Requests Approval of Proposed Point Beach Emergency Preparedness Exercise Scheduled for Sept 1983,as Agreed Upon at 820421 Meeting W/Nrc Region 3.Proposed 3-month Extension Will Not Be Detrimental to State of Emergency Preparedness
ML20054M228
Person / Time
Site: Point Beach, Susquehanna, San Onofre  NextEra Energy icon.png
Issue date: 06/30/1982
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Clark R, Harold Denton
Office of Nuclear Reactor Regulation
References
TAC-48586, TAC-48587, NUDOCS 8207120126
Download: ML20054M228 (2)


Text

o ., Djf WISCONSIN Electnc m cower 231 W. MICHICAN, P.O. BOX 2046. MILWAUKEE, WI 53201 June 30, 1982 Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U. S. NUCLEAR REGULATORY COMMISSION Washington, D. C. 20555 Attention: Mr. R. A. Clark, Chief Operating Reactors Branch 3 Gentlemen:

DOCKET NOS. 50-266 AND 50-301 EMERGENCY PREPAREDNESS EXERCISE SCHEDULE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 On April 21, 1982, a meeting was held at O' Hare International Airport in Chicago, Illinois to discuss the scheduling of emergency plan exercises for nuclear plants within NRC Region III. Participants included representatives of NRC Region III, FEMA Region V, and the states and utility licensees within the NRC Region III area.

At the meeting it was determined and agreed upon by ,

all participants, including NRC Region III, that the next exercise for our Point Beach Nuclear Plant would be tentatively scheduled for September 20, 1983. This date coordinates well with the schedular needs of the federal, state, and local government agencies involved, as well as our own outage planning schedule.

Our last exercise (full-scale) was held on March 9, 1982. Since the proposed September 1983 date would result in approximately 18 months between exercises, NRC Region III has recommended that we request an exemption pursuant to the inter-pretation that the annual exercise requirement of Appendix E to 10 CPR 50 is to be measured on the basis of one year from the previous exercise + 25%, i.e., a maximum of 15 months.

8207120126 820630 DR ADOCK 05000266 i

PDR l[)$

i

.A . ,

Mr. H. R. Denton June 30, 1982 We note that the proposed schedule would satisfy the frequency requirement on the basis of a calendar year interpre-tation and that, in any event, the spirit and intent of the annual exercise requirement will be preserved. Furthermore, the proposed three-month extension of the normal maximum interval will not in any way be detrimental to our state of emergency i preparedness, since our schedule for drills, training, and implementation of planned emergency preparedness modifications I will be unaffected by this proposal.

4 Accordingly, wt 5' quest your approval for the proposed exercise schedule.

Very truly yours, Assistant Vice President C. W. Fay

Copy to NRC Resident Inspector l