m w n j TOLEDO o EDISON February 16, 1982 Log No. K82-299 File: RR 2 (P-6-78-08 P-6-78-ll Docket No. 50-346 P-6-78-12)

License No. NPF-3 Mr. Norman Haller, Director Office of Management and Program Analysis U. S. Nuclear Regulatory Commission Washington, D. C. 20555 ,

Dear Mr. Haller:

Attached are ten copies each of revised Operating Data Reports for Davis-Besse Nuclear Power Station for the months of August 1978, November 1978, and December 1978. These have been revised due to an error in the year-to-date forced outage rate.

Please replace your previous copies of the Operating Data Reports, which are included in our Monthly Operating Reports, with the attached revisions.

If you have any questions, please contact Bilal Sarsour at (419) 259-5000, Extension 384.

",urs truly, aq h #

Terry D. Murray Station Superintendent Davis-Besse Nuclear Power Station TDM/BMS/ljk Attachments cc: Mr. James G. Keppler Regional Administrator, Region III Encl: 1 copy Mr. Richard DeYoung, Director Office of Inspection and Enforcement Encl: 2 copics Mr. Luis Reyes NRC Resident Inspector f $

Encl: 1 copy d'

, D 0 R TOLEDO, OHIO 43652 THE TOtEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE