Forwards IE Insp Repts 50-424/82-05 & 50-425/82-05 on 820309-12 & Notice of Violation
ML20054G729
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/31/1982
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Kelly R
GEORGIA POWER CO.
Shared Package
ML20054G719 List:
References
NUDOCS 8206220246
Download: ML20054G729 (2)


See also: IR 05000424/1982005

Text

. '.4 .

MAR 311982

Georgia Power Company

ATTN: Mr. R. J. Kelly

Executive Vice President

P. O. Box 4545

Atlanta, GA 30302

Gentlemen:

Subject: Report Nos 42 82-05 a d 50-425/82-05

This refers to the routine safety inspection conducted by Mr. W. P. Kleinsorge of

this office on March 9-12, 1982, of activities authorized by NRC Construction

Permit Nos. CPPR-108 and CPPR-109 for the Vogtle facility. Our preliminary

findings were discussed with Mr. H. H. Gregory, III, Construction Project

Manager, at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your license

appear to violate NRC requirements. This item and references to pertinent

requirements are listed in the Notice of Violation enclosed herewith as

Appendix A. Elements to be included in your response are delineated in

Appendix A.

We have examined actions you have taken with regard to previously identified

enforcement matters and unresolved items. The status of these items is discussed

in the enclosed report.

Four new unresolved items are identified in the enclosed inspection report.

These items will be examined during subsequent inspections.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room unless you notify this office, by

telephone, within ten days of the date of this letter and submit written appli-

cation to withhold information contained therein within thirty days of the date

of this letter. Such application must be consistent with the requirements of

2.790(b)(1).

The responses directed by this letter and the enclosures are not subject to the

clearance procedures of the Office of Management and Budget as required by the

Paperwork Reduction Act of 1980, PL 96-511.

8206220246 820610

PDR ADOCK 05000424

G PDR

l

.

Georgia Power Company 2 MAR 311982

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

F. J. Long, Acting Chief

, Reactor Projects Branch 2

Division of Project and

Resident Programs

Enclosures:

1. Appendix A, Notice of Violation

2. Inspection Report Nos. 50-424/82-05

and 50-425/82-05

cc w/enci:

H. H. Gregory, III, Construction

Project Manager

E. D. Groover, QA Site Supervisor

D. O. Foster, Project General Manager