ML20054H749

From kanterella
Jump to navigation Jump to search
Forwards IE Emergency Preparedness Appraisal Rept 50-219/82-01 on 820104-15 & Emergency Preparedness Findings, Improvement Items & Evaluation
ML20054H749
Person / Time
Site: Oyster Creek
Issue date: 06/11/1982
From: Galen Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Fiedler P
GENERAL PUBLIC UTILITIES CORP.
Shared Package
ML20054H750 List:
References
NUDOCS 8206240389
Download: ML20054H749 (37)


See also: IR 05000219/1982001

Text

[

e

<

JUN 111982

Docket No. 50-219

GPU Nuclea Corporation

ATTN:

Mr. P. B. Fiedler

Vice President and Director

Oyster Creek Nuclear Generating Station

P. O. Box 388

Forked River, New Jersey 08731

Gentlemen:

-

Subject:

Emergency Preparedness Appraisal 50-219/82-01

To verify that licensees have attained an adequate state of onsite emergency

preparedness, the Nuclear Regulatory Commission is conducting special appraisals

at each power reactor site. These appraisals are being performed in lieu of

certain routinc inspections normally conducted in the area of emergency prepared-

ness. The objectives of the appraisal at each facility are to evaluate the

overall adequacy and effectiveness of emergency preparedness and to identify

areas of weakness that need to be strengthened. We use the findings from

these appraisals as a basis not only for requesting individual licensee action

to correct deficiencies and effect improvements, but also for effecting improvements

in NRC requirements and guidance.

During the period of January 4 - 15, 1982, the NRC conducted an appraisal of

the emergency preparedness program for the Oyster Creek Nuclear Generating

Station. Areas examined during this appraisal are described in the enclosed

NRC Cegion I Inspection Report No. 50-219/82-01. Within these areas, the

appraisal team reviewed selected procedures and representative records, inspected

emergency facilities and equipment, observed work practices, and interviewed

personnel.

The findings of this emergency preparedness appraisal indicate that certain

corrective actions are required in your emergency preparedness program. These

are discussed in Appendix A, "Significant Emergency Preparedness Findings".

Significant findings for which you have made acceptable commitments to resolve

were discussed in the Confirmatory Action Letter dated February 18, 1982. All

significant findings, except Appendix A, Item 18 were addressed in this

letter. A copy of the letter is enclosed (Enc ksure 5).

Significant findings nos. 11 and 14 address your need for equipment which

would allow the sampling of reactor coolant and containment atmosphere under

post-accident conditions per NUREG-0737. The NRC has yet to take a position

concerning your request to postpone the installation of the post-accident

sampling equipment from your next major refueling / maintenance outage

until an outage scheduled for 1984. As was indicated in the Confirmatory Action

Letter dated February 18, 1982, as soon as we resolve the status of your request,

we will inform you when this sampling equipment must be installed.

g(

OFFICIAL RECORD COPY

g

p

a

V

A/

b

rup>

9

8206240389 820611,,

a

--

~

p

-

I

e

r

JUN 111932

GPU Nuclear Corporation

2

Other areas needing improvements are discussed in Appendix B, " Emergency

Preparedness Improvement Items."

In conjunction with the aforementioned appraisal, emergency plans for your

facility were reviewed by the Emergency Preparedness Licensing Branch, Division

of Emergency Preparedness, Office of Inspection and Enforcement.

The results

of this review indicate that certain deficiencies exist in your emergency

plan.

These are discussed in Appendix C, " Emergency Preparedness Evaluation

Report."

Appendices A, B, and C of this letter contain an inclusive listing of all

outstanding errergency preparedness items at your facility at this time.

We recognize that an explicit regulatory requirement pertaining to each item

identified in Appendices A, B, and C may not currently exist.

Notwithstanding

this, you are requested to submit a written statement within thirty (30) days

of the date of this letter, describing your planned actions for improving each

of the items identified in Appendix A and the results of your consideration of

each of the items in Appendix B.

This description is to include, (1) actions

which have been taken, (2) actions which will be taken, and (3) a schedule for

completion of actions for each item. With regard to Appendix C, you are

requested to provide to this office within 120 days of the date of this letter,

page changes to the emergency plan correcting each deficiency or provide

written justification as to why you believe a revision should not be made.

Copies of these changes are to be submitted in accordance with the procedures

delineated in Section 50.54(q), Part 50, Title 10, Code of Federal Regulations.

This is to inform you that if finding no. 18, listed in Appendix A, which was

not included in the February 18, 1982 letter, is not corrected within 120 days

from the date of this letter, the Nuclear Regulatory Commission will determine

whether enforcement action is appropriate.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure

will be placed in the NRC Public Document Room, unless you notify this office

by telephone within ten days of the date of this letter and submit written

application to withhold information contained therein within thirty days af

the date of this letter.

Such application must be consistent with the requirements

of 2.790(b)(1). The telephone notification of your '.ntent to request withholding,

or any request for an extension of the 10 day period which you believe necessary,

should be made to the Supervisor, Files, Mail, and Records, USNRC Region I, at

(215) 337-5223.

The reporting requirements contained in this letter affect fewer than ten

persons and, therefdre, are not subject to Office of Management and Budget

clearance as required by PL 96-511.

OFFICIAL RECORD COPY

]

,e

l

GPU Nuclear Corporation

3

JUN 11 D32.

Should you have questions concerning this inspection, we will be pleased to

discuss them with you.

Should you have questions concerning the items of

Appendix C, please contact Mr. R. Van Niel, Emergency Preparedness Licensing

Branch at (301) 492-4535.

Sincerely,

g Silp*d D8

gg

s . H . S M Tet

George H. Smith, Director

Division of Emergency Preparedness

and Operational Support

Enclosures:

1.

Appendix A, Significant Emergency Preparedness Findings

2.

Appendix B, Emergency Preparedness Improvement Items

3.

Appendix C, Emergency Preparedness Evaluation Report

4.

NRC Region I Inspection Report Number 50-219/82-01

5.

Confirmatory Action Letter, dated February 18, 1982

cc w/encls:

M. Laggart, Licensing Supervisor

J. Knubel, BWR Licensing Manager

Public Document Room (POR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New Jersey

bcc w/encls:

Region I Docket Room (with concurrences and enclosures)

Chief, Operational Support Section (w/o encis)

1

0

R

R

POS

Croc r

Snyd

'G

H.

mith

A.titi!Ac.T

cKC

tJI

a

x

4 ,,

0 FICIAL R CORD COPY

-

.

_.

-

.

=

APPENDIX A

SIGNIFICANT EMERGENCY PREPAREDNESS FINDINGS

Based on the results of the NRC's appraisal of the GPU Nuclear Corporation's

Emergency Preparedness Program 2 the Oyster Creek Nuclear Generating Station

conducted January 4 - 15, 19E

the following improvements are required:

(First parenthetical references are to the pertinent section in NRC Region I

Inspection Report No. 50-219/E2-01.) (Second parenthetical references are the

February 18, 1982 Confirmatory Action Letter (CAL) item which addressed the

specific improvement.)

1.

