i t.
. ;3. :
?-
PHILADELPHIA ELECTRIC COMPANY t'
LIMERICK GENEIU.fING STATION, UNITS 1 & 2 DOCKET NOS.~50-352 & 50-353 ORDER EXTENDING CONSTRUCTION COMPLETION DATES Philadelphia Electric Company is the holder of Construction Permits CPPR-106 and CPPR-107 issued by the Commission on June 19, 1974.
~
These permits authorize the construction of the Limerick Generating
~
Station, Units 1 & 2, presently under construction at.the Company's site. This site is located on the Schuylkill River, near Pottstown, in Limerick Township, Montgomery County, Pennsylvania.
.On September 10, 1974, Philadelphia Electric Company filed a request i
\\
for an extencion of the earliest and latest construction co=pletion dates for these units.
l Philadelphia Electric Cocpany gave as reasons for the schedule change a reduction in their planned construction program by approximately
$600 million for the five-year period 1974-1978 due to (1) high l
l interest rates, (2) extremely tight credit, (3) the severely depressed stock market, and (4) uncertain economic conditions. This action in'olves no significant hazards consideration. Good cause has l
v l
been shown for extension of the earliast and latest construction 1
completion dates for Unit 1 to October 1,1979 and April 1,1981, 1
I
(
l 3
s2020io29s eaotas yr.m
. mm c
.- -- - - -- - r.
1-PDR ADOCK 05000352 G
ea
.r s.-
, */
' [. ~
' - +! '
~
e:
respectively.
Good cause has also been shown for extension.of the
.b earliest and latest construction completion dates for Unit 2 tc March 1,.1981 and April 1, 1982, respectively'. The bases for the extension of these dates is set forth in a staff evaluation, dated May 13, 1975.
It is HEREBY ORDERED THAT THE earliest and latest completion date for CPPR-106 be extended from:
Earliest: April 1, 1979 to October 1, 1979 Latest:
October 1, 1979 to April.1, 1981
~
and that the earliest and latest completion date for CPPR-107 be extended from:
Earliest: Septecher 1, 1980 to March 1, 1981 Latest:
March 1, 1981 to April 1, 1982.
i
.FOR THE NUCLEAR REGULATORY COMMISSION
?
-RichardC.DeYoung,Asistantpirector W
for Light Water Reactors Gr'oup 1 Division of Reactor Licensing Date of Issuance: