ML20039E450

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-309/81-30,on 811112-1215.Noncompliance Noted:Failure to Monitor Personnel Exposure Per Approved Procedures
ML20039E450
Person / Time
Site: Maine Yankee
Issue date: 12/22/1981
From: Gallo R, Lazarus W, Swetland P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20039E446 List:
References
50-309-81-30, NUDOCS 8201070303
Download: ML20039E450 (10)


See also: IR 05000309/1981030

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

50309-811210

0FFICE OF INSPECTION AND ENFORCEMENT

50309-811130

Region I

Report No.

81-30

Docket No.

50-309

License No. DPR-36

Priority

--

Category

C

Licensee:

Maine Yankee Atomic Power Company-

1671 Worcester Road

Framingham, Massachusetts 01701

Facility Name: Maine Yankee Nuclear Power Station

Inspection at:

Wiscasset, Maine

Inspection conducted: November 12 - December 15, 1981.

Inspectors:

3 /u

'

O

~

Swetlaf)ttj Rea

r Inspector

date signed

P[ h

& 6e

iz n /si

w

W. Lazarus, Reactor Inspector

date signed

date signed-

Approved by:

b

I

Rl

R. Gallo, Chief, Reactor Projects

dat'e sigh 6d

Section No. 1A, DRPI

Inspection Summary:

Inspection on:

November 12 - December 15,1981 (Report ~ No. 50-309/81-30)

Areas Inspected:

Routine, regular and backshift inspection by the resident

inspectors (108 hours0.00125 days <br />0.03 hours <br />1.785714e-4 weeks <br />4.1094e-5 months <br />). Areas inspected included the Control Room. Turbine Building,

Primary Auxiliary Building, Spray Building, and Auxiliary Feed Pump Room. Acti-

vities/ Records inspected included Plant Operations, Radiation Protection, Physical

Security, followup of previous inspection findings, observation of maintenance and

surveillance testing, followup of Potential Generic Issues, In-office Review of

Licensee Event Reports, followup of Events Occurring during the Inspect % n.

Results: Of the eight areas inspected no items of noncompliance were identified

in seven areas; one item of noncompliance (Failure to monitor personnel exposure

in accordance with approved procedures, Detail 3.d) was identified in the re-

maining area.

Items were opened on containment isolati n of main steam line

-drains (Detail 3.h) and 10 CFR 50.59 safety evaluations for jumper / bypass modifi-

cations (Detail 2.h).

Region I Form 12

(Rev. April 77)

Q 1 Q f o b b

Qm

G

PDR

-

-

-

.

.

DETAILS

1.

Persons Contacted

R. Arsenault, Operations Department Head

J. Brinkler, Tecnr.ical Support Department Head

G. Cochrane, Health Physics Supervisor

R. Forrest, Fire Protection Coordinator

D. Hakkila, Administrative Department Head

W. Paine, Assistant to the Plant Manager

R. Prouty, Maintenance Department Head

R. Radasch, I & C Supervisor

D. Sturniolo, Technical Assistant to the Plant Manager

E. Wood, Plant Manager

The inspectors also interviewed several plant operators, technicians

and members of the engineering and administrative staffs,

2.

Followup on Previous Inspection Findings

a.

(Closed) Followup Items (309/76-01-01, 76-01-02 and 79-13-01)

Integrated Containment Leakrate Testing Discrepancies.

NRC Licensing action in this area is ongoing.

Further progress will

be tracked by Technical Assignment Control Number 08897.

b.

(Closed) Followup Item (309/78-BU-12) Atypical Weld Material in

Reactor Pressure Vessel Welds.

The inspector contacted G. Georgiev of NRC Licensing to confirm that

the licensee's response supplemented by specific information included

in a generic report submitted by Combustion Engineering (vessel fabri-

cator) was sufficient to meet the short term objectives of this

bulletin. NRC Licensing Generic Letter 81-19, Reactor Vessel Pressurized

Thennal Shock Issue, encompasses long term corrective actions to ensure

reactor vessel integrity.

c.

(Closed) Followup Item (309/79-BU-02) Pipe Support Base Plate Design.

Based on contacts with J. Fair, IE HQTRS and L. Tripp, Region I, the

inspector detennined that no unresolved items were outstanding for this

licensee and that no further action is pending.

d.