Complete the development of, and establishment of, a more comprehensive

training / retraining program for all emergency response personnel which is

consistent with the Emergency Plan and Emergency Plan Implementing Procedures.

(Section 3.1) (CAL-3.)

2.

Include training in post-accident sampling and analysis of reactor coolant,

containment air, and stack effluents in the training program after the

implementing procedures and equipment are available. Hands-on, walk-through,

and talk-through training should be a part of this training.

(Section

3.1) (CAL-3.)

3.

Implement an effective training program, and train members of the newly

defined Initial Response (Onsite) Emergency Organization and Full

Mobilization (Offsite) Emergency Organization in the emergency response

functions.

(Section 3.2) (CAL-3.)

4.

Train all personnel who will perform emergency response functions.

(Section 3.2) (CAL-3.)

5.

Relocate the Emergency Control Center away from the control room.

(Section

4.1.1.1) (CAL-1.a.)

6.

Upgrade the present Technical Support Center with a ventilation system

providing adequately filtered air, instrumentation to detect direct

radiation and airborne contamination, a more comprehensive set of plant

drawings, more comprehensive plant parameter data from the computer

terminal, more space for the occupants, and better spacing of the telephones.

Also, provide a copy of the results of the TSC shielding study to Region

I of the NRC.

(Section 4.1.1.2) (CAL-1.b(1))

7.

Resubmit conceptual design information for a suitable TSC which meets the

requirements of the Office of Nuclear Reactor Regulation, February 18,

1981, Generic Letter 81-10 concerning " Post-TMI Requirements for the

Emergency Operations Facility." Also, include a schedule showing milestones

and the date when the facility will be operational. (Section 4.1.1.2)

(CAL-1.b.(2))

,

OFFICIAL RECORD COPY

m

-

-

,

.

I

I

Appendix A

2

8.

Locate the Operations Support Center in the Maintenance Building, as

described in the Emergency Plan. Assure that it has adequate space, a

communications system, personnel protection equipment and supplies, and

other equipment and supplies needed for the performance of tasks during

an emergency.

(Section 4.1. 1.3) (CAL-1.c.)

9. .

Upgrade the Nearsite Emergency Operat.fons Facility located in Building 12

of the Forked River site with equipment and supplies to allow management

and technical personnel to perform energency functions as described in

'

your September 11, 1981, letter to the Director of the Office of Nuclear

Reactor Regulation.

(Section 4.1.1.4) (CAL-1.d.).

10. Provide a Farsite Emergency Operation Facility which has the same capabili-

ties as the Nearsite Emergency Operations Facility, as called for in your

Emergency Plan and in your September 11, 1981, letter to the Director of

the Office of Nuclear Reactor Regulation.

(Section 4.1.1.4) (CAL-1.e.)

11.

Install a system capable of collecting a high activity reactor coolant

sample (up to 10 curies / gram) under post-accident conditions per NUREG-0737

specification.

(Section 4.1.1.5) (CAL-Unresolved.)

12. Define and predetermine conditions under which reactor building access-

ibility for interim-type coolant sampling can be reasonably expected or

precluded.

(Section 4.1.1.5) (CAL-2.b.)

13. Determine reactor coolant radioactivity levels which can be sampled using

interim-type facilities without exceeding appropriate NRC exposure criteria

or EPA protective action guides.

(Section 4.1.1.5) (CAL-2.b.)

14. Provide facilities capable of collecting a containment air sample under

condit Sns specified in NUREG-0737.

(Section 4.1.1.6) (CAL-Unresolved)

15. Define and predetermine conditions under which reactor building access-

ibility for interim-type containment air sampling can be reasonably

expected or precluded.

(Section 4.1.1.6) (CAL-2.b.)

16. Complete the installation and calibration of the new stack and turbine

building vent radiological gaseous effluent monitoring systems.

(Section

4.1.1.7) (CAL-2.a.)

17. Develop an interim-type methodology to collect and analyze high activity

post-accident gaseous, particulate, and iodine samples consistent with

the activity levels identified in Table II. F.1-2 of. NUREG-0737. Consideration

should be given to any restrictions posed by direct radiation exposure

from normal monitoring and sampling equipment which might have been

operating under accident release conditions.

(Section 4.1.1.7) (CAL-2.b.)

.

18.

Incorporate all area and process radiation Emergency Action Levels given

in the Emergency Plan into the Emergency Plan Implementing Procedures.

(Section 4.2.1.2) (This item was not included in the CAL.)

0FFICIAL RECORD COPY

[

,

.

4

Appendix A

3

19.

Perform an engineering study of existing Area Radiation Monitors (ARM's)

and Process Radiation Monitors (PRM's) to determine the upgrading necessary

to the monitoring system to provide adequate accident detection and

classification and post-accident radiation mapping capabilities to meet

ANSI-N320.

Incorporate the results of the study in the Emergency Plan

and the Emergency Plan Implementing Procedures.

(Section 4.2.1.2) (CAL-5.)

20.

Include in the Emergency Plan Implementing Procedures precautions limitations,

and references to other procedures used in the completion of the , emergency

response tasks.

(Section 5.1) (CAL-4.b.)

21.

Incorporate appropriate references to the Emergency Plan Implementing

Procedures in your 500 Series Procedures.

(Section 5.2) ( CAL-4.a.)

22. Complete the revision and expansion of your Emergency Plan Implementing

Procedures so that personnel are specifically directed in the completion

of all required emergency response tasks.

(Section 5.3) (CAL-4.b.)

23. Develop a method to determine offsite doses to the thyroid based on

measured and projected radiciodine concentrations. The method should

document the assumptions used, incorporate appropriate EPA-520 or ICRP

models, and be made consistent with the method used by the appropriate

offsite agencies.

(Section 5.4.2) (CAL-4.c.)

24.

Include all methods to be used in the performance-of the offsite radiological

surveys in Emergency Plan Implementing Procedures.

(Section 5.4. 2.1)

(CAL-4.b.)

25.

Include all methods to be used in the performance of the onsite radio-

logical surveys in the Emergency Plan Implementing Procedures.

(Section

5.4.2.2) (CAL-4.b.)

26.

Include the procedures to be followed for in plant radiological control

under emergency situations in the Emergency Plan Implementing Procedures.

(Section 5.4.2.3) (CAL-4.b.)

27.

Revise your procedures for performing post-accident reactor coolant

sampling using interim-type equipment. This revision should include, but

not be limited to, consideration of the following: personnel radiation

exposure limits, dosimeters to be used by personnel, radiation level of

coolant that may be sampled, points where sampling should be terminated

due to radiation levels, determination of path of travel to and from

sample location, sample size, and sample labeling.

(Section 5.4.2.4)

( CAL-2. b. )

28.

Develop procedures to address the analysis of high activity coolant

samples consistent with criteria detailed in Section II.B.3 of NUREG-0737.

Such procedures should include specific radiation protection provisions

to assure personnel whole body and extremity limits are not exceeded,

should provide for use of adequate shielding from elevated post-accident

background direct radiation exposure rates, and should identify proper

disposition of samples following analysis.

(Section 5.4.2.5) (CAL-2.b.)

0FFICIAL RECORD COPY

f

.

.

O

Appendix A

4

29.

