GPU Nuclear Corporation arsi a

,N Jersey 07054 201-316-7000 TELEX 136-482 Writer's Direct Dial Number.-

June 4, 1993 C000-93-2112 C321-93-2139 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 Gentlemen:

Subject:

Oyster Creek Nuclear Generating Station (0CNGS)

Docket'No. 50-219 Integrated Schedule Project List Semi-Annual Update Pursuant to condition 2.C.(10) of Operating License DPR-16, GPU Nuclear has implemented the Long Range Planning Program fn OCNGS. As required by Section V.A of the Plan, the following attachments are submitted to provide;the semi-annual project list update:

1 1.

Attachment A contains a new project list of Category A, B and C-projects, annotated by an asterisk (*) to ' identify new.

'l projects. Completed projects have been removed from the schedule listing. Also noted by a double asterisk (**) are budget re.tivity numbering _ changes.

2.

Attachment B_contains a summary of Category A, B, and_C projects which have' been completed, deleted, deferred, changed in scope. Category A and B projects which have had schedule changes are provided with explanations, as appropriate.

j 3(OI03 0

0 9306110147 930604 I (g PDR ADOCK 05000219 R

PDR GPU Nuclear Corporation is a subsidiary of General Pubic Utilities Corporation i-l-

. June 4, 1993 C000-93-2112 C321-93-2139 Page 2 Two (2) new Category B projects have been added to the list in Attachment A.

Three (3) Category B project schedule changes are discussed in Attachment B, and, one (1) activity change (scheduled period identification).. Pursuant to

.the LRPP for Oyster Creek, it will be assumed that you are in agreement with the actual Category B changes above if you do not respond to this submittal within 15 days of receipt.

Sin ly,

'/ '

)

e R. L. Long Vice President and irector Services & TMI-2 Divisions RLL/GMG/ pip cc: Director, Project Directorate I-4 l

Oyster Creek NRC Project Manager 1

Region I, Administrator Senior NRC Resident Inspector, OCNGS 1

'l

+: : a.-

?

ATTACHMENT A b

PROJECT LISTING-

j

.. INTEGRATED SCHEDULE.

SEMIANNUAL' UPDATE' (JUNE 1993) o a

B B

A i

1 l

l l

.i 1

.I i

.4

y..

~n OYSTER CREEK PROJECT LISTING LECEND NRC INTEGRATED SCHEDULE NEW PROJECTS.

    • -'BA NUMBER CHANGE CATEGORY

'B' PROJECTS SORT BY CATEGORY / CYCLE /BA STATUS AS OF 27MAY93 OBS BA DESCRIPTION CYCIE/

CLASSIFICATION NUMBER YEARS 1 315302-SEP TOPIC III-l 14 NRR INCORPORATE RESULTS IN AN UPDATE TO THE FSAR.

2 328030 CNTL RM HUMAN FACTORS DESGN REVIEW 14 NRR CR REPAINT, REFURBISH & RELABEL CR PANELS 1R THRU 10R,6XR,llXR,12R,12XR,14R,14XK, 16R AND 117,9XRE11R.NUREG 0737 SUP 1.

3 402910' C R RECORDERS 14 NRR CR REMOVE AND REPLACE 5 DEFICIENT / OBC 4LETE RECORDER GROUPS (7 RECORDERS),'AND DELETE 6 RECORDERS. NUREC 0737 SUPP. 1 4 402944 RX BLDG ROOF FRAME 14 NRR 119 ADD BRACING TO DIE R B ROOF STRUCTURE TO ENSURE ROOF STABILITY UNDER HIGH WIND

.14 ADS. NRC SEP S 409772 ACCESS CONTROL UPGRADE-CONTROL ROOM 14 NRR PROCUREMENT in INSTALLATION OF KEY CARD READER UNITS W/ ALARM FOR CONTROL ROOM AND NEW CABLE SPREADING ROOM

-- 6 328226 SQUG PROGRAM IMPLEMENTATION 14/15 NRR

' ESTABLISH SEISMIC QUALIFICATION FOR-OYSTER CREEK. SCOPE INCLUDES WALKDOWNS IN OUTAGE 15R AND EVALUATIONS 7' 328030 CNTL RM HUMAN FACTORS DESGN REVIEW 15 NRR-CR REPAINT, REFURBISH &' RELABEL CR PAhM 1R THRU 10R,6XR,11XR,12R,12XR,14R,14XR, 16R AND llF,9XRfillR.NUREG 0737 SUP 1.

t

...x..-

OYSTER CREEK PROJECT LISTING LEGEND N'R C INTEGRATED SCHEDULE NEW PROJECTS.

