ML20032A548

From kanterella
Jump to navigation Jump to search
Proposed Changes to Tech Specs 3/4.8 Re Electrical Power Sys.Extends Outage Time to 18 Days,Start Time to 12-s & Modifies Test Frequency Basis
ML20032A548
Person / Time
Site: Farley  
Issue date: 10/28/1981
From:
ALABAMA POWER CO.
To:
Shared Package
ML20032A545 List:
References
NUDOCS 8110300329
Download: ML20032A548 (16)


Text

.,.

Unit 1 Technical Specifications 8110300329 810228 PDR ADOCK 05000348 P

PDn

O 3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power. sources shall be OPERABLE:

a.

Two physically independent circuits between the offsite transmission network to the switchyard and two physically independent circuits from the switchyard to the onsite Class 1E distribution system, and b.

Two separate and independent diesel generator sets (Set A:

DG 1-2A and DG-1C, Set B: DG-1B and DG-2C) each with:

1.

Separate day tanks containing a minimum volume of 900 gallons of fuel for the 4075 kw diesel generators and 700 gallons of fuel for the 2850 kw diesel generator.

2.

A separate fuel transfer pump for each diesel.

c.

A fuel storage system consisting of four, independent storage tanks each containing a minimum of 25,000 gallons of fuel.*

l APPLICABILITY: MODES 1, 2, 3 and 4.

ACTION:

a.

With an offsite circuit inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.e within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter; restore at least two offsite circuits to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

The provisions of Specification 3.0.4 are not applicable.

l b.

With one diesel generator set inoperable, demonstrate the operability of the offsite A.C. sources and the other diesel set ** by performina Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.e within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and at least once per 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> thereafter. Restore both diesel generator sets to OPERABLE status within 18# days or be in at least H0T STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. The provisions of Specificatior 3.0.4 are not applicable.

One operable fuel storage tank must be available for each required oiesel generator.

  1. The time for restoring the diesel set to OPERABLE status may be extended if requalification of a diesel is required as indicated in Table 4.8-1.

For the purpose of diesel operability determination, the diesel set is defined as the parallel diesel in the opposite train.

FARLEY UNIT 1 3/4 8-1

~

ACTION-(continued)

With one o' fsite circuit and one diesel generator set of the above f

c.

required A.C. electrical power sources ^ inoperable, demonstrate the OPERABLILITY of the' remaining offsite A.C. source and diesel set by performir g Surveil 7 ance Requirements 4.8.1.1.1.a and 4.8.1.1.2.e

-within two hours; rastore at least one of the inoperable sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within

'l the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

Restore the other AC power source (offsite cirucit or diesel generator set) to OPERABLE status in accordance with the provisions of Section 3.8.1.1 Action Statements a or b, as appropriate.

d.

With two of the above required offsite A.C. circuits inoperable, demonstrate the OPERABILITY of both diesel generator sets by performing Surveillance Requirement 4.8.1.1.2.e within two hours; l

unless the diesel generators are already operating; restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. With only one offsite source restored, restore both offsite circuits to OPERABLE status within 7 days from time of initial loss or be.in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

e.

With both of the above required diesel generator sets inoperable, demonstrate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within two hours; j

restore at least one of the inoperable diesel generator sets to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least H0T STANDBf within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Restore both diesel generator sets to OPERABLE status within 18# days from time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.8.1.1.1 Each of the above required independent circuits batween the offsite transmission network and the onsite Class IE distribution system shall be:

a.

Determined OPERABLE at least once per 7 days by verifying correct breaker alignments, indicated power availability, and b.

Demonstrated OPERABLE at least once per 18 months during shutdown by transferring unit power supply from the normal circuit to the alternate circuit.

  1. The time for restoring both diesel sets to OPERABLE status may be extended if requalification of a diesel is required as indicated in Table 4.8-1.

FARLEY UNIT 1 3/4 8-2

e' ELECTRICAL POWER SYSTEMS 5

~.

SURVEILLANCE REQUIREMENTS (Continued) 4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:

a.

In accordance with the frequency specified in Table 4.8-1 on a STAGGERED TEST BASIS by:

1.

Verifying the fuel level in the day tank, 2.

Verifying the fuel level in the fuel storage tanks, 3.

Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the da; tank, 4.