Develop a procedure for performing post-accident containment air sampling

consistent with NUREG-0737 Section II.B.3 criteria. The procedure should

include specific provisions for collecting particulate, iodine, and gas

samples, specific instructions for the safe handling of highly radioactive

samples, a sketch of the sampling location and equipment, and assignment

of responsibility for performance of planning activities consistent with

positions defined in the Emergency Plan organization.

(Section 5.4.2.6)

(CAL-2.b.)

30.

Develop procedures for anald.:ing containment air samples under the post-accident

conditions specified by NUREG-0737 Section II.B.3. and Table II.F.1-1.

Such procedures should incorporate specific personnel radiation protection

requirements.

(Section 5.4.2.7) (CAL-2.b.)

31.

Review and upgrade airborne effluent sampling procedures incorporating

specific radiation protection provisions appropriate for sampling effluent

streams using the design basis criteria of NUREG-0737, Table II. F.1-2.

(Section 5.4.2.8) (CAL-2.b.)

32. Develop procedures for the analysis of high activity airborne stack effluent

samples under post-accident conditions.

Procedures must address analysis

of radioiodines and particulates as a minimum and meet the criteria of

NUREG-0737, Table II.F.1-2.

Specific radiation protection concerns

applicable to high activity sample analysis shall be incorporated into

the procedures.

(Section 5.4.2.9) (CAL-2.b.)

0FFICIAL RECORD COPY

.

.

APPENDIX B

EMERGENCY PREPAREDNESS IMPROVEMENT ITEMS

Based on the results of the NRC's appraisal of GPU Nuclear Corporation's

Emergency Preparedness Program at the Oyster Creek Nuclear Generating Station

conducted January 4 - 15, 1982, the following improvements should be considered:

(References are to sections in NRC Region I Inspection Report No. 50-219/82-01).

1.

Expedite the hiring of permanent staff Emergency Preparedness Planners.

(Section 1.1)

2.

Define the authority of the Emergency Preparedness Supervisor over matters

concerning the implementation of the Emergency Plan.

(Section 1.2)

3.

Require Emergency Preparedness to review documents such as Emergency

Operating Procedures for adequacy from Emergency Preparedness standpoint

prior to the PORC review.

(Section 1.3)

4.

Include in the Emergency Plan Implementing Procedures checklists to

assure that key Initial Response (Onsite) Emergency Organization members

perform required functions.

(Section 2.1)

5.

Move the location of the technical leaders and experts and technical

information from the Parsippany Technical Functions Center to the onsite

Technical Support Center.

(Section 2.2)

6.

Include in the Emergency Plan Implementing Procedures checklists to

assure that key Full Mobilization (Offsite) Emergency Organization

members perform required functions.

(Section 2.2)

7.

Provide consistency among all the documents which specify emergency

response training.

(Section 3.1)

8.

Develop qualification criteria for all members of the emergency response

organization.

(Section 3.1)

9.

Include in the emergency training program the training of bargaining unit

personnel who would be used during an emergency response in appropriate

procedures used under emergency conditions.

(Section 3.1)

10.

Develop comprehensive lesson plans.

(Section 3.1)

11. Perform more hands-on type training with people dressed in the full

protection clothing and wearing respiratory protection.

(Section 3.1)

12.

Provide respiratory protection training for all members of the Radiolo-

gical Monitoring Teams (Section 3.1)

0FFICIAL RECORD COPY

-_

,

.

Appendix B

2

13.

Include more site-specific informtion in the " hazardous conditions"

section of the Mitigation of Core Damage Course.

(Section 3.1)

14. Provide written examinations and performance tests which demonstrate

training of personnel.

(Section 3.1)

15.

Provide retraining of personnel in changes to procedures and equipment

which occur between training periods.

(Section 3.1)

16. Train personnel prior to assigning them on an emergency organization

roster.

(Section 3.2)

17.

Provide Red Cross Standard First-Aid Multimedia Training for Damage

,.

Control Radiological Control Team members.

(Section 3.2)

~

18. Make the updated Emergency Plan and Emergency Plan Implementing Procedures

available in both the control room and in the Group Shift Supervisor's

office. (Section 4.1.1.1)

19.

Provide more space in the area of the control room communications systems.

(Section 4.1.1.1)

20.

Provide a mobile laboratory to perform reactor coolant and other pertinent

analyses during emergencies.

(Section 4.1.1.9)

21.

Provide more room in the First Aid Station for personnel and equipment

and for storage of emergency supplies.

(Section 4.1.2.2)

22.

Provide decontamination facilities at the Berkeley Operating Headquarters

Remote Assembly Area.

(Section 4.1.2.3)

-23.

Provide for replacement clothing in the decontamination facilities.

(Section 4.1.2.3)

24.

Provide emergency equipment and supplies in emergency kits as specified

in procedure EPAP-05, Rev. O.

(Section 4.2.1.1)

25.

Provide proper operable equipment for the offsite monitoring teams by

assuring that scalars are-operable, check sources are available, power

sources for air samplers are available, filter chambers in air samplers

accommodate the filter cartridges, and air samplers can be placed to take

a representative sample.

(Section 4.2.1.1)

26.

Provide either a redundant power supply to the meteorological tower or

develop a procedure for obtaining representative meteorological data if

the tower measurements are unavailable.

(Section 4.2.1.4)

27.

Establish a remote interrogation capability for the meteorological data

for use by offsite agencies.

(Section 4.2.1.4)

0FFICIAL RECORD COPY

. _ _

_

_

_

_

.

.

Appendix B

3

28. Establish a. supplementary meteorological tower or develop procedures to

assess the possible effects of sea breeze circulations on the effluent

plume transport.

(Section 4.2.1.4)

29.

Develop p*ocedures that assure the testing and maintenance of communications

equipment and provide instructions for the use of all communication

systems and equipments.

(Section 4.2.3)

30.

Identify communicators with regard to technical background, and train and

qualify the communicators prior to assignment.to the emergency organization.

(Section 4.2.3)

31.

Provide a back-up power supply system for all communications equipment

identified for usage during an emergency.

(Section 4.2.3)

32. Designate in the procedure (EPIP-14) where damage control teams would

acquire specific equipment required to perform their function.

(Section

4.2.4)

33.

Formalize responsibility for the control of vehicles designated for

emergency use, revise the Pnergency Plan Implementing Procedures to

reflect this vehicle control, and assure the vehicles are maintained in a

state of readiness for emergency use.

(Section 4.2.6)

34. Reexamine all Emergency Action Levels (EALS) to determine if the information

is readily available to control room personnel.

(Section 5.3)

35. Address the. limitations on the use of normal operating procedures under

emergency conditions in the normal operating procedures. (Section 5.3)

36.

Simplify and consolidate the notification requirements in EPIP's 1-5.

(Section 5.4.1)

37. Define the responsibility for dose assessment in the procecure.

(Section

5.4.2)

38.

Provide additional training in dose assessment.

(Section 5.4.2)

39.

Implement computer analysis for dose assessment at the TSC and control

room.

(Section 5.4.2)

40.

Develop qualification requirements for Offsite Monitoring Team members.

