Informs That Util Response to Attachment 2 of TMI Action Item II.F.1 Re Sampling of Plant Effluents Is Satisfactory. Item Resolved
ML20052F713
Person / Time
Site: Pilgrim
Issue date: 05/10/1982
From: Vassallo D
Office of Nuclear Reactor Regulation
To: Morisi A
BOSTON EDISON CO.
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.F.1, TASK-TM NUDOCS 8205130457
Download: ML20052F713 (2)


Text

.

s O

MAY 101982 Distr.ibutto -

CDocket File

~

NRC PDR Docket No. 50-293 Local PDR ORB #2 Rdg

,Nh, pM/m DEisenhut 0 ELD 67 Mr. A. Victor Mortsi, Manager 01&E (1)

Q, 1

W Nuclear Operations Support Department KEccleston d **

V b-Boston Edison Company SNorris N

/

, 'g,4

/g M/C Nuclear NSIC h.;

800 Boylston Street EConner

(

'iP@

j[

Boston, Massachusetts 02199 ACRS (10)

Ab

  • \\ g [f '-

+

JHel temes

/

Dear Mr. Morisi:

CRAT5 gqQ)

SUBJECT:

NUREG-0737 ITEM II.F.1-2 " SAMPLING AND AtlALYSIS OF PLANT EFFLUENTS" RE: Pilgrim Nutlear Power Station We have completed our review of your October 16, 1981 submittal on this subject, as clarified by subsequent discussions with the NRC staff, and find that sufficient information to meet the objectives of Attachment 2 of Item II.F.1, NUREG-0737, has been provided.

Specifically Boston Edison Company has (1) described acceptable provisions for detemining iodine releases from plant effluent release points by field neasurements of the radioindine accumulated on filter - adsorber cartridges and (2) stated that procedures have been prepared for sample retrieval and transport, and for either the detemination of radioactivity retained on cartridge by laboratory analysis or by gross measurement using distance and shielding parameters and monograms for I-131 release determination.

Consequently, we find your description of the provisions taken by Boston Edison Company to satisfy Attachment 2 of Item II.F.1 to be satisfactory and consider this item resolved for Pilgrim.

In view of the above, no further response is necessary to our March 1,1932 letter on this subject.

Sincerely, an a LG i

Domenic B. Vassallo, Chief i

Operating Reactors Branch #2 l

Division of Licensing l

i cr.

so.

..+....

8205130457 820510 PDR ADOCK 05000293 P

PDR A \\'

s DL:0RB#S*

DL :0R,B #.3.-. DL:0RB#2 I

omce>

suomur)...K.E,c,c,],e,s,,t.o,n,:ms.YCConnE, DBVassal1o

.. 5../.. 7./. 8. 2.......

... 5../. 2../ 8..2.......

. 5../......./.8 2.......

omy 1 NRC FORM 313 (10 80) PvH M 0240 OFFIClAL RECORD COPY usam i,.i-m.e4

O Mr. A. Victor Morisi Boston Edison Company cc:

Mr. Richard D. Machon Pilgrim Station Manager Boston Edison Company RFD #1, Rocky Hill Road Plymouth, Massachusetts 02360 Henry Herrmann, Esquire Massachusetts Wildlife Federation 151 Tremont Street Boston, Massachusetts 02111 Plymouth Public Library North Street Plymouth, Massachusetts 02360 Resident Inspector c/o U. S. NRC P. O. Box 867 Plymouth, Massachusetts 02360 Ms. JoAnn Shatwell Office of the Attorney General Environmental Protection Division 1 Ashburton Place 19th Floor Boston, Massachusetts 02108 Ronald C. Haynes Regional Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 i