y e

June 22, 1990 Docket No. 50-508 Mr. G. D. Bouchey, Director Licensing &-Assurance Washington Public Power Supply System P. O. Box 968 4

3000 George Washington Way Richland, Washington 99352

Dear Mr. Bouchey:

SUBJECT:

NRC REVIEW OF SEISMIC REPORT ON WNP-3 This letter is in response to your letter to me dated June 8,1990, concerning the WNP-3 seismic report review. You expressed concern at the length of time it was taking NRC to review the report.

-I want to assure you that my staff remains cognizant of this report und that

-the resources invested in this review by the Supply System and the portion of the NRC staff review completed to date will not be lost. However, due to other priorities we will not be able to meet our current SER completion target of late spring 1990. Our current estimate is that the SER will be completed by December 1, 1990.

If you have questions on the precise status and progress of the staff review, please call our Project Manager for WNP-3, Mr. Alexander Adams, Jr., at (301)492-1127.

Sincerely, Original signed by Frank J. Miraglia Thomas E. Murley, Director Office of Nuclear Reactor Regulation

/ DISTRIBUTION 4 Docket File w/ incoming GBagchi l

PDNP r/f 3 Richardson NRC & Local PDRs TMurley/FMiraglia

.JPartlow DCrutchfield WTravers-L SWeiss l~ '

AAdams

.EHylton CSmyre, PMAS

$8

[YT909129]

88

~M

  • PREVIOUSLY CONCURRED D6h PDNP:LA*

PDNP,%

P 0

ADSP:AD*

D:DRSP*

1. c4 EHylton AAd#tiffsr SWeiss WTravers DCrutchfield L 8e 6/13/90 6/20/90 6/p/90 6/13/90 6/15/90

'8Se

'ESGB*

DET ~

ADPM DN R

.' IQ(

FMi/i.) ia 4

GBagchi JRi dson JPartlow 6/15/90 6/pv /90 6/

/90 6/

/90 6/q 0

(

- $:~

,',+f'ph RECg)o,,

UNITED STATES

y'i-

',' g NUCLEAR REGULATORY COMMISSION.

o g

t

. ASHINGTON, D. C. 20SSS W

  • s

%...../

June 22, 1990 Docket No. 50-508' 4

i Mr. G. D. Bouchey,- Director.

i 1.icensing & Assurance Washington Public Power Supply System P. O. Box.968 3000 George Washington Way Richland, Washington 99352:

Dear Mr. Bouchey:

SUBJECT:

NRC REVIEW OF SEISMIC REPORT ON WNP-3 This' letter is in response to your letter to me dated June 8, 1990, concerning the WNP-3 seismic report review.

You expressed concern at the length of time it was taking NRC to review the report.

t l want-to~ assure you that my staff remains cognizant of this report and that

.the rescurces invested in this review by the Supply System and the portion of the NRC staff review completed to date w'.ll not be lost. However, due to other priorities we will not be able te meet our current SER completion target

.of late, spring 1990.

by December 1,1990.

Our turrent estimate is that the SER will be completed If.you have questions on the precise status-and progress of the staff review, please call our Project Manager for WNP-3, Mr. Alexander Adams, Jr., at (301) 492-1127.

i p

Sincerely, L

akrwek i

a I

Thomas E. Murley, Director g Office of Nuclear Reactor Regulation M

b I

l l

l

1 r

J,. c ' Y.. i '

i

/

'o,,

UNITED STATES q,_y :j g '+ g NUCLEAR REGULATORY COMMISSION WU e-wAsHINGT ON, D. C. 20655 i...+pf h

k L<

n(b-y

F ROM
-

ORIGINAL DUE DT: 07/05/90 TICKET NO: 0909129 DOC DTa' 06/08/90 G.' D.~ : B O U C H E Y, DIRECTOR 4

EWASHINGTON PUBLIC NRR RCVD.DATE: 06/12/90 POWER SUPPLY SYSTEM t

103-MURLEY s

FOR. SIGNATURE OF:

    • YEL- **

b L

.MURLEY

'DESC:

ROUTING:

1 NRC. REVIEW OF SIESMIC RESPONSE FOR WNP-3 MIRAGLIA GILLESPIE

ASSIGNED TO

CONTACT:

RICHARDSON DRSP CRUTCHFIELD SMYRE 4

I Please review the due date immediately:

s

1f the
due date does not allow adequate time to respond'to this

!L2cket, you may request a revised due date.. The request must have prior approval' from the appropriate Associate Director or NRR.

Deputy Director and must include a valid justi fication.

Contact

,NRR mailroom with 'the new due date (Cel este Smyre, ex t-21229).

+

Please do not carry concurrence packages to Directors office E

without first goi ng through the NRR mailroom.

6 b OW@D

~~~,,#

ACTION

  1. ~

9

\\.

'9

,0

~

~

. ). -

)

f J;

-