    • . BA NUMBER CILANGE CATEGORY

'B' PROJECTS SORT BY CATEGORY / CYCLE /BA STAIUS AS OF 27MAY93 OBS BA DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS 8 328280 RCS STRESS IMPROVEMENT 15R NRR DW RB23 PERFORM STRESS IMPROVEMENT ON SELECTED STAINLESS STEEL PIPING WELDS IN RCS SYS.

9 328353 **

RCS AUG - IGSCC INSPECTION-15R 15R NRR DW RB75 RB95 INSPECT PIPING WELDS PER G.L. 88-01 AND NUREG 0313 REV.2

'10 402910 C R RECORDERS ~

15R NRR CR REMOVE AND REPLACE 3 DEFICIENT / OBSOLETE RECORDER. GROUPS (6 RECORDERS), AND DELETE 2 RECORDERS. NUREG 0737 SUPP. 1 11 402974.

OC RX OVERFILL PROTECTION SYSTEM 15R NRR CR MODIFICATIONS TO FW PUMPS TRIP CIRCUITRY NRC GEN. LETTER 89-19 12403005 REG GUIDE 1.97 INSTRUMENTATION ISR NRR CR' REPLACE / INSTALL RX WATER LEVEL FUEL ZONE RECORDERS AND PROVIDE POWER SUPPLIES AND NEW POWER DISTR. SYSTEM PER RG 1.97

-RCS AUG-IGSCC INSPECTION - 16R 16R NRR 13.32KAHE RB DW

'INSPEOr PIPING WELDS PER NUREG 0313 REV2 14 328280 RCS STRESS IMPROVEMENT 16R NRR-DW RB23 PERFORM STRESS IMPPINEMENT ON FOUR VESSEL: INLET RECIRC SJLSE EPOS 4

OYSTER. CREEK. PROJECT LISTING LEGEND NRC INTEGRATED SCHEDULE

  • - NEW PROJECTS.

ee ' BA' NUMBER CHANGE CATEGORY

'B' PROJECTS

SORT BY CATEGORY / CYCLE /BA STATUS AS OF 27MAY93

-OBS BA DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS 15.32XAHE RCS AUG-IGSCC INSPECTION - 17R 17R-NRR RB. DW -"

INSPECT PIFING WELDS PER NUREG 0313 REV2

- 16 326216 RK. VESSEL BELTLINE INSPECTION 17R NRR 119 UT ACCESSIBLE WELD SEAMS IN THE RPV BELTLINE REGION. INSPECTIONS WIIL BE DONE R 6.Y. ASME SECT. XI REQUIREMENTS 17' 328205 SQUG SUPPORT & PARTICIPATION - BWROG 87-97 NRR PARTICIPATION IN SEISMIC QUALIFICATION' UTILITY' GROUP.FOR EQUIP SEISMIC QUA-LIFICATION. UNRESOLVED SAFETY ISSUE.

18 328312 MOV PROGRAM 90-94 NRR DESIGN BASIS REVIEW, STRESS ANALYSIS AND TESTING OF MOV'S IDENTIFIED BY THE PROGRAM PER NRC GL-89-10.

O Y S T'E R.

CREEK - P R O J E C T-LISTING LEGEh"J NRC INTEGRATED SCHEDULE NEW PROJECTS.

    • BA NUMBER CHANGE CATEGORY *C*

PROJECTS SORT BY CATEGORY / CYCLE /BA STATUS AS OF 27MAY93 J OBS BA DESCRIPTION CYCLE /

CLASSIFICATION-NUMBER YEARS 19 323L34 VALVE MAINT & OVERHAUL 14 MRC RB TB - DW CORRECTIVE AND PREDICTIVE MAINT ON SELECTED VALVES 20 323624 VALVE MAIh M CE & OVERHAUL-14 MRC TB - DW RB COPJtECTIVE & PREDICTIVE MAINTENANCE OF SELECTED VALVES.