Verifying the diesel starts and accelerates to at least l

900 rpm, for the 2850 kw generator and 514 rpm for the 4075 kw generators, in less than or equal to 12 seconds.

l The generator voltage and frequency shall be 1 3952 volts and l 57 Hz within 12 seconds after the start

,]

signal.

5.

Verifying the generator is synchronized, loaded to 2700-2850 kw for the 2850 kw generator and 3875-4075 kw for the 4075 kw generator and operates for greater than or equal to 60 minutes.

6.

Verifying the diesel generator is aligned to provide standby power to the associated emergency busses.

I b.

At least once per 92 ' days by verifying that a sample of diesel fuel from the fuel storage tank obtained in accordance with ASTM-D270-65, is within the acceptable limits specified in Table 1 of ASTM 0975-74 when checked for viscosity, water and sediment.

c.

At least once per 18 months by:

1.

Subjecting the diesel to an inspection in accordance with procedures prepared in conjunction with its manufacturer's reconnendations for this class of standby service, 2.

Verifying the capability to reject a load of greater than or equal to the largest single load associated with that diesel generator, while maintaining voltage between 3120 and 4910 volts and speed less than or equal to 75% of the difference between nominal speed and the overspeed trip setpoint and verifying recovery to 4160 i 420 volts and 60 i 1.2 Hz within 2 seconds.

3.

Verifying that on an Safety Injection test signal (without loss of offsite power) the diesel generator starts on the auto-start signal and operates on standby for greater than or equal to 5 minutes. The generator voltage and frequency shall be 2. 3952 volts and > 57 Hz within 12 seconds after the auto-start signal; the steady state generator voltage and frequency shall be main-tained between 4160

  • 420 volts and 60 i 1.2 Hz during this test.

FARLEY UNIT 1 3/4 8-3

ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) 4.

Simulating a loss of offsite power in conjunction with a Safety Injection test signal, and a) Verifying de-energization of the emergency busses and -

load shedding from the emergency busses.

b) Verifying the diesel starts on the auto-start signal, 1-energizes the emergency busses with permanently connected loads within 12 seconds, energizes the auto-connected emergency (accident) loads through the load sequencer and operates for greater _than or equal to 5 minutes while its generator is' loaded with the emergency loads. After energization, the steady state voltage and frequency of the emergency busses shall be maintained at 4160 1 420 volts and 60

  • 1.2 Hz during this test.

c) Verifying that all automatic diesel generator. trips, except engine overspeed and generator differential and.

low lube oil pressure, are automatically bypassed upon loss of voltage on the emergency bus and/or a safety injection test signal.

5.

Verifying the diesel generator operates for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The diesel generator shall be loaded to 3875-4075 kw for the 4075 kw diesels and 2700-2850 kw for the 2850 kw diesels.

6.

Verifying that the auto-connected lo. ids to each diesel generator do not exc.eed the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 4353 kw for the 4075 kw generator and 3100 kw for the 2850 kw generator.

7.

Verifying the diesel generator's capability to:

a)

Synchronize with the offsite power source while the generator is loaded ' ith its emergency loads upon a w

simulated restoration of offsite power, b) Transfer its loads to the offsite power source, and c) Be restored to its standby status.

8.

Verifying that with the diesel generators operating in a test

~

mode (connected to its bus), a simulated safety injection signsi overrides the test mode by returning the diesel generator to standby operation.

9.

Verifying that the automatic load sequence tiner is OPERABLE with each load sequence time within i 10% of its required value or 0.5 seconds whichever is greater.

FARLEY UNIT 1 3/4 8-4

r ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued)

10. Verifying that the.following diesel generator lockout features prevent diesel generator starting only when the diesel is in the test mode:

a) Oil Temperature High (OTH) b) Coolant Temperature High (CTH) c) Coolant Pressure Low (CPL) d) Crankcase Pressure High (CCPH) d.

At least once per 10 years or after any modifications which could affect diesel generator interdependence by starting the diesel generators simultaneously, and verifying that the diescl generators accelerate to at least 900 rpm, for the 2850 kw generator and 514 rpm for the 4075 kw generator, in less than or equal to 12 seconds.

e.

The diesel generator shall be determined OPERABLE by verifying that the diesel-is not out of service nor in an Initial Requalification Program, as defined in Table 4.8-1.

