Informs That Proposed Schedule Changes of Apr 1994 for Submitting IPE Summary Rept & Feb 1996 for Submitting IPEEE Rept,Acceptable
ML20056H250
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 08/25/1993
From: Marlone Davis
Office of Nuclear Reactor Regulation
To: Miltenberger S
Public Service Enterprise Group
References
GL-88-20, TAC-M74421, TAC-M83630, NUDOCS 9309090046
Download: ML20056H250 (3)


Text

_

pm afcq

/

c, Ig.( mg i UNITED STATES i

NUCLEAR REGULATORY COMMISSION g,,

P WASHINGTON, D C. 20$55-0001 Annist 25, 1903 t

Docket No. 50-354 Mr. Steven E. Miltenberger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Box 236 r

Hancocks Bridge, New Jersey 08038

Dear Mr. Miltenberger:

SUBJECT:

REVISED SCHEDULE FOR THE SUBMITTAL OF THE INDIVIDUAL PLANT EXAMINATION FOR SEVERE ACCIDENT VULNERABILITIES, GENERIC LETTER 88-20, HOPE CREEK GENERATING STATION (TAC N05. M74421 AND M83630)

By letter dated July 30, 1993, you proposed to revise the schedule for i

submitting the summary report of your Individual Plant Examination (IPE) from July 1993 to April 1994 and the subsequent report of the Individual Plant Examination for External Events (IPEEE) from May 1995 to February 1996. The NRC ' staff has reviewed the basis provided in your letter to support the proposed schedule changes and has determined that the revised schedule of April 1994 for submitting the IPE summary report and February 1996 for submitting the IPEEE report is acceptable.

We appreciate you keeping us informed of the progress being made, problems encountered, and changes to the schedules related to this effort.

Sincerely, l/

w gud Michael J. Davis, Acting Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc:

See next page 9309090046 930825" PDR ADDCK 05000354 P

PDR;

August 25, 1993 i

Docket No. 50-354 Mr. Steven E. Miltenberger Vice President and Chief Nuclear Officer l

Public Service Electric and Gas Company l

Post Office Box 236 Hancocks Bridge, New Jersey 08038 l

Dear Mr. Miltenberger:

SUBJECT:

REVISED SCHEDULE FOR THE SUBMITTAL OF THE INDIVIDUAL PLANT EXAMINATION FOR SEVERE ACCIDENT VULNERABILITIES, GENERIC LETTER

)

88-20, HOPE CREEK GENERATING STATION (TAC NOS. M74421 AND M83630)

By letter dated July 30, 1993, you proposed to revise the schedule for submitting the summary report of your Individual Plant Examination (IPE) from July 1993 to April 1994 and the subsequent report of the Individual Plant Examination for External Events (IPEEE) from May 1995 to February 1996.

The NRC staff has reviewed the basis provided in your letter to support the proposed schedule changes and has determined that the revised schedule of April 1994 for submitting the IPE summary report and February 1996 for submitting the IPEEE report is acceptable.

We appreciate you keeping us informed of the progress being made, problems encountered, and changes to the schedules related to this effort.

]

Sincerely, Original signed b Michael J. Davis, yActing Project Manager Project Directorate I-2 l

Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc: See next page DISTRIBi) TION Docket file NRC & Local PDRs PDI-2 Reading SVarga JCalvo MBoyle MDavis M0'Brien RHernan OGC ACRS(10)

'600C3 EWenzinger, RGN-I JWhite. RGN-I f

0FFICE PDIihLA PDI-2/PM PDI-4/PM PDI-2/D.

2 NAME M0'sied MDavis:rb' T RHernanh MBoylefik DATE S/[/93 7 /23/93 9 hif/93 8/26/93 OFFICIAL RECORD COPY g" gJ] {p%f DOCUMENT NAME: HC74421. GEN

Mr. Steven E. Miltenberger Hope Creek Generating Station Public Service Electric & Gas Company cc:

M. J. Wetterhahn, Esquire Mr. J. A. Isabella Winston & Strawn MGR. - Generation Department 1400 L Street, N.W.

Atlantic Electric Company Washington, DC 20005-3502 Post Office Box 1500 1199 Black Horse Pike Pleasantville, New Jersey 08232 R. Fryling, Jr., Esquire Law Department - Tower SE Richard Hartung 80 Park Place Electric Service Evaluation Newark, New Jersey 07101 Board of Regulatory Commissioners 2 Gateway Center, Tenth Floor Hope Creek Resident Inspector Newark, NJ 07102 U.S. Nuclear Regulatory Commission Drawer I Lower Alloways Creek Township Hancocks Bridge, New Jersey 08038 c/o Mary 0. Henderson, Clerk Municipal Building, P.O. Box 157 Mr. J. Hagan Hancocks Bridge, NJ 08038 Vice President - Nuclear Operations Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. R. Hovey General Manager - Hope Creek Operations Hope Creek Generating Station P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. Frank X. Thomson, Jr., Manager Licensing and Regulation Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection and Energy CN 415 Trenton, New Jersey 08625-0415