Monthly Operating Repts for Apr 1993 for Point Beach Nuclear Plant Units 1 & 2.W/930507 Ltr
ML20044D005
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/30/1993
From: Arnold R, Link B
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CON-NRC-93-057, CON-NRC-93-57 VPNPD-93-095, VPNPD-93-95, NUDOCS 9305140291
Download: ML20044D005 (10)


Text

~

Wisconsin

' Electnc '

POWER COMPANY 6

23 w regan pc to 2:es wwoe e s32:e gui2:42345 VPNPD-93-095 NRC-93-057 May 7, 1993 Document Control Desk U.S. NUCLEAR REGULATORY COMMISSION Mail Station P1-137 Washington, D.C. 20555 Gentlemen:

DOCKETS 50-266 AND 50-301 MONTHLY OPERATING REPOPTS POINT BEACH NUCLEAR PL'iT, UNITS 1 AND 2 1

Attached are monthly operating reports for Units 1 and 2 of the Point Beach Nuclear Plant for the calendar month of April 1993.

Sincerely,

, [

Bob Link Vice President l Nuclear Power MFB/jg cc: L. L. Smith, PSCW NRC Regional Administrator, Region III NRC Resident Inspector I

f l Y M j I

9305140291 930430 / /g  !

I PDR ADDCK 05000266 / // .!

R PDR Y }

A sulukgafHiwonsm EncyGepwkm

OPERATING DATA REPORT DOCKET NO. 50-301 DATE: 05/03/93 COMPLETED BY: Richard F. Arnold TELEPHONE: (414) 755-6193 OPERATING STATUS

1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 2 . NOTES .
2. REPORTING PERIOD: April - 1993 . .
3. LICENSED THERMAL POWER (MWT): 1518.5 . .
4. NAMEPLATE RATING (GROSS MWE): 523.8 . .
5. DESIGN ELECTRICAL RATING (NET MWE): 497.0 . .
6. KAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0 . .
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0 . . . . . . . . . . . . , . . . . .
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NA
10. REASONS FOR RESTRICTIONS, (IF ANY):

NA THIS MONTH YEAP TO DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD 719.0 2,879.0 181,872.0
12. NUMBER OF HOURS REACTOR WAS CRITICAL 719.0 2,866.7 159,142.6
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 4.0 233.9
14. HOURS GENERATOR ON LINE 719.0 2,858.3 156,840.8 i
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 302.2
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,073,515 4,259,587 224,905,848
17. GROSS ELECTRICAL ENERGY GENERATED 368,580 1,461,810 76,461,930
18. NET ELECTRICAL ENER0Y GENERATED (MWH) 352,928 1,400,027 72,886,434
19. UNIT SERVIta FACTOR 100.0% 99.3% 86.2%
20. UNIT AVAILABILITY FACTOR 100.0% 99.3% 86.4%
21. UNIT CAPACITY FACTOR (USING MDC NET) 101.2% 100.3% 82.0% ,
22. UNIT CAPACITY FACTOR (USING DER NET) 98.8% 97.8% 80.6%
23. UNIT FORCED OUTAGE RATE 0.0% 0.7% 1.0%
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

Refueling Outage, 09/25/93, 50 Days

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: I NA DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22, 1977 0

0

+ - - . , ,

. - . - . - . ~ .. ._ . . - . - . - --. .. . . - . . -

POINT BEACH NUCLEAR PLANT >>CKET NO, 50-301 AVERAGR DAILY UNIT POWER I.EVEL UNIT NAME Point Beach. Unit 2 MONTil APRIL - 1993 DATE May 1.1993 COMPLETED BY R. F. Amold TELEPflONE 414r7554193 AVERAGE AVERAGE AVERAGE DAILY DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAX MWe NET DAX MWe NET DAX MWe NET 1 449 11 496 21 499 2 418 12 494 22 491 3 495 13 494 23 495 4 498 14 498 24 496 5 490 15 492 25 496 6 494 16 495 26 4%

7 494 17 495 27 495 8 494 ad 495 28 496 9 4% 19 494 29 496 10 493 20 495 30 496 PBFM28a mm

... - . - . . . . . . . _ . ..- -.. ._ - . .. . ._ .- - .. . . - ~ . . .. .. .- - .. .