(Section 5.4.2.1)

41.

Define a central collection and storage location for environmental samples.

(Section 5.4.2.1)

42. Develop qualification requirements for Onsite Monitoring Team members.

(Section 5.4.2.2)

0FFICIAL RECORD COPY

.

.

Appendix B

4

L

43. Define the emergency organization responsible for providing in plant-

radiological control, including in plant radiological surveys, during-

emergencies. (Section 5.4.2.3)

44. Develop qualification requirements for in plant monitoring team members.

These requirements should include respiratory protection training and a

-respirator fit test.

(Section 5.4.2.3)

i

45.

Incorporate sketches of sampling facility location and equipment set up

in the sampling procedures.

(Section 5.4.2.8)

d

46.

Delete the references to the non-existent procedure 804.38, Post-Accident

'

Sampling, or develop such a procedure.

(Section 5.4.2.8)

47.

Develop a procedure or plan documenting methods and philosophy for the

storage and handling of large volumes of contaminated water.

(Section

5.4.2.10)

48.

Determine the need; and, if required, develop a procedure for post-accident

sampling of torus water, incorporating specific radiation protection

criteria.

(Section 5.4.2.10)

49. Assess the impact of elevated background radiation levels which could

'

result from direct radiation from the reactor building or stack under-

major release conditions on the normal analytical laboratory procedures.

Based on the assessment results, either revise the normal procedures or

develop new procedures.

(Section 5.4.2.11)

,

50. Make the emergency exposure criteria for emergency workers consistent-

with'the EPA Emergency Worker and Lifesaving Activity Protective Action

Guides given in EPA-520/1-75-001.

(Section 5.4.3.1)

51.

Require the monitoring and decontamination of personnel assembled at the

Monitor and Control Area prior to evacuation, if possible.

(Section 5.4.

3.4)

52.

Specify action levels which require further assessment of personnel

radiation exposure and/or contamination, and define the assessment techniques

to be used.

(Section 5.4.3.4)

53.

Develop specific security procedures and/or checklists which consolidate

the security organization emergency duties.

(Section 5.4.4)

54. Develop a procedure for the security organization which addresses the

manner in which the security system should be left should the security

'

force be ordered to evacuate.

(Section 5.4.4)

55. Address emergency repair / corrective actions in the Emergency Plan and the

training program.

(Section 5.4.5)

f

0FFICIAL RECORD COPY

..

,- ..

i

.

Appendix B

5-

56.

Develop appropriate Emergency Plan Implementing Procedures (EPIP's) which

address repair and corrective actions under emergency conditions.

These

EPIP's should specify the location of tools, radiation detection instruments,

and communication equia-

, and should address personnel radiological

protection.

(Section 5.4.a)

57.

Integrate the Emergency Public Information Plan into the Emergency Plan

and prepare and include appropriate public information procedures in the

Emergency Plan Implementing Procedures. _ Include the Communications

personnel in the appropriate Emergency Response Organizations, and train

the personnel in their emergency response functions.

(Section 5.4.7)

t

58.

Develop a mechanism to assure that all emergency response personnel

participate in drills or exercises and that some of the drills or exercises

are started during the off shifts.

(Section 5.5.2)

59.

Establish the quarterly review and updating of telephone numbers used in

the Emergency Plan Implementing Procedures.

(Section 5.5.3)

60. Address emergency actions to be taken concerning that portion of the 10

mile radius surrounding the Oyster Creek Nuclear Generating Station -

comprised by the Atlantic Ocean.

In particular, reach an agreement with

the U. S. Coast Guard for their support during an emergency.

(Section

6.1)

61.

Expedite the final preparation, printing, and distribution of the emergency

information pamphlet to the public.

(Section 6.2)

62.

Perform the exercises and drills in accord with the program described in

the Emergtncy Plan, especially Table 8.2 and EPAP-16.

(Section 7.1)

63.

Expedite the accomplishment of needed improvements in energency prepared-

ness as indicated by the critiques of the drills and exercises.

(Section

7.1)

e

3

0FFICIAL RECORD COPY

..

-

-

.

.

l

!

,

.

s

APPENDIX C

r

EMERGENCY PREPAREDNESS EVALUATION REPORT

BY THE

DIVISION OF EMERGENCY PREPAREDNESS

OFFICE OF INSPECTION AND ENFORCEMENT

U. S. NUCLEAR REGULATORY COMMISSION

IN THE MATTER OF

GYSTER CREEK NUCLEAR GENERATING STATION

DOCKET NO. 50-219

MARCH 1982

1'

..

.

_ _ _ _ _ _ _ _

.

.

Appendix C

2

INTRODUCTION

The GPU Nuclear Corporation filed with the Nuclear Regulatory Commission

revisions to the Oyster Creek Emergency Plan, dated January 29, 1982.

The plan was reviewed against the sixteen planning standards in Section 50.47

of 10 CFR Part 50, the requirements of Appendix E to 10 CFR Part 50, and the

criteria of NUREG-0654/ FEMA-REP-1, Revision 1 entitled, " Criteria for Preparation

and Evaluation of Radiological Emergency Response Plans and Preparedness in

Support of Nuclear Power Plants," November 1980, which is endorsed by Revision

2 of Regulatory Guide 1.101.

This evaluation report follows the format of Part II of NUREG-0654 in that

each of the Planning Standards is listed and followed by a summary of the

applicable portions of the plan and the deficiencies that relate to that

specific standard.

The final section of this report provides our conclusions.

A separate report will be issued describing the findings and determinations of

the Federal Emergency Management Agency on the State and local emergency

response plans.

f

f

.

m.

~

_ _ __ _ _ _

.

.

.

Appendix C

3

EVALUATION

A.

ASSIGNMENT OF RESPONSIBILITY (ORGANIZATIONAL CONTROL)

Planning Standard

Primary responsibilities for emergency response by the nuclear facility licensee,

and by State and local organizations within the Emergency Planning zones have

been assigned, the emergency responsibilities of the various supporting organizations

have been specifically established, and each principal response organization

has staff to respond and to augment its initial response on a continuous

basis.

Emergency Plan

The Federal, State, and local organizations that are intended to be part

of the overall response organization for Emergency Planning Zones are

identified.

Federal support is provided by the U. S. Department of

Energy.

The role of the State of New Jersey is described, and reference

is made to the New Jersey State Radiological Emergency Preparedness Plan

Local aid is available through the Ocean County Emergency Management

Agency.

The concept of operations and its relationship to the total effort are

described.

The Group Shift Supervisor shall initially assume the role of Emergency

Director.

The Emergency Director is identified as the individual who

shall be in charge of the emergency response.

The licensee will provide for 24-hour per day emergency response, including

24-hour per day manning of the communication links.

Written agreements have been established with the following support

l

l

organizations: Lacey Township First Aid Squad, Bayville First Aid Squad,

i

Community Memorial Hospital, Forked River Volunteer Fire Company, and the

i

Radiation Management Corporation.

The licensee is capable of continuous (24-hour) operations for a protracted

period.

The Emergency Support Director is vested with the authority to

expend corporate funds and utilize manpower and equipment as necessary to

i

mitigate or terminate the emergency situation.

l

l

DEFICIENCIES

The Plan requires revision and/or additional information as follows:

l

l

1.

