Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-424/81-13 & 50-425/81-15
ML20041A833
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/09/1982
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML20041A834 List:
References
NUDOCS 8202220568
Download: ML20041A833 (2)


See also: IR 05000424/1981013

Text

.

_

._.

.

~_.

..

.

.

__ _

.

. f.1

') d

.

.

.

4

FEB 0 9198I

Georgia Power Company

,

ATTN: Mr. J. N. Miller Jr.

<

Executive Vice President

P. O. Box 4545

,

Atlanta GA 30318

,

Gentlemen:

'

Subject:

Report Nos

3'and 50-425/81-15

Thank you for your letter of January 28. 1882 informing us of stepryou

have taken to correct the violation concerning activities under NRC

Construction Permit No. CPPR-108 add CPPR-109 brought to your attention in

our letter of December 28, 1981. We will examine your corrective actions

and plans during subsequ6nt inspections.

We appreciate your cooperation with us.

Sincerely.

.

F. J. Long. Acting Chief

Reactor Projects Branch 2

Division of Resident and Reactor

Project Inspection

ec:

H. H. Gregory. III. Construction

Project Manager

E. D. Groover QA Site Supervisor

D. O. Foster. Project General Manager

bec: NRC Resident Inspector

Document Management Branch

l

State of GA

44CQy ,

i

s'v

'o , ,

'

e'<

)

RI :RRPI

'Y

f

N3v

l'

f

RII: RPI

RI):R I

JRogge:ls

VBrownlee

FJL g

(

- ; i ," ,

o

C

2/g /82

2/h/82

2/ /82

-e

'

N'[

h

M

g'

77-

B20222056B 820209

PDR ADOCK 05000

///

l