4.8.1.1.3 Reports - All diesel generator failures, valid or non-valid, shall be reported to the Commission pursuant to Specification 6.9.1.

Reports of diesel generator failures shall include the information recomended in Regulatory Position C.3.b of Regulatory Guide 1.108, Revision 1, August, 1977.

If the number of failures in the last 100 valid tests (on a per diesel basis) is greater than or equal to 7, the report shall be supplemented to include the additional information recommended in Regulatory Position C.3.b of Regulatory Guide 1.108, Revision 1, August, 1977.

FARLEY UNIT 1 3/4 8-5

D TABLE 4.8 DIESEL GEhERATOR TEST SCHEDULE (PER DIESEL)

NORMAL TEST' FREQUENCY TEST FREQUENCY _

NUMBER OF SUCCESSFUL TEST *-

at least once per 14 days

> 19 of last 20 tests and > 95 of last 100 tests at least once per 7 days 18~of last 20 tests and > 95 of last 100 tests 16 or 17 of last 20 tests or at least once per 7 days between 90 and 94 of last T00 tests and implement diesel generator Reliability Improvement PrcJram #

unless requalification just completed REQUALIFICATION TEST FREQUENCY _

perform diesel generator 215 of last 20 tests or > 89 of requalification**

-- -~

last 100 tests i

l d

  • Criteria for determining valid test and failures shall be in accor ance with Regulatory Position C.2.e of Regulatory Guide 1.108.

l

    • Requalification of the diesel generator shall con l

I ility tests (Initisi Requalification) within u45 days fro t

Subsequent to 14 cor.secutive successful tests, the test Section frequency for that diesel shall be determined by Table 4.8-1.

frequency.

4.8.1.1.2.a.4 defines a successful test.

  1. Report a description of the Reliability Improvement Prog i

ion.

recommendations of NUREG/CR-0660 and its implementation to j

3/4 8-6

.FARLEY UNIT 1

e' ELECTRICAL DOWER SYSTEMS SHUTDOWN LIMITING CONDITION FOR OPERATION 3.8.1.2 As a minimum, the following A.C. electrical power sources shall be OPERABLE:

a.

One circuit from the.offsite transmission network to the switchyard and from the switchyard to the onsite Class 1E distribution system, and b.

Diesel Generator 1-2A or 1C or diesel generator IB each with:

1.

A day tank containing a minimum volume of 900 gallons of fuel for the 4075 kw diesel generator and 700 gallons of fuel for the 2850 kw diesel generator.

2.

A fuel storage' tank containing a minimum volume of 25,000 gallons of fuel, and 3.

A fuel transfer pump.

APPLICABILITY: MODES 5 and 6.

ACTION:

With less than the above minimum required A.C. electrical power sources OPERABLE, suspend all operations involving CORE ALTERATIONS or positive reactivity changes until the minimum required A.C. electrical power sources are restored to OPERABLE status.

SURVEILLANCE REQUIREMENTS l

i 4.8.1.2 The above required A.C. electrical power sources shall be demonstrated OPERABLE by the performance of each of the Surveillance Requirements of 4.8.1.1.1 and 4.8.7.1.2 except for requirement

4. 8.1.1. 2. a. 5.

FARLEY-UNIT 1 3/4 8 7 w

_y

.,,--.y

-,,--~,,y

, er.

..m,-

-a--,

4' i

l a

1 a

a i

e Unit 2 Technical Specifications

(

i i

i h'

9 t

u.

e' 3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.-1. As a minimum, the following A.C. electrical power sources shall be UPERABLE:

a.

Two physically independent circuits between the offsite transmission -

network to the switchyard and two physically independent circuits-from the switchyard to the onsite Class IE distribution system, and b.

Two separate and independent diesel generator sets (Set A: DG 1-2A and DG-1C, Set B: DG-2B and DG-2C) each with:

1.

Separate day tanks containing a minimum volume of 900 gallons of fuel for the 4075 kw diesel generators and 700 gallons of fuel for the 2850 kw diesel generator.

2.

A separate fuel transfer pump for each diesel.

c.

A fuel storage system consisting of four, independent storage tanks each containing a minimum of 25,000 gallons of fuel.*

APPLICABILITY: MODES 1, 2, 3 and 4.

ACTION:

a.

