ML20055B551

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-293/82-12 on 820405-0509 & Notice of Violation
ML20055B551
Person / Time
Site: Pilgrim
Issue date: 07/07/1982
From: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Harrington W
BOSTON EDISON CO.
Shared Package
ML20055B552 List:
References
NUDOCS 8207220486
Download: ML20055B551 (2)


See also: IR 05000293/1982012

Text

.

.

..

JUL 0 71982

Docket No. 50-293

Bostr,n Edison Company M/C Nuclear

ATTN: Mr. William D. Harrington

Senior Vice President, Nuclear

800 Boylston Street

Boston, Massachusetts 02199

Gentlemen:

Subject: Inspection 50-293/82-12

This refers to the routine safety inspection conducted by Mr. J. Johnson of

this office on April 5 - May 9,1982, at the Pilgrim Nuclear Power Station,

Plymouth, Massachusetts, of activities authorized by HRC License flo. DPR-35

and to the discussions of our findings held by Mr. Johnson with Mr. R. Machon

and other members of your staff periodically during the inspection and at the

conclusion of the inspection.

Areas examined during this inspection are described in the NRC Region I In-

spection report enclosed with this letter. Within these areas, the inspection

consisted of selective examinations of procedures and representative records,

interviews with personnel, and observations by the inspector.

Based cn the results of this inspection, it appears that one of your activities

was not conducted in full compliance with NRC requirements, as set forth in

the Notice of Violation, enclosed herewith as Appendix A.

This item of non-

compliance has been categorized into the level described in 10 CFR 2. Appendix

C and the Federal Register Notice 47 FR 9987 dated March 9,1982. You are

required to respond to this letter; and, in preparing your response, you

should follow the instructions in Appendix A.

In your response, please include those actions taken or planned to ensure that

actions specified by the Technical Specifications in the event of inoperable

equipment are followed.

Include cases where the loss cf one component may

affect several sections of the T.S. and where the loss may involve instrument

channels and logic systems.

The item described in the attached Notice of Violation Appendix A, involving

reactor vessel water level instrumentation, is classified as a Severity Level

IV violation. As indicated in Supplement I of the NRC Enforcement Policy

(10 CFR 2, Appendix C), significant violations of this type are normally

classified at Severity Level III. However, after careful consideration of

the factors involved in this instance including plant and facility status

and compensatory monitoring measures we have exercised our judgement under

the NRC Enforcement Policy and have classified this violation as a Severity

<

IE01

. .

8207220486 820'707

CFFICIAL RECORD COE'T

PDR ADOCK 05000293

G

PDR

)

l

'

.

.

uoston toison t.ompany

-c-

M/C !!uclear

JUL 0 71982

Level IV. Similar violations of this type in the future may result in

additional enforcement action. Furthemom, we also note that the violation

was identified by you and reported in LER F" 011/01T; however, we are con-

cerned about the occurrence of this event and the need for appropriate

training of the operating staff to prevent recurrence. Accordingly, we will

schedule an enforcement conference with you in the near future in order to

discuss our concerns in this regard.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures

will be placed in the NRC Public Document Room, unless you notify this office,

'

by telephone, within ten days of the date of this letter and submit written

application to withhold ir.fomation contained therein within thirty days of

the date of this letter. Such application must be consistent with the require-

mentsof2.790(b)(1).

Your cooperation with us in this matter is appreciated.

Sincerely,

Richard W. Starostecki, Director

Division of Project and Resident

Programs

Enclosures:

1.

Appendix A.

Notice of Violation

2.

flRC Region I Inspection Report flo. 50-293/82-12

cc w/encls:

J.11. Bonsall, Chaiman, Department of Public Utilities

J. E. Howard, Vice President, Nuclear

R. D. Nachon, Huclear Operations Manager - Pilgrim Station

A. V. Morisi, Manager, Nuclear Operations Support

Joanne Shotwell, Assistant Attorney General

Plymouth Board of Selectman

Public Document Room (PDR)

localPublicDocumentRoom(LPDR)(NSIC)

fluclear Safety Information Center

HRC Resident Inspector

Commonwealth of Massachusetts (2)

bec:

Region I Docket Room (with concurrences)

Chief Operational Support Section (w/o encis)

J. Liebeman

,

D. Holody

i

A

//} [)

M

,

s

OFFICE) .. RI.: DPRP... . ...

,.'.:...... DREP.. . .(.t.. DRBP.. .. . .

. . .. .Q.PRP. . . . . . . . .. ..

n

v

,1: -

,t

. . . . . . . . . . . . . . . . . .

. . . . . . . . . . . , , . . . . . . .

. . . . . . , , . . . . . . . . . .

Starosgcki

Johnson:jm

Elsasser

B

ner

SURNAME)

V

,

..., .. ., q v

..D... ... ,.

a. y . ... ..,,

, . , . . . , . , . , . . . _ . . . _ . _ . _ . . , .

, , , . . _ . . . , . _ . . _ . . . .

_ . . _ . . . . _

4

..a...l..i, ( C v. . ..

.'..i .! !.., .i s k

<

om>

. . . . . . . . . . . .

.

.

.

.

. . . . .

.

. . . .

Nnc ronu ais tto.aon nacu o24o

OFFICIAL RECORD COPY

uso m an- a ,m

,

. .

._

__ _- -

.

--

_

. - - _ _