POINT BEACil NUCLEAR PLANT Docket No, 50-301

. Unit Name Point Beach. Unit 2 IINIT SilllTDOWNS AND POWER REDUCTIONS Date hiav 1.1993 _

Completed By R. F. Amold REPORT MONTil _ APRII. - 1993 Telephone No. 414n55-6191 Method of Shuning Duration Down Licenace Event Syncm Conponent Cause assJ Corrective Action No. Date Type' (llours) Reason p,,cis Report No. Code' Code' To Prevent Recurrence 2 4/1/93 F 0 F 5 NA lill IITEXCll Observed increano in modium icvwls in the steam generators initiated a load rcJuction to 300 MWo so facilitato condenaarinspection for tube leakage.

'F: Forced 2 Reawn: 'hiethod: ' Exhibit G - Instiuctions S: Scheduled A - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data entry s! eess C - Refueling 3 - Automatic Scram LER tile (NilREG.0161)

D - Regulatory Restriction 4 - Continuation of E - Operator Training & Previous Shutdown Licensing Etam 5 - Reduced Ital 8

F - Administri.tive 6 - Othet (explain) Exhibit .e Source 0 - Operational Error (explain) 11 Other (explain) d 4 0

- PDF 4 )28b,

' (03-90) ,

+

DOCKET NO. 50-301 UNIT NAME Point Beach Unit 2 DATE May 2, 1993 COMPLETED BY R. F. Arnold TELEPHONE 414/755-6193 Unit 2 operated at approximately 491 MWe net throughout the report period.

An observed increase in Unit 2 steam generator sodium levels initiated a load reduction to 300 MWE for approximately 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> to facilitate condensor waterbox inspection for tube leakage.

Licensee Event Report 301/93-002-00, Unit 2 Reactor Trip During Turbine Trip Tests, was submitted.

A Notice of Enforcement Discretion was received for Unit 2 to allow

  • the postponement of certain surveillance testing while KNPP and PBNP Unit 1 are shutdown. <

The setpoints for the Unit 2 safeguards time delay relays which control the sageguards sequencing of the containment fan )

cooler motors were changed to meet the 60-second start time following the initiation of a design basis LOCA as described in FSAR.

Safety-related maintenance included:

1. Oil added to steam driven auxiliary feedwater pump (2P-29) governor.
2. Installad seismic bumpers for the lift indicating switch assembly (LISA) instrumentation in Unit 2 ASIP panel.

i I

OPERATING DATA REPORT DOCKET NO. 50-266 DATE: 05/03/93 i

COMPLETED BY Richard F. Arnold l

TELEPHONE: (414) 755-6193 OPERATING STATUS

1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 1 . NOTES .
2. REPORTING PERIOD: April - 1993 . .
3. LICENSED TiiERMAL POWER (MWT): 1518.5 . .

'4. NAMEPLATE RATING (CROSS MWE): 523.8 . .

5. DESIGN ELECTRICAL RATING (NET MWE): 497.0 . .
6. HAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0 . .
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0 . . . . . . . . . . . . . . . . . .
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NA
10. REASONS FOR RESTRICTIONS, (IF ANY): ,

NA T!!IS MONTH YEAR TO DATE CUMULATIVE

11. HOURS IN REPORTING PERIOD 719.0 2,879.0 197,087.0 12, NUMBER OF HOURS REACTOR WAS CRITICAL 0.0 2,046.0 162,929.3
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 667.3 l l
14. HOURS GENERATOR ON LINE 0.0 2,044.9 159,884.3
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 846.9
16. GROSS THERMAL ENERGY GENERATED (MWH) 0 3,093,553 224,830,526
17. GROSS ELECTRICAL ENERGY GENERATED 0 1,046,540 75,922,940
18. NET ELECTRICAL ENERGY GENERATED (MWH) 0 1,001,206 72,353,369
19. UNIT SERVICE FACTOR 0.0% 71.0% 81.1%
20. UNIT AVAILABILITY FACTOR 0.0% 71.0% 81.6%
21. UNIT CAPACITY FACTOR (USING MDC NET) 0.0% 71.7% 75.3%
22. UNIT CAPACITY FACTOR (USING DER NET) 0.0% 70.0% 73.9%
23. UNIT FORCED OUTAGE RATE 0.0% 0.0% 1.6% '
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

NONE

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

05/08/93 DNTA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMDER 22, 1977 9

O

b. _ . . _ _ _ _ . _ . _ _ __ _ _ _ . _ _ . _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ . .. . .

