannon Date: - $ /j a /90 7/t[/90 p/Jf/90 i
Mr. C. W. Fay: Point Beach Nuclear Plant Wisconsin' Electric Power Company Unitt 1 and 2 cc: Ernest L. Blake,' Jr.
Shaw, Pittman,- Potts ant _Trowt ridge 2300 N: Street, N.W. i Washington, DC 20037 Mr. Gregory J. Maxfield, Manager Point Beach Nuclear Plant Wisconsin Electric Power Company 6610 NL: lear Road Two Rivers,-Wisconsin 54241 Town Chairman Town of Two Creeks Route 3 Two Rivers, Wisconsin 54241- _i Chairman 1
Public Service Commission of Wisconsin j Hills Farms State Office Building i Madison, Wisconsin 53702 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Office of Executive Director !
for Operations 799 Roosevelt Road Glen Ellyn, Illinois 60137 i
Resident Inspector's Office U.S. Nuclear Regulatory Commission l 6612 Nuclear Road ,
1 Two Rivers, Wisconsin 54241-l 1
~
i h.,,..
y l
'f Page 1 of 8 j ENCLOSURE 1 NRR REVIEW OF WESTINGHOUSE OWNERS GROUP (WOG)
BOUNDING EVALUATInN FOR PRESSURIZER SURGE LINE THERMAL STRATIFICATION WCAP-12277 4
INTRODUCTION The pressurizer aurge line (PSL) in the pressurized water reactors (PWRs),
is a stainless steel pipe, connecting the bottom of the pressurizer vessel to the hot leg of the coolant loop. The out flow of the pressurizer water ;
I is generally warmer than the hot leg flow. Such temperature differential !
(AT) varies with plant operation activities and can be as high as 320*F ;
during the initial plant heat up. Thermal. stratification is the separation of_-cold flow stream in the horizontal portion of the-PSL resulting in temperature difference at the top and bottom of the pipe.
Since thermal stratification is the direct result of the differences in-densities between the pressurizer water and the hot leg water, the !
potential for_ stratification is increased as system AT increases and as the insurge or outsurge flow decreases. Stratification'in PSL was found.
,: recently and confirmed by data measured from seural PWR plants.
i, Original design analyses did not include any stratified flow loading conditions. Instead it assumed complete sweep of-fluid along the line during insurges or outsurges resulting in uniform _ thermal loading at any particular piping location. Such analyses did not-reflect PSL actual-thermal condition and potentially may overlook undesirable line deflection ;
e and its actual high stresses may exceed design limits.- In addition,;the striping phenomenon, which is the oscillation of_the hot and cold '
stratified boundary, may induce high cycle fat 1gue to the inner pipe wall and needs also to be analyzed. Thus assessment of stratification effects on I'SL _is necessary to ensure piping integrity and ASME Code Section III ,
conformance.
f
~
9$w
w ,
. j Page 2 of 8 1
STAFF EVALUATION Since stratification in PSL is a generic concern to all PWRs an NRC Information Notice No 88-80 was issued on October 7. 1988, and then an NRC Bulletin 88-11 for the same concern was also issued on December 20, 1988.
-l Westinghouse, on behalf of the Westinghouse Owners Group (WOG), has performed a generic bounding evaluation report WCAP-12277 (Reference 1).
This report provides the technical basis for the generic justification for .i continued operation (JCO), for each of the WOG plants and constitutes j compliance with the requested action 1.b of Bulletin 88-11. Plants which have discovered any gross discernable distress during performance of the a walkdown, as requested by Bulletin's action 1.a. should report findings '
and specify corrective actions in their JCO, in addition to that provided_
in this report. The following is,the staff's evaluation of the Westing- :
house's efforts and information provided in the report.
l Prior to:the issuance of the Bulletin, WOG implemented a program to address-the issue of the surge line thermal stratification. The program consisted of plant-specific analysis covering five plants and a review of' thermal monitoring data from eight plants. Westinghouse had instrumented:
PSLs and collected data for verifying stratification conditions. The thermal monitoring data obtained considered outside wall temperatures at i different location around the pipe and along-the axis of the pipe vs.
time, vertical end lateral displacements at various locations along the ,
pipe vs. time, and various plant parameters vs. time, from existing plant instrumentation and control sensors. In some cases the data were based l
-not only on plant heatup but also on operation and plant cooldown conditions. The specific analyses included redefinition of revised thermal ~ transients considering stratification effects and evaluation of pipe stress and fatigue usage factors. The overall analytical approach (+
used inbyallthe detail these NRCc:.ses staff.have been consistent and has been reviewed in '
The evaluation concluded that a single bounding analysis was not feasible.
Due-to the variations in design, Westinghouse could not-define a single envelope case to justify the 40 year life of the surge line, therefore a t bounding evaluation was performed to justify continued operation for at i least ten (10) additional heatup/cooldown cycles.
l The bounding-evaluation is essentially a demonstration of the applicability
[ of the plant specific and the monitoring results to the remaining WOG .
plants. All plant-specific analyses completed to-date, have demonstrated-a 40 year life of the surge line !