(Closed) Unresolved Item (309/80-10-01) Review acceptibility of

prolonged Reactor Protection System operation with a 2 of 3 logic.

NRC Licensing action on this item has been initiated by NRC letter

dated April 16, 1981. Further progress will be tracked by Technical

Assignment Control Number 08902.

_ . -

_

-

-

_

_

-

-

-

.

.

3

e.

(Closed) Followup Item (309/80-17-01) Licensee to Revise Pump Test

Acceptance Criteria.

The inspector reviewed revised procedure 3.17.6.6, Inservice Testing

of Safeguards Pumps, Revision 2, dated 3/19/81. Acceptance criteria

derived from the ASME Section XI requirements are required to be

specified on the test data sheet. The inspector had no further questions

in this area.

f.

(Closed) Unresolved Item (309/81-04-04) Adequacy of Standpipe Pressure.

The licensee verified by c ntact with representatives of American

Nuclear Insurers and the National Fire Protection Association that the

maximum fire pump pressure (150 psi) would not hamper the ability of

fire brigade members to control the lh" fire hoses. No further inade-

quacies were identified.

g.

(Closed) Unresolved Item (309/81-04-05) Adequacy of Fire Water System

to Supply Sprinkler Systems.

The licensee determined that the questioned design flow rate and

pressure were maximum values to prevent the dilution of the aqueous

film during the extinguishing process. Minimum flow rate and pressure

were verified with W. McNeil of ITT Grine11 to be 79 gallons per

minute at 115 psi. The fire water system capacity was verified to meet

these criteria. The inspector had no further questions in this area.

h.

(Closed) Followup Items (309/SB-80-01 and SB-80-02) Licensee Compliance

with 10 CFR 50.59.

The inspector reviewed the licensee's familiarity and compliance with

the requirements specified in 10 CFR 50.59. Modifications which are

identified as design changes / alterations receive appropriate review

and documentation in accordance with the licensee's quality assurance

program. The inspector determined that the licensee's procedure for

jumpers and bypass functions allow system modification without the

required safety evaluation. Specifically, procedure 16.1, " Maine Yankee

Operation Safeguard, Yellow Tag Control", controls the use of jumpers /

bypasses within the facility, but the procedure does not provide measures

to insure that the requirements of 10 CFR 50.59 are completed prior to

returnir,g safety systems to service in a modified condition. The in-

spector reviewed the previous yellow tag requests to determine whether

modifications had been made to safety functions using this procedure.

Of the fifty jumpers / bypasses installed during 1981, one jumper (Ser.

  1. 81-49) altered a safety function described in the Final Safety

'nalysisReport(FSAR).

Automatic trip valve PCC-A-299 isolates

component cooling water flow from the high pressure drain cooler on

high flow in the component cooling outlet line. This high flow is

.

.

4

indicative of a tube rupture in the drain cooler. Upon failure of

the trip initiation micro switch, the valve failed shut rendering

the drain cooler inoperable. To restore the cooler to service, pending

receipt of spare parts, the licensee jumpered the trip circuit to

allow manual operation of PCC-A-299. This modification defeated the

safety function of the trip valve. No safety evaluation was documented

justifying this action.

The inspector brought this finding to the attention of the Assistant

Plant Manager on November 20, 1981. The licensee concurred that the

Yellow Tag Procedure did not require written safety evaluations for

those jumpers which alter the FSAR description of systems affecting

the safety of operations. The licensee committed to modify procedures

to require that systems returned to operation in a condition different

from the FSAR description shall be evaluated in accordance with

10 CFR 50.59 prior to return to service and to complete this action

prior to February 1, 1981.

This item is unresolved pending NRC review of licensee corrective

actions.

(309/81-30-01)

3.

Review of Plant Operations - Plant Inspections

The inspector reviewed pl'nt operation through direct observation through-

out the reporting period. Except as noted below, conditions were found

to be in compliance with the following licensee documents:

Maine Yankee Technical Specifications

--

Maine Yankee Technical Data Book

--

Maine Yankee Fire Protection Program

--

--

Maine Yankee Radiation Protection Program

Maine Yankee Tagging Rules

--

Administrative and Operating Procedures

--

a.

Instrumentation

Control room process instruments were observed for correlation between

channels and for conformance with Technical Specification requirements.

Ho unacceptable conditions were identified.

b.