21. 402823 GROUNDING & LIGHTNING PROTECTION 14 ISM YARD TB INSTALL LIGHTNING PROTECTION FOR" PLANT STACK AND TURBINE BUILDING 22 402880 OC SPENT FUEL S W RAGE CAPACITY EXPANSION 14 ORR LICENSING AND ENGR. FOR MANUFACIURE OF

_ ]

DRY S M RAGE CASAS, CONSTRUCT CONCRETE FOUNDATION 23 323L34 VALVE MAINT & OVERHAUL -

15 MRC RB

-TB DW CORRECTIVE AND PREDICTIVE MAINT ON SELECTED VALVES

-24 323L48- '*

SPENT FUEL TRANS TO PERMANENT STORAGE 15 IOE TRANSFER' SPENT FUEL FROM FUEL POOL TO.

. DRY STORAGE FACILITY 25 402880

OC SPENT FUEL STORAGE CAPACITY. EXPANSION 15

~ORR INSTALL PERIMETER INTRUSION DEIECTION f.;

SYSTEM (PIDS)

OYSTER CREEK PROJECT LISTING LECEND NRC INTEORATED SCHEDULE

  • ' NEW PROJECTS.
    • BA NUMBER CHANGE CATEGORY

'C' PROJECTS SORT BY CATEGORY / CYCLE /BA STATUS AS OF 27MAY93 OBS BA-DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS 26 323LO7 CONTAINMENT ISOLATION VALVE MAINT 15R NRR RB DW PERFORM CORRECTIVE MAINTENANCF ON CONTAINMENT VALVES WHICH DO NOT PASS ILRT 27 323L13 ASBESTOS ABATEMENT 15R ORR CB LEVEL OF. EFFORT ASBESTOS REMOVAL TO SUPPORT OUTAGE WORK 28 323L22 PEFUEL FICOR-RK. DISASSEMBLY / REASSEMBLY 15R MRC TASKS ASSOCIATED WITH REACIOR DISASSEMBLY AND REASSEMBLY AND SUPPORTING ACTIVITIES 29 323L34 VALVE RELIABILITY MAINTENANCE 15R MRC RB TB DW CORRECTIVE AND PREDICTIVE MAINT ON SELECTED VALVES 30 323L38 CRD HCU REBUILD ISR MRC

- RB INSPECT & REBUILD EQUIVILANT OF 35 CRD HCUS. REPLACE V-117 & V-118 VALVES 31 323L47 LPB ' TURBINE AND GENERAIOR INSP-15R 15R MRC TB' INSPECP LPB, GENERATOR, VALVES &

MOISIUPE SEPERATOR/ REHEATER FOR NML -

REQUIREMENTS AND MANUF. SUGGESTION

.'32.

326L14 DRYWELL SCAFFOLDING & INSUIATION ISR GWC DW INSTALLSCAFFOLD IN D.W. 10 SUPPORT ALL ACTIVITIES. REMOVE & REINSTALL D.W.

INSULATION. REMOVE SCAFFOLD

. ~,

O*7TER CREEK P R O J.E C T LISTING.

t LEGEND NRC INTEGRATED SCHEDULE

~*

NEW PROJECTS.

    • BA NUMBER CHANGE CATEGORY

'C' PROJECTS

. SORT BY CATEOORY/ CYCLE /BA STATUS AS OF 27MAY93

'OBS BA DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS 33 32694J OUTAGE ISI-15R ISR

!UtR ALL INSPECT HANGERS, PIPING WELDS,&

COMPONENTS TO SATISFY SECTION KI REQUIREMENTS 34.328AGZ PIPE WALL THINNING-15R 15R ISM TB' RB REMOVE INSULATION, PREP. SURFACE &

PERFORM UP ON SELECTED PIPING SYSTEMS.