Expand the section entitled, " Coordination with Government Agencies" to

include the role of the U. S. Coast Guard and the Ocean County Emergency

Management Agency. Also include the arrangements made with private

sector organizations such as General Electric and other utilities whose

assistance may be requested in an emergency.

,

i

l

'

_

_.

.

.

Appendix C

4

2.

Provide a block diagram depicting the interrelationships of the Oyster

Creek emergency response facilities with the offsite organizations having

a primary emergency response role.

Include all Federal, State, local,

and private sector organizations.

3.

Provide agreements with the New Jersey Department of Environmental Protection,

Bureau of Radiation Protection; New Jersay State Police, Office of Emergency

Management; Ocean County Emergency Management Agency; U. S. Coast Guard;

U. S. Department of Energy; General Electric Corporation; and any other

organizations whose services may be relied upon during an emergency.

4.

Explicitly identify the individual, by normal organizational title, who

will be resporisible for assuring continuity of resources during an emergency.

I

i

,

.

.-.

.-

.

-

__

.

.

Appendix C

5

\\

B.

ONSITE EMERGENCY ORGANIZATION

Planning Standard

On-shift facility licensee responsibilities for emergency response are unambiguously

defined, adequate staffing to provide initial facility accident response in

key functional areas is maintained at all times, timely augmentation of response

capabilities is available, and the interfaces among various onsite response

activities and offsite support and response activities are specified.

Emergency Plan

The onsite emergency organization of plant personnel and its relation to

the responsibilities and duties of the normal staff complement are addressed.

The Emergency Director is designated as the individual with the authority

and responsibility to immediately and unilaterally initiate any emergency

actions, including protective action recommendations to offsite author-

ities.

The position of the Emergency Director will initially be filled by the

Group Shift Supervisor until relieved by the on-call Emergency Director.

The functional responsibilities of the Emergency Director are specified.

The responsibility for recommending off-site protective measures may not

be delegated.

Personnel titles and major tasks to be performed by persons assigned to

the functional areas of emergency activity are specified in the plan.

'

The contractor and private organizations who may be requested to provide

technical assistance to and augmentation of the emergency organization

,

l

are identified.

l

The services to be provided by local agencies for handling emergencies,

including fire-fighting and medical services, are identified.

Copies of

letters of agreement are appended to the plan.

DEFICIENCIES

The plan requires revision and/or additional information as follows:

!

1.

The role of the Emergency Director is somewhat ambiguous, following the

l

arrival of the Emergency Support Director.

It appears that the latter

assumes the authority and responsibility for the overall control and

direction of the emergency response.

Upon arrival of the Emergency

Support Director, it-is not clear what functions, if any, remain with the

,

Emergency Director.

Resolve this apparent ambiguity to clearly define

'

who is in charge of what at the time when both the Emergency Director and

the' Emergency Support Director are present.

Depending on the resolution

of the above, it may be in order to transfer the title of Emergency

l

!

_.

_ __.

.

______-__ ___-_-______________________ _ ___ _ __-_ _ -_ _ _

- _ _ _ - _ _ -

.

.

Appendix C

6

Director to the individual having the overall control and direction of

the emergency response, and eliminate the title of Emergency Support

Director.

2.

Specify by title the individuals, including members from the corporate

staff, qualified to assume the position of Emergency Director and Emergency

Support Director.

3.

The description of the emergency organization staffing in the plan differs

so greatly from that set forth in Table B-1 of NUREG-0654, that a valid

comparison between the two cannot be made.

Provide a revised format

equivalent to Table B-1 of NUREG-0654.

If the minimum on-shift complement

and the 30 and 60 minute staffing requirements are deficient with respect

to the aforementioned table, provide a commitment to meet the minimum

staffing requirements in accordance with the schedule set forth in evaluation

criteria B.5 of NUREG-0654.

4.

Provide a figure depicting the interrelationships of Oyster Creek Station

with the various response org:nizations.

Include the technical support

center, operational support center, emergency operations facility, and

headquarters support.

5.

The various support services to be provided by the private sector (e.g.,

General Electric Corporation) should be supported by written agreements,

and the agreements should be appended to the plan.

These agreements

should contain the information set forth in criteria B.9 of NUREG-0654.

l

.

..

-

_ . _ - _ _ _ _ _ _ _ _ _ _

..

.

.

l

Appendix C

7

C.

EMERGENCY RESPONSE SUPPORT AND RESOURCES

Planning Standard

Arrangements for requesting and effectively using assistance resources have

been made, arrangements to accommodate State and local staff at the licensee's

near-site Emergency Operations Facility have been made, and other organizations

capable of augmenting the planned response have been identified.

Emergency Plan

The Emergency Director is indicated as the person authorized to request

Federal assistance.

The assistance to be provided by the Department of Energy and the Nuclear

Regulatory Commission is described in the plan.

The provision of support services needed to maintain Federal radiological

assistance is addressed in the plan.

Radiological laboratories available during an emergency are identified at

the Three Mile Island Nuclear Generating Station, and the Radiation

Management Corporation.

Nuclear and other facilities which can be relied upon to supply assist-

ance in an emergency are identified for fire fighting, ambulance, and

medical services, and radiological assessment.

DEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

Indicate the expected on-site arrival time for requested DOE assistance

under the Federal Radiological Monitoring and Assessment Plan.

2.

Identify the specific resources which are available to support the Federal

response.

3.

Describe the provisions for dispatch of a company representative to the

principal offsite governmental emergency centers.

. _ . .

.

.

Appendix C

8

0.

EMERGENCY CLASSIFICATION SYSTEM

Planning Standard

A standard emergency classification and action level scheme, the bases of

which include facility system and effluent parameters, is in use by the nuclear

facility licensee, and State and local response plans call for reliance on

information provided by facility licensees for determinations of minimum

initial offsite response measures.

Emergency Plan

The licensee has established an emergency classification scheme consist-

ent with the four emergency categories set forth in Appendix 1 to NUREG-0654.

The licensee has identified various initiating conditions and their

associated emergency action levels for events that could initiate one of

the four emergency classes.

Most of the specific initiating conditions

listed in Appendix 1 to NUREG-0654 have been addressed.

DEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

It appears that the Emergency Action Levels (EALs) associated with initiating

events having potential offsite dose consequences have been established

on a very conservative basis with respect to NUREG-0654 recommendations.

As a result, these conservative EALs run counter to the objective of

achieving uniformity and consistency throughout the industry with respect

to emergency classification. .For example, it appears that a " General

Emergency" could result from events involving fuel handling and off gas

system accidents because of the conservative EAL values.

However, it is

doubtful that such accidents could realistically produce offsite doses in

excess of EPA Protective Action Guides (PAGs).

Normally, it is considered

that accidents leading to or involving at least core degradation are

necessary to produce conditions justifying the declaration of a " General

i

Emergency."

It is requested that you reevaluate that portion of your

I

emergency classification scheme based on projected dose consequences in

.

light of the recommendations set forth in NUREG-0654.

!

i

2.

