TENNESSEE VALLEY. AUTHORITY CH ATTANOOG A. TENNESSEE 37401 SN 157B Lookout Place 00T 261990 i
U.S. Nuclear Regulatory Conaission ATTN:
Document Control Desk
. Washington, D.C.
20555 Gentlemen:
In the Matter of
)
Docket No. 50-260 Tennessee Valley Authority
)
BROWNS FERRY NUCLEAR PLANT (BFN) - TVA SUBMITTALS REQUIRED TO SUPPORT RESTART LICENSING' ACTIONS j
i This letter is-in-response to the NRC's August 3, 1990 letter which contained i
a list-of TVA submittals which were deemed necessary to support resolution of j
the remaining licensing actions required for the restart of BFN Unit 2.
The j
target dates. established for these submittals were based upon the existing j
restart schedule. Subsequently. an updated restart schedule was presented to j
the Commissioners on September 26, 1990.
Enclosed is an update.to the submittal list which shows actual completion dates or committed completion j
dates which are-based upon the current restart schedule.
1 i
If you have'any questions, please contact Patrick P. Carler, Manager of Site f
Licensing, at (205) 729-3566.
Very truly yours,
'I TENNESSEE VALLEY AUTif0RITY A
l o
}rt l
E. G. Wallace, Manager l
Nuclear Licensing and Regulatory Affairs Enclosure l
i cc:' See page~2
[' bb 9011050300 901026 M
ADOCK0500ggO p,,
PDR P
/
An Equal Opportunity Employer
e
_2-(107 26 1990 U.S. Nuclear Regulatory Commission cc (Enclosure):
Ms. S. C. Black, Deputy Director Project Directorate 11-4 U.S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike, Rockville, Maryland 20852
.NRC Resident Inspector Browns Ferry. Nuclear Plant Route 12, Box 637 Athens, Alabama 35609-2000 Mr. Thierry M. Ross, Project Manager U. S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852 Mr. B. A. Wilson, Project Chief U.S. Nuclear' Regulatory Commission Region II
'101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 M
F t
l Pegs 1 of 3
-4 i
ENCLOSURE BROWNSFERRYNUCLEARPIMT LIST 0FRESTARTSUBMITIALS I
TITLE DATE l
i 1.
Restart Technical Specification Amendment Requests:
l A '.
' Shutdown Cooling Isolation (TS 282) 8/06/90 A B.
Fire Pump Capability (TS 292) 8/07/90 A C.
Analytical Limits (TS 291) 8/06/90 A I
D.
RAI - Analytical Limits (TS 291) 10/05/90 A j
i E.
RAI - RPS Circuit Protectors (TS 286) 10/24/90 A i
F.
Hydro /ILRT (TS 280 - Sup. 1) 10/30/90 C j.
2.
Regulatory Performance Improvement Plan (RPIP) Closure 9/18/90 A 4
I 3.
BFN Nuclear Performance Plan Closeout Letter 2/14/91 0 1
4.
NUREG-1232, and Supplement 1 Open Item Status 10/26/90 C l
5.
Safety Parameter Display System (SPDS) Final Design Description and Interim Design Installation 10/22/90 A-6.
Environmental Qualification Certification of Compliance 2/01/91'C (USI A-24/10 CFR'50.49) i t
'7. ' Cable Installation Issues and Final Testing Report 9/19/90 A j
.(Revised by' letter dated 10/04/90) 8.
Regulatory Guide 1.97 Supplement 10/15/90 A l
9.
Generic Letters (GL):
A.
GL 89-19 (Revised Response and Implementation 8/17/90 A Complete)
B..
GL 90-03 (Initial Response) 8/24/90 A l
C.
.GL 88-14 (Implementation Complete) 2/04/91 C i
.D.
'GL.90-10 (Program and Schedule) 12/21/90 C Legend: A - Actual Submittal Date C - Committed Submittal Date
- J
a' P:ss 2 of 3 EN0LOSURE(Continued)
BROWNS FERRY NUCLEAR PIET LISTOFRESTARTSUBMITTALS TITLE DATE
- 10. Bulletins (B):
A.
B 79-02/79-14 (Restart Commitments Complete) 1/29/91 C B..
B 80-06 (Implementation Complete) 11/27/90 C
-C.
B 80-11 (Implementation Complete) 8/17/90 A D.
B 88-08 (Supplement 3 Response and Implementation 8/16/90 A Complete)
E.
B 88-10 (Implementation Complete) 11/28/90 C F.
B 90-01 (Implementation Complete) 10/15/90 A
- 11. NUREG-0737 - TMI Action Plan:
A.
Final SPDS Description (I.D.2.1)
Same as 5 B.
Noble Gas monitor (II.F.1.2.A) 12/17/90 C C.
Iodine / Particulate Sampling (II.F.1.2.B) 12/17/90 C D.-
. Automatic Depressurization System (ADS) Timer 1/19/91 C I
(II.K.3.18.0)
E.
' ADS Accumulators (II.K.3.28) 9/17/90 A F.
Post-Accident Sampling System Insta11atior and No longer Procedures (II.B.3) required for restart i
G.
Containment Pressure Monitor (II.F.1.2.D).
10/01/90 A H.
. Containment Isolation Dependability Same as 10B (II.E.4.2.1
.8) 4 I.
Common Reference Level (II.K.3.27)
Included in 11J-3 l: >
Legend: A - Actual Submittal Date C - Committed Submittal Date 4
1 1
'o' Page 3 of 3 4
EN0LOSURE(Continued)
BROWNSFERRYhUCLEARPLANI l
i LISI0FRESIARTSUBMITIALS l
TITLE DATE l
I
- 11. NUREG-0737 - TMI Action Plan (Continued):
l J.
Detailed Control Room Design Review - Restart 2/14/91 0 Items Only (II.D.1)
K.
Plant Sheilding Supplemental Response 11/14/90 C i
)
I A.
Mark I Containment Long Term Program (USI A-7) 10/01/90 A B.
Main Feedwater and Control Rod Drive Nozzle 10/09/90 A
i I
Cracking (USI A-10)
C.
Scram Discharge Volume Pipe. Break (GSI 40) 10/01/90 A
- 13. 10 CFR 50, Appendix,' J Primary Containment Testing-8/28/90 A Program Implementation Complete j
- 14. Emergency Diesel Generator - Probabilistic Risk 10/01/90 A Assessment Reliability Matrix j
i
- 15. Systematic Assessment of Licensee Performance Report 8/08/90 A l
Response
]
t 16.' Readiness for Operational Readiness Inspection To Be' j
Determined-
{
'17. Special Nuclear Material - Final Report 2/22/91 C l
l 1
)
l 1
Legend: A - Actual Submittal Date C-- Committed Submittal Date
/