' POSSIBLE REPIACEMENT OF FITTINGS / PIPING,

35 328352 **'

RX V INTERNAL INSPECTION-ISR~

15R NRR

~

119 VISUAL INSPECTION OF SELECTED INTERNAL' COMPONENTS AND SURFACES AS REQ'D BY ASME CODES.

36 402ABQ SQUG MODS ISR NRR IMPLEMENT MODS RESULTING FROM SQUG '

WALKDOWN IN 15R. SCOPE NOT YET DEFINED.

t 37 402736 DUAL' VALVE INDICATION REMOVAL-PH I 15R

. ISM CR.

RB REPLACE DOUBLE VALVE INDICATION LIGHTS 'IN C.R.- PNLS 1F/2F,- 11F. INSTAL NEW CABLING FROM R.B. TO C.R.

38 402898.

.REPL UPPER TB & OLD MACHINE SHOP ROOF 15R MRC

. YARD

. REPLACE THE. UPPER TURBINE BUILDING ROOF.

39 ~402901 FEEDWATER SYSTEM IMPROVEMENTS 15R

~REL CR-NCSR REPLACE GEMAC SYSTEM WITH A DIGITIL CONTROL SYSTEM.

u

=...

=

~

OYSTER

.C R E'E K PROJECT L1 STING LEGEND NRC INTEGRATED SCHEDULE NEW PROJECTS

    • BA NUMBER CHANGE CATEGORY

'C' PROJECTS SORT BY CATEGORY /CYCIE/BA STAWS AS OF 27MAY93 OBS BA DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS

~

40 402925 GENERATOR PROTECTION UPGRADE ISR ISM TB ADD RELAYS AND ALARMS M PRCTTECT THE GEN AS PER PJM RECOMMENDATIONS.

41 402929 DIGITAL RECIRC FLOW CONTROL 15R 15R REL CR REPIACE GEMAC EARDWARE WITH DIGITAL SYSTEM. THIS SCOPE HAS BEEN INCLUDED IN B/A 402901B.

42 402939 DRYWELL EXPOSURE REDUCTION MODS.

15R RAD DW INSTALL IMPROVED EQUIPMENT IN 1-B SUMP AND HYDROIAZE AND RECOAT l-8 SUMP i

'43 402961 OC EDG OUTPUT CONTROL MODIFICATION 15R MRC TB REPLACE THE EXISTING GOVERNOR WITH A WOODWARD AUTOMATIC GEN ICADING CO?TTROL.

REPLACE MISC.- ELECTRICAL COruuu:.m.

44 402966 RECIRC FICW SCRAM ELECTRONICS REPLACEM'T 15R ORR RB-CR REPLACE EXISTING ELECTRONICS WITH DIGITAL EIECTRONIC EQUIPhENT.

'45 408L24 VALVE REPLACEMENT / RETIREMENT 15R REL.

RB' TB DW REPLACE SELECTED VALVES IDENTIFIED AS HAVING MMOR DEFICIENCIES

'46. 323L48

. SPENT FUEL TRANS TO PERMANENT S MRAGE 16

. IDE TRANSFER SPENT FUEL FROM FUEL POOL TO DRY STORAGE FACILITY

OYSTER CREEK PROJECT LISTING LEGEND NRC INTEGRATED SCHEDULE NEW PRG7ECTS.

    • BA NUMBER CHANGE CATEGORY

'C' PROJECTS SORT DY CATEGORY / CYCLE /BA STATUS AS OF 27MAY93

.OBS BA DESCRIPTION CYCLE /

CLASSIFICATION Nt.MBER YEARS 47 32XAHA PIPE WALL THINNING - 16R 16R ISM RB TB -

REMOVE INSULATION, PREP SURFACES &

PERFORM UT ON SELECTED PIPING SYSTEMS.

POSSIBLE REPLACEMENT OF FITTINGS / PIPING

~48 32XAHD RX. VESSEL INTERhAL INSPECTION -16R 16R NRR 119 VISUAL INSPECTION OF SELECTED INTERNAL COMPONENTS AND SURFACES AS REQUIRED BY ASME CODES--

49 323LO3 TURBINE INSP.-16R-16R MRC.