)
.Two sets of parameters were defined.
1 L
l a) Pararreters which affect severity of thermal stratifica- '
tion (i.e thermal hydraulic and operational effecte)
(
Page 3 of 8 b) Parameters which affect PSL response to thermal strati-fication (i.e. structural effects).
. The range of the parameters for the plants analyzed and/or monitored was
- used to establish the bounding criteria and to enable an individual plant by plant comparison.
To expand the data base for a wider range of PSL configurations, Westinghouse recommended additional plant monitoring based on plant similarities (grouping), and surge line physical, design and operational parameters of all 55 domestic Westinghouse plants. Plants with parameters not within the range of the current monitoring database were recommended for additional monitoring.- Ten (10) different groups were identified for the 55 domestic Westinghouse plants for data collection, review and analysis of the pertinent thermal hydraulic, operational and structural parameters. Currently 22 separate monitoring programs are either completed, in process, or being planned. About 40% of the plants falling in one group with the remaining 60% of the Westinghouse PWR's divided among the nine groups. When this program is completed, it will provide sufficient monitoring data with at.least one plant monitored in each group.
Parameters which have a significant effect from a thermal hydraulic stand point are pipe inside diameter vnd slope. Plants falling outside the resulting bounding criteria of p!pe ir. side diameter of 7" to 15.4" and pipe average slope of O' to 1.44' degrees, were recommended for monitoring.
The range of the parameters was expanded by 1 20% in determining a bounding criteria to which other plants were compared. It was concluded that a bounding evaluation which is based on enveloping techniques, will not have a significant effect on the thermohydraulic behavior dte to a i 20% change in pipe size and slope. The staff. agrees with Westinghoc e's efforts and methodology for monitoring, updating and assessing PSL for the stratification condition.
Thermal hydraulic evaluations using higher slope and smaller diameter pipe are expected to reduce the stratification effects. Eleven plants have an average slope higher and one plant has a pipe size smaller than that allowed by the criteria.
Some parameters judged to be relatively significant for the structural effects are:
Entrance angle to the hot leg nozzle Mid line riser 1
Length of the longest straight run of pipe Type of in-line component Presence of whip restraints Number of vertical rigid supports
It'
., y .-
i 4- J Page 4 of 8 Two plants.have longest straight ..: lengths which are lessLthan the minimum in the criteria, and four plants have welded lugs or trunnion attachments to PSL. Since none of the analysis to date has included
' evaluation of welded attachments, which may increase thermal stresses due-to structural discontinuities, this condition falls outside the criteria ,
and the following has been recommended.
a) Inspection of these welds during walkdown ;
b) Evaluation of these attachments on a plant-specific basis. '
The five plant specific analysis consisted of three parts: (1) global effects on stresses, moments, displacements, and support reaction loads; based on both axial and radial variations in the pipe metal terperature, (2) local stresses due to thermal gradient, and (3) local stresses and effects to fatigue due to thermal striping. The global and local stresses in items (1) and (2) above were superimposed to obtain total stresses. In-addition to the detailed plant specific analysis for the five plants, twelve (12) plants have completed interim evaluations of the surge line s'
stratification which include Finite Element structural analysis of each specific. configuration under stratified conditions.
The five plants for which detailed plant-specific analyses performed and evaluation reports submitted.to NRC, are as follows:
Seabrook (see WCAP-12151-and Suppl. 1, and WCAP-12305) South Texas Units 1 and 2 (see WCAP-12067 Rev 1 and Suppl. 1) Vogle Unit 2 (see WCAP-12132, WCAP-12199 and WCAP-12218) Beaver Valley Unit 2 (see WCAP-12093 and i Supp1's 1 and 2) Comanche Peak Unit 1 (see WCAP-12248 and Suppl. 1) t Based on these reviews Westinghousi concluded that a shorter horizontal s
length will result. in lower loads since the the surge line will experience less vertical deflection and it will tend to to result in a more uniform - J distribution of the bending moment due to stratified loading.' In addition I middle line risers will also t6nd to reduce the stratification effects.
The stratification induced global bending of the surge line was calculated i
'~
usirg ANSYS computer code. Although a 320*F step temperature change was assumed for stratification through out the surge line, the changes were linearized in ANSYS using conventional pipe eierent model. Finite Element l' models were used to calculate local stresses due to top-tobottom non-linear thermal gradients in the PSL. Five-(5) hot-to-cold interface locations were analyzed-using eleven (11) cases of thermal stratification, to-calculate piping response undser all required loading conditions, reflecting temperatures differences up to 320'F. Other cases we,e obtained by interpolation. Westinghouse reported that their best estimate analytical results compared favorably with measured displacements data observed during monitoring.
l
4 Page 5 of 8 h
In two of the analyses, a rigid vertical support was removed. In one case ;
it was shown that the support was not required, and in the other case it '
was replaced with a snubber and a spring. The PSL was subsequently '
re qualified and found acceptable.