Establish Emergency Action Levels (EALs) for each " General Emergency"

initiating condition specified in Appendix 1 to NUREG-0654.

The EALs

should be observables (e.g., instrument readings, equipment status indications,

l

alarm annunicators) which are both necessary and sufficient to explicitly

and uniquely characterize each initiating condition. Also insure that

,

!

the EALs specified for all of the initiating conditions leading to the

remaining three categories of emergencies are both necessary and sufficient

'

to uniquely characterize the event.

l

l

- -

--

-

-

- _.-

- - _ .

.

.

.

.

__

. _ -

.

.

Appendix C

9

E.

NOTIFICATION METHODS AND PROCEDURES

Planning Standard

Procedures have been established for notification by the licensee of State and

local response organizations and for notification of emergency personnel by

all response organizations; the content of initial and followup messages to

response organizations and to the public has been established, and means to

provide early notification and clear instruction to the populace within the

plume exposure pathway Emergency Planning Zone (EPZ) have been established.

Emergency Plan

Notification procedures have been established, consistent with the emergency

classification scheme.

Provisions have been made for verification of

emergency messages.

Procedures for alerting, notifying, and mobilizing emergency response

personnel are described in the plan.

The contents of the initial and followup emergency messages to be sent

from the plant conform with the recommendations set forth in NUREG-0654.

The message format to be used is included in the emergency plan implementing

procedures.

An early warning system has been provided for alerting the population-at-risk

within the plume exposure pathway EPZ.

The system includes fixed sirens

together with the Emergency Broadcast System and supplemented by vehicles

with mobile loudspeakers. When required, the siren system will be activated

by the Ocean County Emergency Coordinator.

DEFICIENCIES

The following requires revision and/or additional information as follows:

1.

Provide copies of the written messages intended for release to the public

in the event of a serious emergency.

If these are still in the process

of being developed, provide a schedule for their completion.

-

_ _ - _ - _ _ - _

..

.

.

_ _ .

. _ _ _ _ _ -

.

.

Appendix C

10

F.

EMERGENCY COMMUNICATIONS

Planning Standard

Provisions exist for prompt communications among principal response organiza-

tions to emergency personnel and to the public.

Emergency Plan

24-hour notification to, and activiation of, the State / local emergency

response network are provided.

Communications with State / local governments within the EPZ's are provided.

Communications as needed with Federal emergency response organizations

are provided.

Communications between the nuclear facility, State, and local Emergency

Operation Centers (E0Cs), and radiological monitoring teams are provided.

Provisions are made for alerting or activating emergency response personnel.

Communication by the licensee with NRC headquarters and the NRC Regional

Office is provided.

DEFICIENCIES

1.

Specify the organizational titles and alternates for both ends of the

communication links which would be involved in initiating emergency

response actions.

2.

A diverse means of communication, such as a radio system, should be

available between the site and the primary offsite response agency.

It

is not clear that such radio communications are available with the Ocean

County Emergency Operations Center.

3.

Identify the provisions for communications with the U. S. Coast Guard,

since they are a primary response organization within the plume exposure

pathway EPZ.

4.

Describe the provisions for coordinated communications involving the

plant, ambulance service, and the hospital support facilities.

--_

_ _ _ _ _ - _ _ _ .

.

.

Appendix C

11

G.

PUBLIC EDUCATION AND INFORMATION

Planning Standard

Information is made available to the public on a periodic basis on how they

will be notified and what their initial actions should be in an emergency

(e.g., listening to a local broadcast station and remaining indoors), the

principal points of contact with the news media for dissemination of informa-

tion during an emergency (including the physical location or locations) are

established in advance, and procedures for coordinated dissemination of information

to the public are established.

Emergency Plan

.The points of contact and physical locations for use by news media during

an emergency (Media Center) are designated.

The Manager-Communication Services has the overall responsibility for

public information.

He will designate a spokesperson who will be available

to the media for briefings and questions.

Arrangements for timely exchange of information among designated spokespersons

are established.

Annual programs to acquaint news media with the emergency plans, information

concerning radiation, and points of contact for release of public information

in an emergency are provided.

DEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

Describe the program to be provided for a coordinated yearly dissemina-

tion of information to the public regarding how they will be notified and

what their actions should be in an emergency.

Include the specific items

addressed in evaluation criteria G.1 of NUREG-0654.

2.

Provide a sample copy of the emergency preparedness information which

will be provided for both the resident and transient population around

the site.

. .$.

3.

Describe the provisions made for ensuring that the transient population

~

within the plume exposure pathway EPZ will have access to appropriate

information in advance that would be helpful in the event of a serious

j

emergency.

l

4.

Describe the provisions for accommodating a limited number of the news

media at the nearsite Emergency Operations Facility (EOF).

S' .

Describe your coordinated arrangements for rumor control during emergencies.

I

,

_

_,

-.

a

_

.

.

Appendix C

12

H.

EMERGENCY FACILITIES AND EQUIPMENT

-

Planning Standard

Adequate emergency facilities and equipment to support the emergency response

.

are provided and maintained.

Emergency Plan

A Technical Support Center (TSC) and Operational Support Center (OSC)

have been established. An Emergency Operations Facility (EOF) will be

established on the Forked River site.

In addition, an Environmental

,

Assessment Command Center has been established for the analysis of field

monitoring data and for direction of the offsite radiological monitoring

teams.

-

An onsite meteorological system including instrumentation, data collect-

ion, and transmission to the control room is in place.

A general description of the onsite radiological monitoring system is

provided.

Provisions have been made to obtain offsite meteorological data from the

National Weather Service in case of failure of onsite equipment.

Offsite radiological monitors including ratemeters and sampling devices

have been provided.

Emergency instruments and equipment are checked quarterly.

Sufficient

reserves are provided to replace those removed from service for mainten-

ance and/or calibration.

DEFICIENCIES

i

The plan requires revision and/or additional information as follows:

1.

In addition to the Technical Support Center (TSC), the plan describes an

Emergency Control Center (ECC) for the purposes of " initial assessment

and coordination of corrective actions for all emergency conditions."

It

appears that the ECC is in conflict with the functional objectives established

for the TSC from the standpoint of both its purpose and location in the

area of the reactor control room.

It is recommended that the functions

proposed for the ECC be handled from the TSC.

Expand the discussion of

the TSC in sufficient detail to enable evaluation against the criteria

set forth in NUREG-0696.

2.

It appears from the description of the offsite emergency response facilities

that the functions of the EOF have been spread among the nearsite EOF,

farsite EOF, and the Parsippany Technical Functions Center.

Reevaluate

the functions of these three facilities in light of the criteria in

NUREG-0696, and resubmit a detailed description of the E0F for evaluation

against the aforementioned criteria.

__

.

.

Appendix C

13

3.

Identify the onsite monitors for obtaining seismic and hydrologic information

which may be used for initiating emergency measures in accordance with

criteria H.5.a of NUREG-0654.

-

4.

Identify the onsite radiological and process monitoring systems in accordance

with criteria H.5.b and H.5.c of NUREG-0654.

The monitors identified

should include those used for obtaining Emergency Action Levels for the

appropriate initiating conditions listed in Appendix 1 to NUREG-0654.