TB INSPECT LPC AND OTHER TURBINE RELATED COMPONENTS FOR NML NML REQUIREMENTS AND MANUF. SUGGESTION 50 323LOS CONTAINMENT ISOLATION VALVE MAINT 16R NRR PERFORM CORRECTIVE MAINTENANCE ON VALVES WHICH DO NOT PASS THE ILRT-i 51 323Ll4 ASBESTUS ABATEMENT-16R 16R ORR CB PS - TB LEVEL OF EFFORT TO REMOVE ASBES' IDS to SUPPORT OUTAGE WORK

_ 52 323L23 REFUEL FLOOR RK DISASSEMBLY / REASSEMBLY 16R MRC.

119 TASKS ASSOCIATED WITH REACTOR

- DISASSEMBLY AND REASSEMBLY ' AND SUPPORTING ACTIVITIES' I.

53 323L35 VALVE MAINTENANCE & OVERHAUL'-16R 16R MRC l-RB TB

-DW' PERFORM CORRECTIVE AND PREDICTIVE MAINT l

ON SELECTED VALVES l'

I

..m

OY. STER CREEK PROJECT LISTING

  • ?

'LEGEhD NRC INTEGRATED SCHEDULE NEW PROJECTS.

    • ' BA NUMBER CHANGE CATEGORY

'C' PRGJECTS SORT BY CATEGORY / CYCLE /EA STATUS AS OF 27MAY93 OBS BA DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS 54 323L39 CRD !!CU REBUILD - 16R 16R MRC RB REBUILD HYDRAULIC CONTROL UNITS 55 326L15-DRYWELL SCAFFOIDING & INSUIATION-16R 16R GWC DW

- INSTALL SCAFFOLD IN D.W. TO SUPPORT ALL ACTIVITIES. REMOVE & REINSTALL D.W.

INSULATION. REMOVE SCAFFOLD

-56 32696G OUTAGE ISI-16R-16R NRR ALL INSPECT HANGERS, PIPING WELD,&

COMPONENTS TO SATISFY SECTION XI REQUIREMENTS 57 402ABQ SQUG MODS 16R NRR

- IMPLEMENT MODS RESULTING FROM SQUG WALKDOWN IN ISR. SCOPE NOT YET DEFINED 58 402821 RX RECIRC PUMP & MOTOR VIBRATION MONITRS '

16R MRC-DW RB CR INSTALL VIBRATION MONITORING TRANSDUCERS AND SUPPORT EQUIP. FOR 4 RECIRC PUMPS 7 TRANS./ PUMP AND 5 FOR 1 PUMP.

59 402948 LP TURB. C LAST STAGE BIADE INSTALLATION 16R REL TB REPLACE LAST STAGE BLADES IN LP TURBINE.*C*.

BLADE FAILURE CONCERNS.

~60' 402957 OC IA83 ANAIDG CONVERSION 16R REL RB CR.

REPLACE 5 IAB3 PRESS SWITCHES WITH

~

ANAIOG SYSTEM.

w e

er-'v---

w-

  • -+r-d v c m w'r e

ny-e w ue p,

OYS.TER CREEK PROJECT L'I.S T 1 N G' LEGEND NRC INTEGRATED SCHEDULE NEW PROJECTS.

    • BA NUMBER CHANGE CATEGORY

'C' PROJEC. S T

SORT BY CATEGORY / CYCLE /BA STAnJS AS OF 27MAY93 OBS BA DESCRIPTION CYCLE /

CLASSIFICATION NUMBER YEARS 61 408L25 VALVE REPLACEMENT - 16R 16R PEL RB TB DW REPLACE SELECTED VALVES IDENTIFIED AS HAVING DEFICIENCIES PIPE WALL THINNING - 17R 17R ISM 62 32XAHA RB TB REMOVE INSULATION, PREP SURFACES &

PERFORM UT ON SELECTED PIPING SYSTEMS.

POSSIBLE REPLACEMENT OF FITTINGS / PIPING RK. VESSEL INTERNAL INSPECTICN -17R 17R NRR 63 32XAHD 119.

