ML20059D651
| ML20059D651 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 08/29/1990 |
| From: | Collins S NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | William Cahill TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| Shared Package | |
| ML20059D654 | List: |
| References | |
| NUDOCS 9009070133 | |
| Download: ML20059D651 (3) | |
See also: IR 05000445/1990034
Text
'
..
.. .
,
AUB 29 S00
l
!
Reply Refer To:
Dockets:
50-445/90-34
'
50-446/90-34
TV Electric
i
ATTN:
W. J. Cahill, Jr.
Executive Vice President, Nuclear
Skyway Tower
400 North Olive Street, Lock Box 81
<
Dallas, Texas
75201
Gentlemen:
!
This refers to the special team inspection conducted by Messrs. A. T. Howell,-
i
D. L. Kelley, D. N. Graves, and R. B. Vickrey during the period July 31 through-
August 7, 1990, of activities authorized by NRC Facility Operating _
License NPF-87 and NRC Construction Permit CPPR-127 for the Comanche Peak Steam
Electric Station, Units 1 and 2, and to the discussion of our findings with you
and other members of your staff at the conclusion of the inspection.
~
i
This inspection was conducted to review the circumstances following a. safety
,
injection event at Comanche Peak Steam Electric Station (CPSES), Unit 1, on
'
July 30,1990.
1
The enclosed copy of our inspection report identifies areas examined during the
inspection. Within these areas, the inspection consisted of selective
examination of procedures and representative records, interviews with
personnel, and observations by the inspectors.
During this inspection, it was found-that certain of your activities were in
1
violation of NRC requirements. This violation would normally be considered as
noncited per 10 CFR 2, Appendix C, criteria; however, although your staff
identified the violation and promptly corrected it, this violation was
potentially more significant because the operability of all four atmospheric
relief valves could have been affected by the presence of water from isolated
main steam isolation valve (MSIV) upstream drippots.
Since action has already
_
been taken to correct the hot standby operating procedure inadequacies, no
'
response to this violation is required.
During this inspection, you committed in an Augus't 4, 1990, letter to NRC
Region IV (TXX-90283) to implement a design modification to remove the local
switches for the essential lights, as appropriate. We, thereby, request that
you provide, in writing, to NRC Region IV, a schedule for the implementation of
this design modification, as well as a description of any interim measures that
you deem appropriate to ensure that all essential lighting remains energized
until such time that the design modification can be implemented. We request
that you provide this information within 30 days of the date of this letter.
pC:DRP/PN
RI :DR B:RI
Rf
0
DR
DRS:T
- DRP
D-
AHowell:ww
DGraves
RV ekrey DKell
DChamberlain
TGwynn
C
ns
8/rl/90
$ /27 /90
f/fy/90 $ /fl/90
t/$/90
[/)f/90
000CO
[
/
$ 0 *$0$2R Pso$N4s
G
PNU
e'
..
TV Electric
-2-
The response directed by this letter is not subject to the clearance procedures
of the Office of Management and Budget as required by the Paperwork Reduction
Act of_1980, PL 96-511.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter, the enclosures, and your response to this letter will be placed in the
,
NRC Public Document Room.
l
Should you have any questions concerning this inspection, we will be pleased to
discuss-them with you.
Sincerely,
Samuel J. Collins, Director
Division of Reactor Projects
Enclosure;:
'
1.
Appendix A - Notice of Violation
2.
Appendix B - NRC Inspection Report
50-445/90-34; 50-446/9 M 4
cc w/ enclosures:
TV Electric
ATTN:
Roger D. Walker, Manager,
Nuclear Licensing
Skyway Tower
400 North Olive Street, Lock Box 81
Dallas, Texas 75201
Juanita Ellis
President - CASE
1426 South Polk Street
Dallas, Texas 75224
GDS Associates, Inc.
Suite 720
1850 Parkway Place
Marietta, Georgia 30067-8237
Billie Pirner Garde, Esq.
Robinson, Robinson, et al,
103 East College Avenue
Appletor., Wisconsin 45911
I
.
T
.
, .
,
TV Electric
-3-
TU Electric
Bethesda Licensing
3 h:tro Center, Suite 610
Bethes'J, Maryland 20814
l
i
Heron, Burchette, Ruckert, & Rothwell
ATTN: William A Burchette, Esq.
I
Counsel for Tex-La Electric
Cooperative of Texas-
1025 Thomas Jefferson St., N.W.
Washington, D.C.
20007
E. F. Ottney
P.O. Box 1777-
Glen Rose, Texas 76043
i
-
Newman & Holtzinger, P.C.
ATTN: Jack R. Newman, Esq.
-1
1615 L. Street, N.W.
_,
Suite 1000
i
Washingtin, D.C.
20036
,
Texas Department of Labor & Standards
l
'
ATTN:
G. R. Bynog, Program Manager /
Chief Inspector
Boiler Division
P.O. Box 12157, Capitol Station
y
$
Honorable George Crump
'
County Judge
-i
Glen Rose, Texas 76043
.
Texas Radiation Control Program Director
1100 West 49th Street
,
bec to DMB (IE01)
'
bec distrib. by RIV:
- R. D. Martin
'* Resident Inspector (2)
- DRP
- DRS
- Section Chief (DRP/B)
- Project Engineer (DRP/B)
- DRSS-FRPS
Lisa Shea, RM/ALF-
- MIS System
- RSTS Operacor
- RIV Files
J. Lieberman, OE
G. F. Sanborn, E0
,
- w/766
)