Supplemental Application for Amends to Licenses DPR-71 & DPR-62 Re Number of Nuclear Svc Water Pumps Required to Be Operable
ML20042F802
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 05/08/1990
From: Cutter A
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20042F803 List:
References
NLS-90-094, NLS-90-94, NUDOCS 9005100011
Download: ML20042F802 (7)


Text

7 i

coronne Power a ushi company P.O Boa 1661

  • FWesgh. N C. 27602 MAY 81990 A, B CUTTER SERIAL: NLS 90 094 Vice Preement 10CFR50.90 Nuclear Services Department 85TSB09 United States Nuclear Regulatory Commission

-ATTENTION: Document Control Desk Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS 1 AND 2

. DOCKET NOS. 50-325 & 50 324/ LICENSE NOS. DPR-71 & DPR 62 SUPPLEMENT TO REQUEST FOR LICENSE AMENDMENT SERVICE WATER SYSTEM Centlemen:

-On February 28, 1990 (NLS 90 043), Carolina Power & Light Company submitted a license, amendment request for the Brunswick Steam Electric Plant (BSEP) Units 1 and 2.

The proposed amendment revised Technical Specification Section 3.7.1.2.to clarify and expand-the service water pump operability requirements.- Based on subsequent reviews, CP6L has determined that an update to the February 28, 1990 submittal is necessary. The requested Technical Specification revision requires at least three-operable nuclear service water pumps per site while the discussions in the letter and the. bases pages were based on two operable nuclear service water pumps. ;This update corrects discrepancies between the letter, the proposed bases pages, and the proposed Technical Specification pages with regard to the number of

~

nuclear service water pumps required to be operable.

In addition, this updated submittal includes marked-up Technical Specification pages demonstrating how the inserts provided in Enclosures 3 and 4 of the February 28, 1990 submittal are to be incorporated. There are no technical changes to.the proposed license amendment request resulting from this update, c

For your convenience, Enclosures 1, 2, 3, and 4 of this submittal are provided to supersede, in their entirety, those provided in the February 28, 1990 submittal.

Please refer any questions regarding this submittal to Mr. M. R. Oates at

-(919) 546 6063.

Yourg g ry tru A. B Cutter

~ ABC/ MAT -

.A. B Cutter, having been first duly sworn, did depose and say that the information contained herein is true and correct to the best of his information, knowledge and-belief; and the sources of his information are officers, employees, contract r'trnd,,'

agents of Carolina Power & Light Company.

C,y Maa e a 175x f" 00 NY g Notary (Seal)

$e, i

1 My commission expires: / _9/- 95 5, i

'Qg;..g.L\\

. EUB

- ~-

l pn28M a$ir j

g

r

~% ' A Document Control Dask 1.

l,NLS-90 094 / Page 2

Enclosures:

1.. Basis <for Change Request 2.

10 CFR 50.92 Evaluation 3.

Technical = Specification Pages

'41 nit 1 4

Technical Specification Pages - Unit 2 cc:

Mr. Dayne H. Brown Mr. S. D. Ebneter :

Mr. N. B. Le Mr. W. H. Ruland o.

5'p.

N.

t ENCLOSURE 1 BRUNSWICK STEAM ELECTRIC PIANT, UNITS 1 AND 2 NRC DOCKETS 50 325 & 50-324 OPERATING LICENSES DPR 71 & DPR 62 REQUEST FOR LICENSE AMENDMENT SERVICE WATER SYSTEM BASIS FOR CHANGE REQUEST Pronosed Change The proposed amendment revises Technical Specification Section 3.7.1.2 to

~ larify and expand the service water pump operability requirements, thereby c

better reflectin6 the plant design. The current specification requires the service water system nuclear header to be operable with at least three operable service water pumps.

The revised Specification will require both the nuclear and the conventional headers to be operable with two nuclear and two conventional service water pumps capable of supplying the headers when the unit is in OPERATIONAL CONDITIONS 1, 2, or 3.

When the unit is in OPERATIONAL CONDITIONS 4 or 5 the number of required pumps drops to any combination of two nuclear and/or conventional service water pumps powered from separate emorgency buses provided that there are at least three operable nuclear service water pumps per site. A change to the Bases for Technical Specification Section 3/4.7.1 reflecting the proposed amendment is included for your information.

Baali The service water system provides water for lubrication and cooling of selected equipment in the turbine building, reactor building, diesel generator building, chlorination system, circulating water system, and screen wash system.

The service water system is subdivided into two major headers which are normally operated independently. The nuclear header supplies service l

L water to selected vital equipment in the reactor building and diesel generator building and the conventional header normally supplies service water to the remaining vital equipment in the reactor building, turbine building, and balance'of plant equipment in the other areas.

Two nuclear service water pumps supply the nuclear header and three conventional service water pumps supply the conventional header for each unit.

Cross connect valves allow the conventional pumps to supply the nuclear header as conditions dictate. The two types of pumps are identical except that the nuclear service water pumps are capable of starting automatically duting a design basis accident (DBA) while the conventional service water pumps must be started manually under these conditions.

The diesel generators, which are the only common service water load between the two units, can receive cooling water from the nuclear header of cither unit.

Either of the conventional or nuclear headers, or a combination of the two, can provide water to other loads including the residual heat removal (RHR) system room coolers, the RHR pump seal heat exchangers, the core spray (CS) pump room coolers, and the RHR service water El-1

7 4

cooling system.

The service water system can also be cross connected to the Rl!R system during emergencies to provide core flooding capabilities.

Presently, Technical Specification Section 3.7.1.2 requires each unit to have three service water pumps operable to supply the service water nuclear header.

It does not specify whether these pumps must be nuclear or conventional. The l

proposed chan5e clarifies and expands on this requirement by specifying that when in OPERATIONAL CONDITIONS 1, 2, or 3, there must be at least two operable nuclear service water pumps and two operable conventional service water pumps capable of supplying the nuclear and conventional service water headers. When the unit is in OPERATION CONDITIONS 4 or 5, two service water pumps powered j

from separate E buses, capable of supplying the nuclear service water header, I

are required to be operable.

The two operable pumps can consist of any

)

combination of nuclear and/or conventional service water pumps, provided that i

there are at least three operable nuclear service water pumps per site. The reduced requirements of OPERATIONAL CONDITIONS 4 and 5 account for reduced core decay heat and conventional service water loads and the ability to supply l

the diesel generators from either unit's nuclear header.

During the laitial stage of a DBA (0 - 10 minutes), the service water system l

provides lube water and service water cooling to the diesel generators. The

[

service water system design allows either unit's nuclear header to supply 1

diesel generator cooling water. Two pumps are necessary to supply sufficient j

flow to cool all four diesel generators under 9orst-case scenarios.

l Therefore, any combination of three operable nualear service water pumps per I

site will meet the single failure criteria and a sure diesel generator cooling. The proposed change requires two operadle nuclear service water

.i pumps associated with a unit in OPERATIONAL CONDITIONS 1, 2, or 3 and at least three operable nuclear service water pumps per site when one or both units are l

in OPERATIONAL CONDITIONS 4 or 5.

Consequently, at least two nuclear service i

water pumps are always operable after a DBA to fulfill emergency diesel generator cooling requirements.

j After the initial ten minutes of a DBA, additional loads require cooling water. These loads include RilR and CS pump room ccclers, RilR service water heat exchangers, and RilR pump seal heat exchange:s.

Evaluations have j

determined that the RilR pumps seals, as well as the equipment in rooms serviced by the RilR and CS roca coolers, remain within the manufacturers' temperature limits for the first ten minutes of a DBA. To meet the additional loads during the post-ten minute stage of a DBA, two service water pumps on the affected unit must be in service.

In order to assure single failure criteria is mec, the proposed Technical Specification change requires two operable conventional service water pumps per unit while in OPERATIONAL CONDITION 1, 2, or 3.

As discussed abeve, when in OPERATIONAL CONDITIONS 4 and 5, the reduced core y

decay heat load and the accessibility to the reactor building for manual operator action reduce the requirement for operable service water pumps after an accident / transient to one.

Therefore, when in OPERATIONAL CONDITIONS 4 or 5, two operable service water pumps (any combination of nuclear and/or conventional) capable of supplying the nuclear header are required provided El-2

3 J

I that there are at least three operable nuclear service water pumps per site.

Maintaining two operable service water pumps (nuclear and/or conventional) on the Unit while in OPERATIONAL CONDITIONS 4 or 5 assures long-term cooling can be supplied, even after application of the single failure criteria, Stipulating at least three operable nuclear service water pumps per site assures diesel generator cooling will be available following any DBA, regardless of which Unit suffers the accident / transient.

The allowed out of service times and compensatory measures established in the i

revised Action Statements are consistent with or more conservative than those I

of the existing Technical Specification 3.7.1.2.

In particular, Action l

Statement a.2 for OPERATIONAL CONDITIONS 1, 2, an6 3 requires the unit to be

~

in HOT SHUTDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 i

hours with no operable nuclear service water pumps.