VISUAL INSPECTION OF SELECTED INTERNAL COMPONENTS AND SURFACES AS REQUIRED BY ASME CODES TURBINE INSP.-17R 17R MP4

'64 323LO3 '*

- TB INSPECT MISCELLANEOUS TURBINE RELATED COMPONENTS FOR NML REQUIREMENTS AND MNUF. SUGGESTION -

1 CONTAINMENT ISOLATION VALVE MAINT 17R NRR 65 323LOS PERFORM CORRECTIVE MAINTENANCE ON VALVES WHICH DO NOT PASS THE ILRT ASBESTOS ABATEMEhT-17R 17R ORR 66' 323L14 CB RB TB IEVEL OF EFFORT TO REMOVE ASBESTUS

-TO SUPPORT OUTAGE WORK' REFUEL FLOOR RK DISASSEMBLY / REASSEMBLY 17R

'MRC

67. 323L23 119 TASKS ASSOCIATED WITH REACTOR DISASSEMBLY AND P2 ASSEMBLY AND SUPPORTING ACTIVITIES'

O.Y'S T'E R..

C R E E'K PROJECT L I S T I'N G IEGEND NRC INTEGRATED SCHEDULE

  • - NEW PROJECTS.
    • BA NUMBER CHAhCE CATEGORY

'C' PROJECTS SORT BY CATEGORY / CYCLE /BA STATUS AS OF 27MAY93 OBS BA DESCRIPTION CYCLE /

CIASSIFICATION NUMBER YEARS

68. 323L35 VALVE MAINTENANCE & OVERHAUL -17R 17R MRC RB TB DW PERFORM CORRECTIVE AND PREDICTIVE MAINT ON SELECTED VALVES 69 323L39- *-

CRD HCU REBUILD - 17R 17R MRC RB REBUILD HYDRAULIC CONTROL UNITS

- 70 '326L15--

  • DRYWELL SCAFFOLDING & INSULATION-17R 17R Ght DW INSTALL SCAFFVLD IN D.W..TO SUPPORT ALL ACTIVITIES. REMOVE & REINSTALL D.W.

INSULATION. REMOVE SCAFFOLD 71 32696G OUTAGE ISI-17R 17R NRR ALL INSPECT HANGERS, PIPING WELD,&

COMPONENTS TO SATISFY SECTION XI-REQUIREMENTS

'72 408L25 VALVE REPLACEMENT -.17R 17R REL RB TB DW REPLACE SELECTED VALVES IDENTIFIED AS

~HAVING DEFICIENCIES 73 328148 0.C. PLANT LIFE ASSURANCE & EXTENSION 92-95 REL DEVEIDP 3-PHASE PLEX PLAN. PHASE 1 TO DETERMINE FEASIBILITY AND COST /

' ANALYSIS OF PLEX.

'74.402982' INDIVIDUAL PMNT EXAM.~ - EXTERNAL EVENTS 92-95

-NRR L

PERFORM IPE ANALYSIS OF EXTERNAL EVENTS FOR SEVERE ACCIDENT VULNERABILITIES BY, 6/39/95, BUT NO LATER THAN'12/22/95 I

7

3 i

. OYSTER C R E E'K.

. PROJECT LISTING LEGEND NRC INTEGRATED SCHEDULE

  • - NEW PROJECTS.

' * * - BA NUMBER N CATEGORY

'C' PROJECTS SORT BY. CATEGORY / CYCLE /BA STATUS AS OF 27MAY93

'OBS' BA.

DESCRIPTION CYCLE /

SIFICATION

-NUMBER YEARS 15 ~402980 CONFIGURATION MANAGEMENT-DBD 92-96 92-96 ISM DEVEIDPMENT OF OC SYSTEM DESIGN BASES PERFORM 4 m 5 DBD'S PR YEAR OVER S YEARS.

76 409229-NUMARC PROCUREMENT INITIATIVE 92-96 NRR IMPROVEMENTS TO PROCUREMENT QA TO MEET T!!E REQUIREMENTS OF THE NUMARC PROCURE-MENT AND NRC GEN LTR,

-77 409256 **

REPLICA SIMULATOR MODS 93 NRR' UPGRADE THE SIMULATOR TO MATCH PIANT MODS AS APPLICABLE

..-- 7 8 402981 ACCIDENT MANAGEMENT-GUIDELINES 93-95 NRR DEVEIOP ACCIDENT MANAGEMENT GUIDELINES TO COPE WITH DAMAGED CORE EVENTS (PART OF IPE REQUIREMENTS, G.L. 88-20).

