Text

%q'%

UNITED STATES a

'(

NUCLEAR REGULATORY COMMISSION y,

E WASHINGTON, D. C. 20555

,l March 10, 1982 Docket fio. 50-219 N' 'f f,

L505-82-03-064 9

NC4.] 'N a

?

MARjg 982A f

~

{. %%*/pg /;d Mr. P. B. Fiedler Vice President and Director - Oyster Creek Oyster Creek fluclear Generating Station A

Post Office Box 388 9

d Forked River, fiew Jersey 08731 y

e

Dear Mr. Fiedler:

SUBJECT:

151 REVIEW - OYSTER CF.EEK !;UCLEAR GEr:ERATIr;G STATI0f!

The i;RC staff has initiated a substantial effort to bring current its approvals of inservice inspection relief requests.

The purpose of this letter is to ensure that the information we are supplying to our con-tractors for review is current and reflects the latest requirements for your facility.

For Oyster Creek our review will include your following submittals:

06/15/75 Finfrock (JCP)/D, f;RR (r;RC)

Tech Spec change *28 06/08/79 Finfrock (JCP)/D, liRR.(fiRC)

Provides status of ISI program 09/06/79 Finfrock (JCP)/D, !!RR (f;RC) 151 prog. (enclosed as 3/1/79 l

report) sections 1 and 3 12/11/79 Finfrock (JCP)/D, !;RR (!iRC)

Tech Spec change =76 to reflect 3/1/79 report l

02/05/61 Finfrock (JCP)/Crutchfield Response to RAI i

(l;RC) 1 Any earlier submittals on the subject of the ISI Program will be considered obsolete.

. Based on the subr.ittals, the proposed inspection interval for Oyster Creek is December 1974 to December 1989.

We will be conducting the review against the requirener.ts of the 1974 edition of Section XI of the A5l:E Code up to and including the 5-75 Addenda.

Please determine if there are any additional previous submittals that we should be reviewing.

Likewise, if there are any additional requests for l

relief that should be considered for the proposed inspection interval, l

please submit these requests within 30 days.

V b~ TIN ()

i 8203170565 820310 PDR ADOCK 05000219

") ) j G

PDR

A

. r, L'

Q 4

Mr. P. B. Fiedler fiarch 10, 1982 Note that such requests should deal with only tihe inservice inspection of pressure-bearing components including supports and with system pres-sure tests. The inservice testing of pumps and valves is being treated separately and you will receive information regarding it by separate correspondence.

Your requests should include both exempted components under the terms of the code as well as relief from the requirements of the code in accordance with Paragraph g of 10 CFR 50.55a.

Also please advise when you are using later code versions than the S-75 Addenda (per Item (g)(4)(iv) of 10 CFR 50.55a) for certain examinations, particularly how you are meeting "all related requirements" from the same version.

Because your previous submittals generally seeni to follow the appropriate guidelines, we are proceeding with the review.

Early in that review, we may be contacting you for additicnal information. To expedite the review, please' advise your assigned project manager verbally within 10 days as to previous submittals we should be reviewing or other requests for relief that are forthcoming.

The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.

Sincerely, MA 7

g/

Dennis M. Crutchfield, Chief f

Operating Reactors Eranch #5

(/

Division of Licensing cc:

See next page

/-

l l

ff y'

SI)

'DS DISTRIBUTION DOCKET ACRS (10)

NRC PDR SEPB Local PDR

h. y' ' z, k ORB Reading NSIC DCruichfield HSmith JLombardo OELD Ol&E

, DL4,[

,DL
ORM#1 DL:,0RB #,

pcrh@pBg,M..hf,i, eld oma>

sua - > JLos ar...

pCh,an

.J !.!AA..

2

. 3,,

om>

sac ronu ais oo-*23 sncu o243

,'O FFICI AL R ECOR D COPY uscm. mi-ax. m

Mr. P. B. Fiedler March 10, 1982 CC l

G. F. Tro'wbridge, Esquire Resident Inspector Shaw, Pittman, Potts and Trowbridge c/o U. S. NRC 1800 M Street, N. W.

Post Office Box 445 Washington, D. C.

20036 Forked River, New Jersey 08731 J. B. Lieberman, Esquire Commissioner Berlack, Israels & Liebeman New Jersey Department of Energy 26 Broadway 101 Commerce Street New York, New York 10004 Newark, New Jersey 07102 Natural Resources Defense Council Ronald C. Haynes, Regional Administrator 917 15th Street, N. W.

Nuclear Regulatory Commission, Region I Washington, D. C.

20006 Office of Inspection and Enforcement 631 Park Avenue J. Knubel King of Prussia, Pennsylvania 19406 BWR Licensing Manager GGPU Nuclear 100 Interplace Parkway Parsippany, New Jersey 07054 Deputy Attorney General State of New Jersey Department of Law and Public Safety.

36 West State Street.- CN 112 Trenton, New Jersey 08625 Mayor Lacey Township 818 Lacey Road Forked Piver, New Jersey 08731 U. S. Environmental Protection Agency Region II Office ATTN:

Regional Radiation Representative 26 Federal Plaza New York, New York 10007 Licensing Supervisor Oyster Creek Nuclear Generating Station Post Office Box 388 Forked River, New Jersey 08731