Include instrument ider.tification, location, and range.

5.

Identify the fire and combustion products detectors whicn may be used for

initiating emergency measures in accordance with criteria H.5.d of NUREG-0654.

6.

Describe your provisions for obtaining offsite information regarding

hydrologic and seismic data as specified in criteria H.6.a of NUREG-0654.

7.

As part of your description of the offsite radiological monitoring program,

provide an area map showing the location of rate meters, sampling devices,

and TLDs in relation to the plant as part of the plan. Also indicate if

the dosimetry provided meets the minimum requirements of the NRC Radiological

Assessment Branch Technical Position for the Environmental Radiological

Monitoring Program.

8.

Although the plan discusses the onsite meteorological instrumentation, it

is insufficient to determine compliance with the criteria set forth in

NUREG-0654.

Provide detailed information which explicitly addresses the

criteria in Appendix 2 of the aforementioned document.

- .-

_

-.

.

- .

. - .

--

.

.

.

Appendix C

14

-

I.

ACCIDENT ASSESSMENT

Planning Standard

Adequate methods, systems, and equipment for assessing and monitoring actual

or potential offsite consequences of a radiological emergency condition are in

use.

Emergency Plan

Availability of resources to provide initial and continuing assessment

throughout the course of an accident is discussed in general terms.

Methods and techniques for determining the source term of releases within

plant systems and the magnitude of the release of radioactive materials

is addressed in the Emergency Plan Implementing Procedures.

The relationship between effluent monitor readings and onsite and offsite

exposures and contamination for various meteorological conditions is

provided in the procedures.

The methodology for determining the release rate / projected dose if assessment

instrumentation is inoperable or offscale is addressed.

The capability to provide field monitoring within the plume exposure

pathway EPZ is described.

DEFICIENCIES

1.

As part of the description regarding onsite capability and resources to

provide initial and continuing assessment throughout the course of an

accident, include post-accident sampling capability, radiation and effluent

monitors, in plant iodine instrumentation, and containment monitoring.

Provide sufficient detail to enable evaluation against clarification

items II.B.3, II.F.1, and III.O.3.3 in NUREG-0737.

1

'

2.

Provide detailed information in the plan on the methods and techniques

used for determining the source term of releases of radioactive material

within plant systems. As an aid in assessing the extent of potential

core damage include plots which show the containment radiation monitor

'

reading vs. time following release of gap activity, 1% release of fuel

inventory, and 10% release of fuel inventory.

3.

Indicate the meteorological information that will be provided to an

offsite NRC center and made available to State agencies for their use.

4.

Indicate how and when field monitoring teams will be activated, their

composition, means of communication and transportation, the kinds of

monitoring equipment that will be used, and how soon monitoring teams can

be deployed offsite.

__-

.

.

.

. .

.

.

Appendix C

15

5.

Describe your capability to detect and measure radiciodine concentrations

in air in the plume exposure pathway EPZ as low as 10-7 pCi/cc under

field conditions.

6.

Describe the means for relating measured field contamination levels _to

dose rates for applicable isotopes listed in Table 3 of NUREG-0654.

.

___

_ _ _ _ _ _ _ _

__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ - _ _ -

_.

.

.

Appendix C

16

J.

PROTECTIVE RESPONSE

Planning Standard

A range of protective actions have been developed for the plume exposure

pathway EPZ for emergency workers and the public.

Guidelines for the choice

of protective actions during an emergency, consistent with Federal guidance,

are developed and in place, and protective actions for the ingestion exposure

pathway EPZ appropriate to the locale have been developed.

Emergency Plan

The means used to warn plant employees and visitors that an accident has

occurred have been established.

Provisions have been made for respiratory protection devices and protective

clothing for onsite emergency personnel.

Provision has been made for the evacuation of non-essential onsite personnel.

Prompt notification will be made directly to State and local authorities

responsible for implementing protective measures by the Emergency Director

when an accident could actually or potentially affect individuals within

the plume exposure pathway EPZ.

Evacuation time estimates for the population within the plume exposure

pathway EPZ are provided.

The plan contains maps and tables showing population distributions around

the plant.

The plan describes the early warning sjstem which could be used for

notifying all segments of the transient and resident population in the

event of a serious accident.

DEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

The plan establishes the means to warn or advise onsite employees and

visitors.

Describe the means used to warn or advise contractor / construction

personnel or those individuals who may be outside the protected area but

inside the owner controlled area. Also, specify the time required to

notify individuals who might be beyond the range of the onsite emergency

signals.

2.

Discuss the means that will be used to transport people to the offsite

assembly location (s), and alternative routes that could be used for

various wind directions or in case of inclement weather.

Provide a map

showing the alternate evacuation routes from the plant site.

_ _ _ _ _ _ _ _ _ _ _ _ _ _

.

..- _

.

.

..-

,

_ _ _

._ _

._-

. .

.

<

Appendix C

17

3.

Indicate the provisions for decontamination of evacuated personnel at the

remote assembly area.

4.

Indicate that the accountability for onsite personnel can be accomplished

within 30 minutes from the start of an emergency.

5.

Describe the availability of radioprotective drugs for onsite emergency

personnel.

6.

Provide a discussion of the decision making process, including the bases,

to be used by the Emergency Director in arriving at a choice of recommended

offsite protective actions in the event of a serious emergency. Discuss

the consideration given to the local protection afforded by residentist

units and other shelters as part of the bases for selecting recommended

protective actions for the plume exposure pathway during emergency conditions.

.

d

4

.

w

r

-

.

M'

-

""

v

n-'

wan

-w4m.

e-

m

--

-~-

,,,,

_,.,e

--,

- - _ . , .

-

_ _ -

-

- . _ _

.

.

Appendix C

18

K.

RADIOLOGICAL EXPOSURE CONTROL

planning Standard

Means for controlling radiological exposures in an emergency are established

for emergency workers.

The means for controlling radiological e'xposures shall

include exposure guidelines consistent with EPA Emergency Worker and Lifesaving

Activity Protective Action Guides.

Emergency Plan

Onsite exposure guidelines consistent with the recommendations of the

National Council on Radiation Protection have been established for emergency

workers.

An onsite radiation protection program has been established for emergency

situations including methods to implement exposure guidelines. The plan

identifies the Emergency Director as the person authorized to approve

emergency workers to exceed 10 CFR Part 20 exposure limits.

,

The means for radiological decontamination of emergency personnel and

disposal of contaminated waste have been established.

OEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

The plan indicates that the methods and conditions for permitting personnel

to receive emergency radiation exposures, including the provisions for

expeditious decisions in such cases, is described in the implementing

procedures.

Identify these procedures by number and title or, as an

alternath e, provide a synopsis in the plan itself.

2.

Describe the capability for providing 24-hour a day determination of

radiation doses to emergency workers, distribution and reading of dosimeters,

and maintenance of dose records.

i

3.

Identify the onsite contamination control measures for area access control

and for food and potable water supplies.

4.

Although the plan discusses the general capability for decontamination,

indicate the decontaminants available for radioiodine contamination of

the skin for relocated onsite personnel.

.

=

n

e

-

-

-

..

..