.79 -409948

. REPLICA SIMUIATOR MODS 94 EPR UPGRADE THE SIMULATOR TO MAKH PLANT MODS AS APPLICABLE 80 '(09L10 REPLICA SIMULAIOR MODS 95 NRR MODIFY TFE SIMULATOR AS NECESSARY TO' MAINTAIN LIKENESS WITH CONTROL ROOM AS REQUIRED

..n..

L.

ABC Classifications a)

Met-NRC Reautrements (NRR) - Activities that a) must be carried out to e

fulfill specific NRC requirements or b) have been committed to the NRC by i

the Company or c) are such that if not accomplished would result in an NRC.non-compliance even though the specific activity is not required by the NRC.

b)

Meet Environmental Reauirements (ERR) - Activities that a) are specifically required by environmental regulatory agencies (State'and Federal) or b) have been committed to environmental agencies by ",e Company or c) are such that if not accomplished would result in a regulatory non-compliance even though the specific activity is not required by an environmental regulatory agency.

c)

Meet Other Reauirements (0RR) - Activities not covered by the NRC or environmental requirements but that are required by local, state, or j

federal ordinances, codes, court order or lawsuit settlement, or other guidance t', which the Company is committed or if not accomplished would l

l re: ult in a violation of that ordinance, code or guidance, court order, etc.

d)

Increase Safety Marains (ISM) - Activities that, if implemented, will irnprove nuclear plant.or personnel safety but are neither required for regulatory compliance nor required by safety regulations, codes or guidance.

e)

Decrease Environmental Effects (E) - Activities that, if implemented, h

will result in an improved environmental quality but are neither required:

[

for regulatory compliance nor requireo by environmental regulations, codes or guidance.

f)

Imorove Radioloaical Conditions (RAD) - Activities that, if implemented, will result in improved radiological conditions, lower man-rem exposure i

rates, or radwaste control / reduction but.are neither required for regulatory compliance nor required by radiological regulations,, codes or guidance.

I g)

Maintain Reliability /CaDability (MRC) - Activities that, if implemented, L

will maintain power production at existing levels by preventing deterioration of plant systems or equipment.

Includes activities in response to national codes and standards, insurance policies, equipment i

vendor specifications or nuclear industry high unavailability equipment l

data without which the plant could not operate prudently. -

h)

Imorove Reliabilitv/Caoability (REL) - Activities that, if implemented, will increase power generation by improving availability or capacity factor to maximize energy output.

u

ABC Classifications

-(continued)-

i)

Imorove Operational Effectiveness (10E) - Activities that, if implemented, will improve staff efficiency or provide a direct economic payback in' terms of reduced operating / maintenance costs.

j)

Improve Personnel Facilities (FAC) - Activities that, if implemented, will improve working conditions and the usefulness of personnel facilities, k)

Provide Continaency/ Blanket (CUI) - Activities that, if implemented, will provide management flexibility to respond in a timely manner to ' emergent work requirements _or the ongoing requirements to procure, replace or repair minor items essential to support routine operations.

1)

Improves Heat Rate Performance (HRP) - Activities, that, if implemented, will increase power production by enhancing the heat rate efficiency.

~ -

3 6

9

,.f.

,' l

.)

1

~

l

=

i I

ATTACHMENT B' i

OYSTER CREEK NUCLEAR' GENERATING. STATION NRC INTEGRATED SCHEDULE t

' SEMIANNUAL UPDATE CATEGORY"A" PROJECTS COMPLETIONS:

402965 Station Blackout. Modifications 402011 Replica Simulator Certification 9

I e

- e r

F i

i m

,.,r..

,9 -

CATEGORY "B" PROJECTS ADDITIONS:

As denoted by

  • next to the Project Title in Attachment A.