Analyses have been i

performed which demonstrate operation in OPERATIONAL CONDITIONS 1 through 3 I

with no operable nuclear service water pumps is acceptable provided that at i

least two nuclear service water pumps are operable on the opposite unit and two conventional pumps are operable on the affected unit.

Specific Action statements and LCO time limits for this situation have not been developed since a more conservative Action Statement has been established in order to minimize the risk of personnel error in administrating this situation.

I El-3

ENCLOSURE 2 BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 NRC DOCKETS 50 325 & $0-324 OPERATINC LICENSES DPR-71 & DPR 62 REQUEST FOR LICENSE AMENDMENT SERVICE WATER SYSTEM 1Q_G7R 50.92 EVALUATION The Commissioa has provided standards in 10 CPR 50.92(c) for determining whether a significant hazards consideration exists. A proposed amendment to an operating license for a facility involves no significant hazards consideration if operation of the facility in accordance with the proposed amendment would not: (1) involve a significant increase in the probability or consequences of an accident previously evaluated, (2) create the possibility of a now or different kind of accident from any accident previously evaluated, or (3) involve a significant reduction in a margin of safety.

Carolina Power & Light Company has reviewed this proposed license amendment request and determined that its adoption would not involve a significant hazards consideration. The bases for this determination are as follows:

Pronosed Chnnce The proposed amendment revises Technical Specification Section 3.7.1.2 to clarify and expand the service water pump operability requirements, thereby better reflecting the plant design.

The current specification requires the service water system nuclear header to be operable with at least three operable service water pumps. The revised Specification will require both the nuclear and the conventional headers to be operable with two nucicar and two conventional service water pumps capable of supplying the headers when the unit is in OPERATIONAL CONDITIONS 1, 2, or 3.

When the unit is in OPERATIONAL CONDITIONS 4 or 5 the number of required pumps drops to any combination of two nuclear.and/or conventional service water pumps powered from separate emergency buses provided that there are at least three operable nuclear service water pumps per site.

Basis The change does not involve a significant hazards consideration for the following reasons:

1.

The proposed change allows the use of the present plant design and l

capabilities to ensure that an adequate supply of water is available for cooling of the diesel generators and other vital equipment, The proposed change requires both the nuclear and the conventional headers to be operable with two nuclear and two conventional service water pumps capable of supplying the headers when the unit-is in OPERATIONAL CONDITIONS 1,.2, or 3.

This change results in four nuclear service water pumps operable whenever both units are at power.

These expanded requirements fulfill single failure criteria and will ensure the E2-1

L availability of service water for diesel generator cooling during the initial ten minute period of a design basis accident (DBA) and provide.

for sufficient service water capability for the post ten minute period of a DBA. When the unit is in OPERATIONAL CONDITIONS 4 or 5 the number of required pumps drops to any cophination of two nuclear and/or conventional service water pumps, provided that there are at least three operable nuclear service water pumps per site. Maintaining two operable eervice water pumps (nuclear and/or conventional) on the Unit while in OPERATIONAL CONDITIONS 4 or 5 assures long term cooling can be supplied, even after application of the single failure criteria.

Stipulating at least three operable nuclear service water pumps per site assures diesel generator cooling will be available following any DBA, regardless of which Unit suffers the accident / transient.

The allowed out of service times and compensatory measures established in the revised Action Statements are consistent with those of the existing Technical Specification 3,7,1,2, Based on this reasoning, the Company has determined that the proposed amendment does not involve a significant increase in the probability or consequences of an accident previously evaluated.

2.

The service water system is designed to provide lubrication and cooling of equipment during normal operations and under accident conditions,-

The system can also be cross-connected to the RHR system during emergencies to provide core flooding capabilities. The service water system aids in mitigation of an accident, but does not act as an initiator of an accident sequence. The proposed change does not affect the ability of the service water system to perform its intended function.

The requested amendment will assure that the service water system will be available to provide an adequate supply of cooling water for both normal and emergency operation. Therefore, the proposed amendment does not. create the possibility of a new or different kind of accident from any accident previously evaluated, 3.

The proposed change clarifies and expands the service water pump operability requirements to better reflect plant design. These expanded requirements will ensure the availability of service water for diesel generator cooling during the initial ten minute period of a DBA and provide for sufficient service water capability for the post-ten minute period of a DBt.,

The proposed change will provide a higher level o#

assurance of service water system availability for both normal operations and accident conditions.

Therefore, the proposed change does not involve a significant reduction in the margin of safety.

E2-2