_

_

,

.

Appendix C

19

L.

MEDICAL AND PUBLIC HEALTH SUPPORT

Planning Standard

!

Arrangements are made for medical services for contaminated injured individuals.

Emergency Plan

Arrangements have been n.ade for local and backup hospital and medical

services having the capability for handling contaminated individuals, and

for the evaluation and treatment of radiation exposure and uptake.

Onsite first aid capability is provided.

Arrangements have been made to transport victims of radiological accidents

to medical support facilities.

.

~

i

i

!

.

--

_

-

_ _

. - , .

_

_-

.

__ .

.

.

Appendix C

20

M.

RECOVERY AND REENTRY PLANNING AND POSTACCIDENT OPERATIONS

Planning Standard

General plans for recovery and reentry are developed.

Emergency Plan

General plans and procedures for reentry and recovery are developed, and

i

the means are described by which decisions are reached to relax protective

measures.

The structure, functions, and membership of the facility recovery organization

are described.

Means are specified for informing members of the response organizations

that a recovery operation is to be initiated.

A method for periodically estimating total population exposure is established.

.

.

1

,

.

.

,

- . , . _ _

a-

-

. -.

--

- ,, _ -

_.

.__

.

.

Appendix C

21

N.

EXERCISES AND DRILLS

Planning Standard

Periodic exercises are (will be) conducted to evaluate major portions of

emergency response cabilities, periodic drills are (will be) conducted to

develop and maintain key skills, and deficiencies identified as a result of

exercises or drills are (will be) corrected.

Emergency Plan

An annual preparedness exercise that simulates an emergency that results

in offsite radiological releases which would require response by offsite

authorities is provided.

The scenario for the annual exercise will be varied from year to year to

assure that the major alements of the plan and the preparedness organizations

are tested at least once in a five year period.

Monthly communications drills will be conducted with State and local

-

governments within the plume exposure pathway EPZ. Quarterly communica-

tions drills will be conducted with Federal emergency response organiza-

tions and States within the ingestion pathway EPZ. Annual communication

drills will be conducted between the licensee, State and County emergency

operations centers, and the field survey teams.

Fire drills are cunducted in accordance with the plant Fire Protection

Plan.

Provisions are made for an annual medical emergency drill, involving a

simulated contaminated individual, which requires participation by the

local support services.

An annual radiological monitoring drill, including the collection and

analysis of sample media, is provided.

A semi-annual Radiological Controls drill will be conducted to test the

response to and analysis of simulated elevated airborne and liquid samples.

The scenarios to be developed for the drills and exercises will contain

the elements outlined in NUREG-0654.

Provision is made for a critique of the exercise as soon as practical

after it is held in which the actions and interactions of response organizations

can be evaluated.

The Supervisor-Emergency Preparedness is responsible for implementing

corrective actions based on observer and participant comments on the

exercise or drill.

.

v

.

,

n

_

.

.

Appendix C

22

DEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

Indicate that the drills will be supervised and evaluated by a qualified

drill instructor.

2.

Communications with the NRC shall be tested monthly in accordance with

paragraph E.9.d of Appendix E of 10 CFR Part 50. Also, the communications

drills should include the aspect of understanding the message content.

-

3.

Annually include in the Radiological Controls drill the analysis of

inplant liquid samples with actual elevated radiation levels, including

use of the post-accident sampling system.

4.

Discuss the mix of structured and less structured aspects of the program

which will allow free play for decision making during drills and exercises.

>

f

4

4

1

,

.

Appendix C

23

0.

RADIOLOGICAL EMERGENCY RESPONSE TRAINING

Planning Standard

i

Radiological emergency response training is provided to those who may be

called on to assist in an emergency.

Emergency Plan

Onsite emergency groups receive formal, as well as practical, training

during drills. A formalized training program has been established to

ensure that all personnel who actively participate in a radiation emergency

maintain familiarity with their responsibilities.

First aid personnel receive Red Cross Multi-Media training.

A specialized training program has been established for the various

categories of emergency perstnnel responsible for the implementation of

the plan.

,

The licensee has provided for arinual retraf ning of personnel with emergency

response duties.

DEFICIENCIES

The plan requires revision and/or additional information as follows:

1.

Describe the site specific training available to those offsite response

organizations whose assistance may be required in the event of an emergency.

Training for hospital personnel, ambulance crews, police, and fire departments

should include the procedures for notification, basic radiation protection,

and their expected roles.

For those support organizations who may be

brought onsite, training should include site access procedures and the

identity of onsite personnel who will control the organizations' activities.

2.

Include provisions in your training program for on-the-spot correction of

erroneous performance during drills and a demonstration of the proper

performance by the instructor.

3.

In order to obtain a better understanding regarding the scope of the

training program, provide the number of classroom hours for each of the

personnel categories identified in Table 8.1 of the plan.

_ _ _ - _ _ _ _ _ _ _ _

.

.

,

,

Appendix C

24

l

.

P.

RESPONSIBILITY FOR THE PLANNING EFFORT:

DEVELOPMENT, PERIODIC REVIEW AND DISTRIBUTION OF EMERGENCY PLANS

Planning Standard

Responsibilities for plan development and review and for distribution of

emergency plans are established, and planners are properly trained.

Emergency Plan

The individual with overall authority and responsibility for radiological

emergency response planning is the Vice President, Nuclear Assurance.

The Supervisor-Emergency Preparedness has the responsibility for development

and updating of the emergency plans, and for coordination of the emergency

plans with other responsible organizations.

The Emergency Plan and its implementing procedures will be reviewed

annually.

Procedures for implementing the Emergency Plan are listed in procedure

number and title.

The plan contains a detailed table of contents and a cross-reference to

the evaluation criteria in NUREG-0654.

,

DEFICIENCIES

j

The plan requires revision and/or additional information as follows:

1.

Describe the training provided for the individuals responsible for the

emergency planning effort.

2.

Identify in Appendix B the section of the plan to be implemented by each

procedure.

3.

In accordance with paragraph 50.54(t) of 10 CFR Part 50, indicate that an

independent review of the emergency preparedness program shall be conducted

every 12 months. The review shall include an evaluation for adequacy of

interfaces with State and local governments, drills, exercises, capabilities,

and procedures. Also identify the management controls to be used for

evaluation and correction of the review findings.

4.

Indicate that the telephone numbers in the emergency procedures will be

updated quarterly.

.

4

..

-

,

--

-

,

. . _ .

,

.-

-

--

__

-

.

i

Appendix C

25

CONCLUSION

Based on our review, we conclude that the Oyster Creek Emergency Plan, upon

satisfactory correction of the previously identified deficiencies, will meet

the planning standards set forth in NUREG-0654, Revision 1, " Criteria for

Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness

in Support of Nu-lear Power Plants," November 1980.

The NRC evaluatior. _n the overall state of emergency preparedness for the

Oyster Creek site will be made following review of the findings and determina-

tions made by FEMA on the State and local emergency response plans, and the

i

review of the joint exercise held to demonstrate the capability to implement

i

the onsite and offsite plans.

.. ,

_

.

.

-.

-.

.

_

. _ _ .

.

.. .

-

_-

- -.