Annunciator Alarms

The inspector observed various alarm conditions which had been received

and acknowledged. These conditions were discussed with shift personnel

who were knowledgeable of the alarms and actions required. Operator

response was verified to be in accordance with procedure 2-100-1,

Response to Panalarms, Revision 4, dated June 1979. During plant

inspection, the inspector observed the condition of equipment asso-

ciated with various alarms. No unacceptable conditions were identified.

- .

.

.

(:

5

c.

Shift Manning

The operating shifts were observed to be staffed to meet the operating

requirements of Technical Specifications, Section 5, both to the

number and type of licenses. Control room and shift manning were-

observed to be in conformance with 10 CFR 50.54.

d.

Radiation Protection Controls

Radiation Protection control areas were inspected. Radiation Work

Permits in use were reviewed, and compliance with those documents,

as to protective clothing and required monitoring instruments, was

inspected.

Proper posting and control of radiation and high radiation

areas was reviewed in addition'to verifying' requirements for wearing

of appropriate personnel monitoring devices.

On November 13, 1981, the inspector observed two workmen performing

system modifications inside the "A" charging pump cubicle. This area

was posted as a !'High Radiation Area; Radiation Work Permit (RWP)

Required". The workers did r.ot meet the High Radiation Area require-

ments of Technical Specification (TS) 5.12 in that neither a continuous

monitoring device nor health physics personnel coverage was-provided.

The inspector reviewed RWP 81-11-64 which granted access to all three

charging pump cubicles. The RWP required the workers to carry a

radiation survey meter to satisfy the monitoring requirement of TS 5.12.

The work party supervisor had signed the RWP acknowledging

the specified requirements; however, the workmen had not signed the

RWP. The work party left the high radiation area, signed the RWP,

and obtained the required survey meter prior to re antering the

area.

Subsequent verification.of radiation dose rates -in the charging

pump cubicles revealed that cubicles A and B had maximun dose rates

of 40 - 60 mrem /hr while cubicle S had maximum dose rates of 100-110

mrem /hr. Although the workmen were observed in a dose rate area

less than 100 mrem /hr, the exposure controls specified pursuant to

10 CFR 20, TS 5.11 and Radiation Protection Procedure 9-1-10, Radia-

tion Work Permits, Revision 10 were applicable since the RWP did not

differentiate requirements for cubicles A, B, and S. The inspector

brought this finding to the attention of the Radiation Controls

Supervisor on November 13, 1981.

Failure to acknowledge and comply with RWP requirements is contrary

to TS 5.11 and Procedure 9.1.10, and collectively constitutes an

item of noncompliance.

(309/81-30-02)

e.

Plant Housekeeping Controls

Storage of material and components was observed with respect to

prevention of fire and safety hazards. Plant housekeeping was eval-

uated with respect to controlling the spread of surface and airborne

contamination. There were'no unacceptable conditions identified.

!

!

-

- -

.

. -

-

.

-

-

-

- - -

-

.

- .

.

<

.

.

6

f.

Fire Protection / Prevention

The inspector examined the condition of selected pieces of fire

fighting equipment. Combustible materials were being controlled and

were not found near vital areas. Selected cable penetrations were

examined and fire barriers were found intact. Cable trays were

clear of debris.

On December 3,1981, the inspector observed the fire door between the

Computer Room and the Main Control Room to be propped open. This

door is required to be closed in accordance with the site fire

protection program. The door was opened by security personnel to

reduce internal control room pressure, to facilitate the closing of

alarmed vital area doors. The fire door was subsequently closed.

The inspector discussed this finding with the Fire Protection Coor-

dinator, Security Supervisor, and the Operations Department Head.

Maintenance of fire barriers was emphasized and coordination of

Control Room pressure conditions as they affect security systems was

,

i

established.

No further abnormal conditions were identified.

g.

Control of Equipment

During plant inspections, selected equipment under safety tag control

were examined. Equipment conditions were consistent with information

in plint control logs.

h.

Equipment Lineups

The inspector verified by observation of the Main Control Board and

by inspections in the Diesel Generator and Auxiliary Feed Pump Rooms

and in the Spray and Turbine Buildings that the major valve and

switch positions were correct to insure operability of the Safety

Injection System, the Safety Injection Accumulators, Containment

Spray, Auxiliary Feedwater, and the Emergency Diesel Generators.