14R OUTAGE COMPLETIONS:

326216 Reactor Vessel Beltline Measurements 328307 RCS Augmented IGSCC Inspection 328342 FW/CRD Nozzle Inspection 402888 RPV Capsule #2 Installation 402894 Containment Spray Auto Start Deletion 402900 Isolation Condenser Piping Stress Improvement 402910 Control Room Recorder Replacement 402936 Containment Isolation Valve Mod to Preclude Auto Restart 402946 Containment Isolation Valve Replacement 402950 Drywell Corrosion Control 402968 Hardened Vent 402011 OC Replica Simulator (87-92)

SCHEDULE CHANGES:

326216 Reactor Vessel Beltline Weld Inspection

~

The schedule for reactor vessel beltline weld inspections has been changed from the ISR'to 17R outage.

This change is based.on the requirements of 10CFR50 and the schedule in ASME Section XI, Table IWB-2500-1, Item Bl.10.

328030 Detailed Control Room Desian Review (DCRDR)

The work scope to refurbish rear panels has been reviewed.

Repainting the back panels will not be necessary, however, minor touch-up painting on some panels will be required. The schedule has been revised from cycle ISR to cycles 14 and 15 due to priority and available GPUN resources. The current scope as defined in B/A 328030 will fulfill our commitments to resolve the DCRDR Human Engineering deficiencies.

402910 Control Room Recorders Schedule has been revised to replace five recorder groups (seven individual recorders) in Cycle 14, and three recorder groups (six individual recorders) in Cycle 15R.

This increases the cycle 14 scope and decreases the cycle 15R scope, but does not affect the overall BA scope.

CATEGORY "B" PROJECTS (continued)

OTHER CHANGES:

The following B/A numbers have been changed:

PREVIOUS NEW OBS #

TITLE B/A Bla 9

RCS Aug. IGSCC Inspec. - 15R 328AFR 328353 13 RCS Aug. IGSCC Inspec. - 16R 328AHE 32XAHE 328226 SOUG Proaram Imolementation Previous Cycle / Years was 87-95, changed to Cycle 14/15.

P v

)

h.

~

CATEGORY "C" PROJECTS ADDITIONS:

As denoted by

  • next to the Project Title in Attachment A.

14R OUTAGE COMPLETIONS:

322036 Drywell Scaffolding & Insulation 323624 Valve Maint. and Overhaul- (13/13U/14R) 323629 CRD HCU Module Rebuild 323637' Check Valve Monitoring / Inspection Program 323646 Turbine Generator Systems Inspection 323648 Containment Isolation Valve Maint.

323651 Asbestos Abatement 323659 Reactor Disassembly / Reassembly 326213 Outage ISI 328295 Pipe Wall Thinning 328308 RCS Piping Repair Contingency 328310 Reactor Internal Inspection 402901 Feedwater System Improvement (Cable Pull) 402925 Generator Protection Upgrade (Cable Pull) 402929 Digital Recirc. Flow Control (Cable Pull) l l

402939 Drywell Exposure Reduction Mods l

402943 Configuration Management DBD 1991-92 402951 H2/02 Analyzer Mod 402963 LP-A, L-0 Turbine Blade Replacement 402996 Core Spray System Upgrade 408836 Valve Replacement 409244 Replica Simulator Mods (1992)

DELETIONS:

323L05 Turbine Valve _ Inspection-NML-15R 323LO6 Turbine Valve Inspection-NML-16R 328AFQ RCS Piping Repair Contingency-15R 402939 Drywell Exposure Reduction Mod (Shielding) 402951 H2/02 Analyzer Mod-15R 402AGZ Site Emerg. Bldg. Emerg. Power Source SCHEDULE CHANGES:

402821 Recirc Pump & Motor Vibration Monitors have been changed from the 15R to 16R outage.

402957 IA83 Analog Conversion has been changed from the 15R to 16R outage.

OTHER CHANGES:

The following B/A Numbers have been changed:

PREVIOUS NEW 0 B. S #

TITLE B/A B/A 35 Reactor Vessel Int. Inspec.-15R 328ADL' 328352 77 Replica Sim Mods (1993) 40993E 409256 402880 Spent Fuel Storaae Caoacity Expansion Previous cycle / years was 87-96, changed to cycle 14 and 15.