IR 05000272/2020011
| ML20044C865 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 02/12/2020 |
| From: | Mel Gray NRC Region 1 |
| To: | Carr E Public Service Enterprise Group |
| References | |
| IR 2020011 | |
| Download: ML20044C865 (12) | |
Text
February 12, 2020
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000272/2020011 AND 05000311/2020011
Dear Mr. Carr:
On January 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Salem Nuclear Generating Station, Units 1 and 2 and discussed the results of this inspection with Mr. Charles McFeaters and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Mel Gray, Chief Engineering Branch 1 Division of Reactor Safety
Docket Nos. 05000272 and 05000311 License Nos. DPR-70 and DPR-75
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000272 and 05000311
License Numbers:
Report Numbers:
05000272/2020011 and 05000311/2020011
Enterprise Identifier: I-2020-011-0004
Licensee:
Facility:
Salem Nuclear Generating Station, Units 1 and 2
Location:
Hancocks Bridge, NJ
Inspection Dates:
January 13, 2020 to January 30, 2020
Inspectors:
C. Baron, Contractor
J. DeBoer, Reactor Inspector
A. Della Greca, Contractor
J. Kulp, Senior Reactor Inspector
A. Patel, Senior Reactor Inspector
J. Schoppy, Senior Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) at Salem Nuclear Generating Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Teams)
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)
=
(1)1B Emergency Diesel Generator (Mechanical)
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents/procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Design calculations
- Surveillance testing and recent test results
- Equipment protection from fire, flood, and water intrusion or spray
- Heat removal cooling water and ventilation
- Energy sources, fuel and air (e.g., engine start, operation, and control)
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
- (2) Unit 2 Motor Driven Auxiliary Feedwater Pump
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents and procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Equipment/environmental controls and qualification
- Operator actions
- Design calculations
- Surveillance testing and recent test results
- Range, accuracy, and setpoint of installed instrumentation
- Equipment protection from fire, flood, and water intrusion or spray
- Heat removal ventilation
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
(3)1B 4KV Switchgear
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents and procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Switchgear bus, breaker, and cable sizing
- Control logic and control power adequacy
- Equipment vendor documentation
- Environmental controls and seismic qualification
- Operator actions
- Transformer tap settings and degraded grid/voltage drop calculation
- Load flow analysis
- Adequacy of electrical power supply for motor and controls
- Short circuit calculation
- Overload and short circuit protective relays setting
- Protection coordination, load in-rush and full load current
- Range, accuracy, and setpoint of installed instrumentation
- Technical Specification required surveillance testing and recent test results
- Component adequacy for minimum voltage
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
(4)11CC16 Residual Heat Removal Heat Exchanger Component Cooling Water Isolation Motor Operated Valve
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents and procedures
- System health report, maintenance effectiveness and records, and corrective action history
- Control logic
- Equipment/environmental controls and qualification
- Operator actions
- Design calculations
- Surveillance testing and recent test results
- Adequacy of electrical power supply for motor and controls
- Thermal overload protection settings
- Protection coordination; Load in-rush and full load current
- Equipment protection from fire, flood, and water intrusion or spray
- Heat removal cooling water and ventilation
- Contactor and fuse ratings; Component adequacy for minimum voltage
- Seismic qualification
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)
- (1) Unit 1 Containment Pressure and Vacuum Relief Isolation Valves (1VC5 and 1VC6)
- Material condition and installed configuration (e.g., visual inspection/walkdown)
- Normal, abnormal, and emergency operating procedures
- Consistency among design and licensing bases and other documents and procedures
- Maintenance records and corrective action history
- Control logic
- Equipment/environmental controls and qualification
- Operator actions
- Design calculations
- Surveillance testing and recent test results
- Adequacy of electrical power supply for motor and controls
- Range, accuracy, and setpoint of installed instrumentation
- Heat removal cooling water and ventilation
- Energy sources, air
The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.
Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)
(1)
===80111452, Salem 2 Nuclear Instrumentation Upgrade (2)80109929, Mitigating Systems Performance Indicator Non-Safety Related Auxiliary Feedwater Pump Modification (3)80116286, Auxiliary Feedwater Room Cooler Controls Replacement (4)80116637, Unit 2 Solid State Protection System Train A Wiring Rework Per TB-13-7 (5)80110461, 11, 21, & 22 Service Water Return Header
Review of Operating Experience Issues (IP Section 02.06)===
- (1) NRC Information Notice 19-02, Emergency Diesel Generator Excitation System Diode Failures, dated June 3, 2019
- (2) NRC Information Notice 15-01, Degraded Ability to Mitigate Flooding Events, dated January 9, 2015
- (3) NRC Information Notice 19-08 Flow Accelerated Corrosion Events, dated October 8,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On January 30, 2020, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. Charles McFeaters and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
317099(15)-01
Weak Link and Seismic Analysis Reports
Revision 1
ES-13-006(Q)
Breaker and Relay Coordination Calculation Safety-Related
AC System
Revision 3
ES-15.017(Q)
Salem Unit 1 & 2 Analytical Voltage Analysis
Revision 3
S-C-CAN-MDC-
2144
Minimum Containment Air Pressure Prior to a LOCA
Revision 1
SC-CBV006-01
Containment Building Differential Pressure Indication LOOP
Uncertainty
Revision 3
Corrective Action
Documents
Resulting from
Inspection
20839697
20843273
20843274
20843289
20843418
20843489
20843617
20843640
20843676
20843677
20843680
20843689
20843759
20843800
20843808
20843831
20843835
20843837
20843849
20843904
20843905
20843906
20843907
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
20843908
20843962
20843974
20843982
20844003
20844005
20844017
20844059
20844060
20844105
20844131
20844146
20844147
20844154
20844157
20844157
20844165
20844171
20844181
20844182
20844194
20844197
20844240
20844244
20844252
20844264
20844321
20844322
Engineering
Changes
80096586
Unit 1 & Unit 2 SSPS Circuit Card Upgrade
Revision 2
80109929
Mitigating Systems Performance Indicator Non-Safety
Related Auxiliary Feedwater Pump Modification
Revision 1
80110461
11, 12, 21, and 22 Service Water Nuclear Return Header
Isolation Valve, Access Branch, and WEKO Seal
Revision 2
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
80110461
No. 11, 12, 21, and 22 Service Water Nuclear Return
Header Isolation Valve and Access Branch Pipe and WEKO
Seal Installation 50.59 Review
Revision 1
80111452
Salem 2 Nuclear Instrumentation Upgrade
Revision 2
80116286
Auxiliary Feedwater Room Cooler Controls Replacement
Revision 0
80116637
Unit 2 SSPS Train A Wiring Rework per TB-13-7
Revision 0
Miscellaneous
IST-SC-INT5
Table 3-1
Inservice Testing Program Plan Valve Test Table
Revision 0
LR-N-17-006
PSEG Letter to USNRC, Focused Evaluation of External
Flooding for Salem Generating Station, Units 1 and 2"
6/30/2017
S1.0P-ST.DG-
0013
1B Diesel Generator Endurance Run
4/11/2019
TB-13-7
Westinghouse Technical Bulletin, SSPS New Design
Universal Logic Board and Safeguards Driver Board 48 VDC
Input
2/10/2013
Procedures
Conduct of Flow Accelerated Corrosion Activities
Revision 9
Guidelines For Flow Accelerated Corrosion Activities
Revision 11
Operator Response Time Program
Revision 0
S1.MD-FT.4KV-
0002(Q)
ESFAS Instrumentation Functional Test 1B 4KV Vital Bus
Revision 31
S1.OP-AB.LOCA-
0001(Q)
Shutdown LOCA
Revision 7
S1.OP-AB.ZZ-
0002
Flooding
Revision 4
S1.OP-SO.CBV-
0002
Containment Pressure - Vacuum Relief System Operation
Revision 21
S1.OP-SO.DG-
0002
1B Diesel Generator Operation
Revision 41
S1.OP-ST.4KV-
0001(Q)
Electrical Power Systems, 4KV Vital Bus Transfer
Revision 16
S1.OP-ST.CBV-
0001
Inservice Testing Containment Ventilation Valves
Revision 8
S1.RA-ST.CBV-
0001
Inservice Testing Containment Valves Acceptance Criteria
Revision 18
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
S2.OP-ST.AF-
0002(Q)
Inservice Testing-22 Auxiliary Feedwater Pump
Revision 18
SC.OP-PT.AF-
0001(Z)
Testing the MSPI Pump and Diesel
Revision 0
Work Orders
60142009
209851