The inspector reviewed the arrangement of containment penetration

isolation systems with respect to the FSAR Chapter 5, General Design

Criteria (GDC) 55, 56 and 57, Operating Procedure 1-12-5, Revision 12,

" Establishment of Containment Integrity", and various plant drawings.

The inspector verified the lineup of selected penetration isolation

valves. No isolation valves were found to be out of position. The

inspector identified six normally shut manual isolation valves in

the main steam line drain system which were not controlled by the

licensee's containment integrity checklist. Three main steam line

drains upstream of the main steam isolation valves (MSIV) lead to a

combined header which has an automatic containment isolation valve

installed. A fourth drain from the atmospheric dump line (also up-

stream of the MSIV) is not provided with a similar isolation capability.

. - - -

. .

-

---.

.

- .

--.=z.

4.'.

-

A.

-

4

aA.m-

. .

7

The inspector reviewed this finding with the Operations Department Head

on December 3,1981 and subsequently with the Senior Plant Mechanical

^

Engineer.

No documented deviation from the containment' isolation.

l

schemes cited by the FSAR and GDC 57 was identified, although the

water hammer hazard created by operation of the atmospheric dump

-

- system without condensation drains was proposed.

The licensee tagged the uncontrolled isolation valves closed pending

revision of Operating Procedure 1-12-5 to include these valves. The

isolation of the atmospheric-dump system _was discussed at a meeting

of the Plant Operations Review Cumnittee. Corrective action includes

an evaluation of the. water hammer. potential in this line followed

by system modification or application for deviation from the containment-

. isolation requirement.

This item is unresolved pending NRC review of licensee corrective

actions.

(309/81-30-03)

4.

Review of Plant Operations - Logs and Records-

During the inspection period, the inspector reviewed operating logs and

records covering the inspection time period against Technical Specifications

j

and Administrative Procedure Requirements.

Included in the review were:

'

Control Room Log

- daily during control room surveillance

-

Jumper and Lifted Leads Log

- - all. active entries

a

Maintenance Requests and Job Orders - all active entries

Safety Tag Log

- all active entries

daily during control room surveillance

. Plant Recorder Traces

-

Plant Process Computer Printed

daily during control room surveillance

Output _

-

Night Orders

- -daily during control room surveillance

The logs and records were reviewed to verify that entries are properly-

l

' made and connunicate equipment status / deficiencies; records ~are being

reviewed by management; operating orders do not conflict with the Technical

,

Specifications; logs detail no violations of Tecnnical Specification or

reporting requirements; logs and records are maintained in accordance with

,

Technical Specification and Administrative Control Procedure requirements.

i

Several entries in these logs were the subject of additional review and

,

discussion with licensee personnel. No unacceptable conditions were

j

identified.

5.

Observation of Physical Security

The resident inspector made observations, witnessed and/or verified, .

l

during regular and off-shift hours, that the selected aspects of the .l

security plan we.e in accordance with regulatory requirements, physica

!

security plans and approved procedures.

i

,

f

-- ...

m. .

.

.

.

.

.m.

. .

.

.

..m . ..

.

m

m-

. .

m.

.

.

.

...

u

--

- . .

. -- -

-

. .

m

-

..m

.-.

..

.

8

--

Maine Yankee Security Plan, dated October 1979

--

15-1, Security Organization and Responsibilities, Revision 6,

April 1980

15-2, Security Force Duties, Revision 9, February 1981

--

--

15-3, Plant Personnel Security, Revision 9, February 1981

15-7, Access Authorization and Contro; . Revision 1, April 1981

--

15-8, Protected Area Entry / Exit Control, Revision 1, September

--

1980

a.

Physical Protection Security Organization

Observations and personnel interviews indicated that a full

--

time member of the security organization with authority to

direct physical security actions was present, as required.

--

Manning of all three shifts on various days was ' observed to

be as required.

b.

Physical Barriers

Selected barriers in the protected area, access controlled area,

and the vital areas were observed and random monitoring of isolation

zones was performed.

Observations of truck and car searches were

made.

c.

Access Control

Observations of the following items were made:

Identification, authorization and badging

--

--

Access control searches

--

Escorting

--

Comnunications

Compensatory measures when required.

--

No items of noncompliance were identified.

6.