Stress summary results from the five plant specific analyses performed to date indicates that the primary plus secondary stress intensity range ratio of equation 12 of ASME III section NB-3600, is less than 1.0. The critical location for stress is usually the safe end weld of the nozzla connecting the surge line to the primary loop hot leg. In one case only I
it was determined to be at the reducer. This seem to be a unique case :!
since no other utility within the WOG has a mid line reducer in the PSL.
Stresses were intensified by "K" factors, to account for the worst case '
concentration-for all piping elements in the PSL. The staff agrees with tne approaches used by the licensee for performing PSL reanalysis. ;
To account for the thermal striping effects to PSL, flow model test' results, performed for the Liquid Metal Fast Breeder Reactor primary 'oop and for the Mitsubishi Heavy Industries Feedwater Line cracking, were reviewed to establish the boundary condition. These test results were t
used to define striping oscillation data, amplitude and frequencies, for evaluating high cycle fatigue. Portions of PSL which experience stratification and striping were defined based on measured results.
- Westinghouse teported that considering AT attenuation with time, and a frequency o' 30 HZ, a usage factor of less than .20 was determined as the worst case due to striping alone, even when the stresses were intensified by "K" factors.
weld. A.' surfaceThe worst case element was do' ermined to be the butt film coefficient of 500 BTU /hr-sq. ft *F was used and it t
was based on a flow rate of 90 gpm.which was assumed to be constant throughout all striping analysis. Although the data used in the assess-ment were obtained from scale test model which showed that the frequency can range from .10-10 HZ. the staff agreed that the stresses will be higher with the lower frequency and the .30 HZ. average frequency is justified. However the thermal striping potential due to a film L coef ficient of 500 BTU /hr-sq. ft. *F and attenuation of AT is questionable, but at this time no other better number exists and therefore this represents the best judgement. If other information will be available, based on the ongoing efforts by EPRI or possible future NRC research work, it will be utilized and further assessments will be made for assessing the striping effects to.PSL.
With the thermal transients redefined, new fatigue usage factors were calculated. To' determine the new fatigue usage facters, the more detail techniques of ASME III NB-3200 were employed. Due to the non-axisymmetric nature of stratification loading, stresses due to all loadings were obtained from Finite Element analysis and then combined on a stress compo-
! nent basis. Five (5) levels of thermal stratification at five worst case l ;
l
Page 6 of 8 points were calculated using the WECEVAL program. Stresses were intensified.
by "K" factors to account for worst case concentration in the piping elements.
Westinghouse reported that a cumulative = usage factor (CUF) of 0.73 was-determined to be the worst case at the hot leg nozzle safe end location for all but one case. For that case a 14x16 reducer existed in the surge line and the CUF at that location was determined to 0.94. The CUF included contributions from both global bending and local effects of stratifi- {
cation considering the nonlinear step change top to bottom temperature l distribution and striping. I
-)
i Stresses. resulting from primary loading such as pressure, dead weight, and l seismic are not affected by thermal stratification loading and typically 'l have a minor effect on the calculation of the fatigue usage factor. The .l contribution'of seismic loadings to the cumalative usage factor from the plant specific analyses was reported to be 18%. All of the detailed plant specific analyses assum',3 the occurrence of twenty operational earthquakes. l The staff agrees with the approaches used by Westinghouse for calculating the usage factor. '
Westinghouse repor.ad that the PSL fatigue life is primarily depended upon the number of heatup and cooldown cycles rather than the years of operation.
The worst case years of operation at any WOG plant is.28.5 years. The a worst case number of heatup cooldown cycles is 75 and occurs at a different- '
plant.
Based on the combination of these two worst case values an
" Operating Life Factor" (OLF) of 0.44 is obtained which indicates -that no more than 50% of the operating life has been used at any Westinghouse plant to date. For the generic case of a CUF = 1.0 a 17% value was 4 attributed to age and an 83% was attributed to fatigue with a 20% of the +
83% value attributed to striping.
.e C
i m
l r*~ . ;j
, ; -, s Page 7 of 8 CONCLUS10NS Based on our review, we conclude that the information provided by Westinghousefin references 1 and 2, is comprehensive and acceptable. i
' Westinghouse on behalf of the Owners Group had made acceptable efforts to i
' -provide technical basis for the licensee's JC0 as indicated in the requested actions of the NRC Bulletin 88-11, item 1.b. The staff-believes that there is no immediate or short term safety concerns associated with the stratification effects for 10' additional heatup/ .
cooldown cycles of continued plant operation. However, each of the WOG l plants should submit a JC0 using this report as the basis. We will assess if the surge line in each plant meet the code acceptance criteria for the l i
40 year plant life when additional generic analyses based on plant grouping !
is performed by; Westinghouse for the Owners group.
)
I--
i l,
s
~
m a g aie.
, Page 8 of 8-REFERENCES l
- 1. Westinghouse Report WCAP-12277 (Proprietary), and WCAP-12278 (Non-Proprietary).. " Westinghouse Owners Group bounding evaluation for Pressurizer surge Line thermal stratification," June 15, 1988.
2, Viewgraphs by Westinghouse. Presentation to NRC on May 23 and 24.
- 1 i
a l
1 I
-l l
C. __m -_..__._____m________.-____...._..m__ . . _ . . . . _