- . ]

s POINT BEACH NUCLEAR PLANT DOCKET NO. 50-266 _

AVERAGE DAILY UNIT POWER LEVEL UNIT NAME Point Beach. Unit 1 MONTil ' APRIL - 1993 DATE May 1.1993 COMPLETED BY R. P. Amold 1

i TELEPIlONE ~ 414n55-6193 AVERAGE AVERAGE AVERAGE 'l DAILY DAILY DAILY ' .

POWER LEVEL POWER LEVEL POWER LEVEL

. DAY MWe NET DAX MWe NET DAX MWe NET 1 -2 11 -2 21 -2 2 -2 12 -2 22 ,.

-2 3 -2 13 -2 23 -2 i

4 -2 14 -1 24 -1 5 -2 15 -2 25 -2 6 -2 16 -2 26 -2 7 -2 17 -2 27 -2 .

8 -2 18 -2 28 -2 9 -2 19 -2 29 -2 10 -2 20 -2 30 -2 ___

9 1

1 PB5M8a ~

(03-q 4

POINT BEACH NUCLEAR PLANT Docket No. = 50-266

. . . Unit Ncme Point Beach. Unit i UNIT SifUrDOWNS AND POWER REDUCT!ONS Date May 1.1993 Completed By R. F. Amold REPORT MONTil APRIL - 1993 - Telephone No. 414 055-6193 Method of shuning No. Date Type' Duration a manaa' Down Licanese Event System Componcat Caues and Corrective Action 1 3/27/93 S 720 C 1 Ni. NA NA Scheduled refbeling and maiwamaes outage (UlR20). Major work items inchie laTechna ggd eJJy currors testing of the steam generators, mechanical sad electrical upgrades of the anala steam isoinuon valves, installation of rod drop testing equipmens, angoscior upgrades for 480 V bus feeder and MG act breakars, P 30B circulation water pung 8 "T*~a" *ad **bdt electrical walkdowns of the reactor protection and safeguarde system.

1 i.

J

'F: Forced 2 Reason: ' Method: ' Exhibit 0 - Instructions S: Scheduled A - Equipment Failure (explain) 1 - Manual ' for prelaration of B - Maintenance or Testing 2 - Manual Scram data entry sheets C - Refueling 3 - Automatic Scram LER file (NUREG-0161)

D - Regulatory Restricnon 4 - Continuation of E - Operator Training & Previous Shutdown Licensing Exam 5 - Reduced Load F - Administrative 6 - Other (explain) 5 Exhibit ! - Same Source 0 - Operational Error (explain)

II - Other (explain)

Pae m ish

@J-90) ,

s DOCKET NO. 50-266 UNIT NAME Point Beach Unit 1 DATE May 1, 1993 COMPLETED BY R. F. Arnold TELEPHONE 414/755-6193 Unit 1 was shutdown for refueling and maintenance outage (U1R20) for the month of April with zero electrical output.

Licensee Event Report 50-266 and 50-301/93-001-00, Nonconservative Setpoints For The Low Temperatu.e Overpressure System, was submitted.

The setpoints for the Unit 1 safeguards time delay relays which control the safeguards sequencing of the containment fan cooler motors were changed to meet the 60-second start time following the initiation of a design basis LCCA as described in FSAR.

Safety-related maintenance included:

1. Reconnected wire in main control board for the electric auxiliary feedwater pump control circuit. Wire was disconnected during as-built wire tracing work activity. All-wire lug connections in the Unit 1 main control board were check tightened.
2. Replaced residual heat removal pump seal and installed outer bearing race spacer.
3. Installed mechanical and electrical upgrades to the main steam isolation valves.
4. Installed a new disk in main steam isolation valve (MS-2017),

stelite face of disk was cracked.

5. Replaced solenoid valve on service water supply valve to radwaste steam systems (SW-LW-061).
6. Replaced air operator slide valve on containment purge supply valve (IliVPSE-3 24 4 ) .
7. Installed mechanical and electrical upgrades on the main steam isolation valves.
8. Installed bypass around mini-recirc control valve solenoid for IST required testing of steam driven auxiliary feedwater pump (1P-29).

u

'9. Installed 4 rotor limit switches on several safety-related MOVs.

10. Rebuilt' actuators and replaced tubing between the actuator and slide valve on the containment purge supply and exhaust valves.

I i

i

(

i 2