Observation of Maintenance and Surveillance Testing

The inspector observed the maintenance and problem investigation activities

listed below. The inspector reviewed these activities to verify compliance

with regulatory. requirements, including those stated in the Technical

Specifications; compliance with applicable codes and standards; required

QA/QC involvement; proper use of safety tags; proper equipment alignment

and use of jumpers; appropriate personnel qualifications; proper radiolo-

gical controls for worker protection; adequate fire protection; and appro-

priate retest requirements. The inspector also ascertained reportability

as required by Technical Specifications.

-

-

- -

-

-

..

..

1

9

The inspector witnessed the performance of surveillance testing (listed

below) of-selected components to verify.that the surveillanca test procedure

was properly approved and in use;_ test. instrumentation required by the

procedure was properly calibrated and in use; technical specifications

were satisfied prior to removal of the system from service;~ test was

performed by qualified personnel; the procedure was adequately detailed

to assure performance of a satisfactory surveillance; and, test results

satisfied the procedural acceptance criteria, or were properly disposi-

tioned.

The following evolutions were reviewed / witnessed:

Plant Alteration (PA) 8-81 - Diesel Generator Tachometer Modification;

--

Surveillance Procedure 3.6.2.2.5 - Steam Generator Pressu e Monthly _

---

LTest, Channel C, 12/11/81;

--

Surveillance Procedure 3.1.2 - Emergency Core Cooling Monthly Tests,

11/18/81.

PA 8-81 installed digital tachometers on both emergency diesel generators.

The modification requires mounting a magnetic probe in close proximity to

the engine fly wheel. The tachometers have no safety function for the

diesel generator; however, the inspector questioned the potential for

vibration loosening of the mounting bracket and the resultant effect on

system operability. . Since the mounting bracket replaces and is similar to

the crank shaft position indicator already installed, and no loosening of

the indicator has been experienced, the licensee determined that the

installation did not affect the operability of the diesel. The inspector

had no further questions in this area.

On December 11, 1981, during the performance of reactor protection system

monthly testing for channel C steam generator pressure,three safety set-

points were noted to be out of specification. Evaluation of the data

indicated that all values were consistently low. Maintenance had been

performed earlier on -the channel C test trunk cable. Since the test unit

had been de-energized during the maintenance, it was determined that in-

sufficient warm-up was a possible cause.

Subsequent testing of channel C'

verified this evaluation in that new values were well within tolerance.

No inadequacies were identified.

.. ..

10

7.

Followup on Potential Generic Issue

NRC Region IV forwarded a potential safety concern (Serial #81-12) related

to Rosemunt resistance temperature detectors (RTD).

Combustion Engineering

(CE) reported the potential for galvanic corrosion of the RTD terminal

blocks and the resultant inaccuracy of RTD readings. The inspector

determined through contacts with the Instrumentation and Control Super-

visor and the resident CE representative that the licensee was aware of

this problem and that the plant had not experienced any terminal corrosi m

problems. The lack of corrosion was due to using like-metals (nickel

plated) for tenninals, lugs and fasteners. The inspector had no further

questions in this area.

8.

In-Office Review of Licensee Event Reports (LERs)

The inspector reviewed the following LERs received in the RI office to

verify that details of the event were clearly reported including the

accuracy of the description of cause and adequacy of corrective action.

The inspector also determined whether further information was required

from the licensee, whether generic implications were indicated, and whether

the event warranted on site followup. The following LER was reviewed:

--

81-24 Exceeded Vent Stack Sample Frequency

9.

Followup on Events Occurring During the Inspection

On December 10, 1981, during routine Control Element Assembly exercising,

control rod #38 dropped into the core. Operators adequately implemented

Casualty Procedure 2-21, " Control Rod Drop", Revision 12, and maintained

the plant within license conditions. The plant was restored to nonnal

conditions in a professional manner and the notification requirements of

10 CFR 50.72 were met. No cause for the rod drop was determined.

Industry

experience indicates that the reversal of rod sequencing sometimes allows

the rod to be momentarily unrestrained. This information is included in

operator training, and is being studied by Combustion Engineering. The

inspector had no further questions in this area.

10.

Unresolved Items

Unresolved items are matters about which more information is required in

order to determine whether they are acceptable items or items of noncom-

pliance. Unresolved items identified during this inspection are discussM

in paragraph 2h and 3h.

11.

Exit Interviews

At periodic intervals during the course of the inspection, meetings were

held with senior facility management to discuss the inspection scope and

findings.

-