ML20054G860

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-321/82-11 & 50-366/82-11 on 820329-0402 & Notice of Violation
ML20054G860
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/21/1982
From: Dance H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Kelly R
GEORGIA POWER CO.
Shared Package
ML20054G848 List:
References
NUDOCS 8206220361
Download: ML20054G860 (2)


See also: IR 05000321/1982011

Text

-

eaw

.

l

>

APR 211982

!

l

l

l

Georgia Power Company

ATTN: Mr. R. J. Kelly

Executive Vice President

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

-

Subject: Report Nos(50-321/82Qand 50-366/82-11

This refers to the routine safety inspection conducted by Mr. L. A. Franklin of

this office on March 29 - April 2, 1982, of activities authorized by NRC Opera-

ting License No. DPR-57 and License No. NPF-5 for the E. I. Hatch facility. Our

preliminary findings were discussed with Mr. T. V. Greene, Assistant Plant

Manager, at the conclusion of the inspection.

Areas examined during this inspection included radiation protection procedures.

Within these areas, the inspection consisted of selective examinations of proce-

dures and representative records, interviews with personnel, and observations by

the inspector.

During the inspection, it was found that certain activities under your license

appear to violate NRC requirements. This item and references to pertinent

requirements are listed in the Notice of Violation enclosed herewith as

Appendix A. Elements to be included in your response are delineated in

Appendix A.

One new unresolved item is identified in the enclosed inspection report. This

item will be examined during subsequent inspections.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosure will

be placed in the NRC's Public Document Room unless you notify this office, by

telephone, within ten days of the date of this letter and submit written appli-

cation to withhold information contained therein within thirty days of the date

of this letter. Such application must be consistent with the requirements of

2. 790( b)( 1) .

The responses directed by this letter and the enclosures are not subject to the

clearance procedures of the Office of Management and Budget as required by the

Paperwork Reduction Act of 1980, PL 96-511.

8206220361 820609

PDR ADOCK 05000321

0 PDR

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

r . .

.

'

APR 211982

Georgia Power Compar,y 2

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

M

H. C. Dance, Chief

Reactor Projects Branch 2

Division of Project and

Resident Programs

Enclosure:

Appendix A, Notice of Violation

cc w/ encl:

J. T. Beckham, Vice President and

General Manager-Nuclear Generation

M. Manry, Plant Manager

C. E. Belflower, Site QA Supervisor

bcc w/ encl:

NRC Resident Inspector

Hugh S. Jordan, Executive Secretary

Document Management Branch

State of Georgia

RII RII RII RII RII

~' ph

LAFranklin:ht Fkhr AFGi son JRogge HCJance

4//r/S2 y? 4f t /82 4/g/ 82 4/ /82 4/p /82