With an offsite circuit inoperable, demonstrate the OPCPABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.e within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter; restore at least two offsite circuits to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

l The provisions of Specification 3.0.4 are not applicable.

l b.

With one diesel generator set inoperable, demonstrate the operability of the offsite A.C. sources and the other diesel set ** by performinq Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.e within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and at least once per 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> thereafter. Restore both diesel generator sets to OPERABLE status within 18# days or be in at least i

HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. The provisions of Specification 3.0.4 are not applicable.

One operable fuel storage tank must be available for t a required diesel generator.

  1. The time for restoring the diesel set to OPERABLE status may be extended if requalification of a diesel is required as indicated in Table 4.8-1.

.For the purpose of diesel operability detennination, the diesel set is defined as the parallel diesel in the opposite train.

FARLEY UNIT 2 3/4 8-1

h

. a' ACTION'(continued)

~

c. -With one offsite circuit and one diese1' generator set of the abovel required A.C. ' electrical power sources inoperable, demonstrate the OPERABLILITY ;f the remaining.offsite A.C. source and diesel set by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.e lwithin two hours; restore at least one of the-inoperable sources-to-0PERABLE-status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in ~at least HOT STANDBY within -

the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in' COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />..

4 Restre the other AC power source-(offsite cirucit or diesel generator set) to OPERABLE status in accordance with-the provisions of..Section 3.8.1.1 Action Statements a or b,- as-appropriate.

d.. With two of the above required.offsite A.C. circuits inoperable, demonstrate the OPERABILITY of both dibsel generator sets by.

perfonning. Surveillance Requirement 4.8.1.1.2.e within two hours;

].

~

unless the diesel generators are already operating; restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in et least HOT STANDBY within the next-6 hours. With only one offsite source restored, restore both offsite circuits to OPERABLE status within 7 days' from time.of initial j

loss or be in at least HOT STANDBY'within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

e.

With both of the above required diesel generator sets inoperable, demonstrate the OPERABILITY of two offsite A.C. circuits.by performing Surveillance Requirement ~4.8.1.1.1.a within twa hours; I

restore at least one of the inoperable diesel generator sets to OPERABLE status withir 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY '

within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Restore both diesel generator sets to OPERABLE status within 18# days from time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.8.1.1.1 Each of the above required independent circuits between the offsite transmission network and the onsite Class IE distribution system shall be:

a.

Determined OPERABLE at least once per 7 days by verifying correct breaker alignments, indicated power availability,-and b.

Demonstrated OPERABLE at least once per 18 months during snutdown by transferring unit power supply from the normal circuit to the alternate circuit.

  1. The time for restoring both diesel sets to OPERABLE status may be extended if requalification of a diesel is required as indicated in Table 4.8-1.

FARLEY UNIT 2 3/4 8-2

ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued)

.4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:

a.

In accordance with the frequency specified in Table 4.8-1 on a STAGGERED TEST BASIS by:

1.

Verifying the fuel level in the day tank, 2.

Verifying the fuel level in the fuel storage tanks, 3.

Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the day tank, 4.

Verifying the diesel starts and accelerates to at least 900 rpm, for the 2850 kw generator and 514 rpm for the 4075 kw gener tors, in less than or equal to 12 seconds.

l The generator

-1tage and frequency shall be 1 3952 volts and 1 cz within 12 seconds after the start l

signal.

5.

Verifying the generator is synchronized, loaded to 2700-2850 kw for the 2850 kw generator and 3875-4075 kw for the 4075 kw generator and operates for greater than or equal to 60 minutes.

6.

Verifying the diesel generator is aligned to provide standby power to the associated emergency busses.

b.

At least once per 92 ' days by verifying that a sample of diesel fuel from the fuel storage tank obtained in accordance with ASTM-D270-65, is within the acceptable limits specified in Table 1 of ASTM D975-74 when checked for viscosity, water and sediment.

c.

At least once per 18 months by:

1.

Subjecting the diesel to an inspection in accordance with l

procedures prepared in conjunction with its manufacturer's recocinendations for this class of standby service, l

2.

Verifying the capability to reject a load of greater than or equal to the largest single load associated with that diesel generator, while maintaining voltage between 3120 and 4910 volts and speed less than or equal to 75% of the difference between nominal speed and the overspeed trip setpoint and verifying recovery to 4160 i 420 volts and 6011.2 Hz within 2 seconds.

I 3.

Verifying that on an Safety Injection test signal (without loss of offsite power) the diesel generator starts on the auto-start signal and operates on standby for L.reater than or equal to 5 minutes. The canerator voltage and frequency shall be 2. 3952 volts and 1 57 Hz within 12 seconds after the auto-start signal; l

the steady state geaerator voltage and frequency shall be main-tained between 4160 420 volts and 60 i 1.2 Hz during this test.

FARLEY UNIT 2 3/48-3 t

l

o' ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) 4.

Simulating a loss of offsite power in conjunction with a Safety Injection test signal, and a) Verifying de-energization of the emergency busses and load shedding from the emergency busses.

b) Verifying the diesel starts on.the auto-start signal, I

energizes-the emergency busses with permanently connected loads within 12 seconds, energizes the auto-1-

connected emergency (accident) loads through the load sequencer and operates for greater than or equal-to 5 minutes while its generator is loaded with-the emergency loads. After energization, the steady state voltage and frequency of the emergency busses shall be maintained at 4160 i 420 volts and 60 i 1.2 Hz during-

-this test.

c) Verifying that all automatic diesel generator trips, except engine overspeed and generator differential and low lube oil pressure, are automatically bypassed upon loss of voltage on the emergency bus and/or a safety injection test' signal.

5.

Verifying the diesel generator operates for at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The diesel generator shall be loaded to 3875-4075 kw for the 4075 kw diesels and 2700-2850 kw for the 2850 kw diesels.

6.

Verifying that the auto-connected loads to each diesel generator do not exceed the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 4353 kw l

for the 4075 kw generator and 3100 kw for the 2850 kw generator.

7.

Verifying the diesel generator's capability to:

a) Synchronize with the offsite power source while the generator is loaded with its emergency loads upon a simulated restoration of offsite power, b) Transfer its loads to the offsite power source, and c) Be restored to its standby status.

8.

Verifying that with the diesel generators operating in a test mode (connected to its bus), a simulated safety injection signal overrides the test mode by returning the diesel generator to standby operation.

9.

Verifying that the automatic load sequence timer is l

OPERABLE with each load sequence time within 10% of its required value or 0.5 seconds whichever is greater.

FARLEY UNIT 2 3/4 8-4

'O' ELECTRICAL POWER SYSTEMS 0,

SURVEILLANCE REQUIREMENTS (Continued)

10. Verifying that the following diesel generator lockout features prevent diesel generator starting only when the diesel is in l_

3 the test mode:

a) 011 Temperature High (OTH) b) Cooiant Temperature High (CTH) c) Coolant Pressure Low (CPL) d) Crankcase Pressure High (CCPH) d.

At least once per 10 years or after any modifications which could affect diesel generator interdependence by starting tile diesel gener ators simultaneously, and verifying that the diesel generators accelerate to at least 900 rpm, for the 2850 kw generator and 514 rpm for the 4075 kw generator, in less than or equal to 12 seconds.

l The diesel generator shall be determined OPERABLE by verifying that e.

the diesel is not out of service nor in an Initial Requalification Program, as defined in Table 4.8-1.

4.8.1.1.3 Reports - All diesel generator failures, valid or non-valid, shall be reported to the Commission pursuant to Specification 6.9.1.

Reports of diesel generator failures shall include the information reconinended in Regulatory Position C.3.b of Regulatory Guide 1.108,- Revision 1, August, 1977.

If the number of failures in the last 100 valid tests (on a per diesel basis) l is greater than or equal to 7, the report shall be suppi :nented to include the additional information recommended in Regulatory Position C.3.b of Regulatory Guide 1.108, Revision 1, August, 1977.

FARLEY UNIT 2 3/4 8-5

.~

'o?'

f,,.

TABLE 4.8-1 DIESEL GENERATOR TEST SCHEDULE.(PER DIESEL)

NORMAL TEST-FREQUENCY NUMBER OF SUCCESSFUL TEST

  • TEST FREQUENCY

> 19'of last 20 tests and > 95

. at. least once per 14 days ;

of last 100 tests of last 100 tests at least once.per 7 days 18 of last 20 tests and > 95-16 or 17 of last 20 tests or between 90 and 94 of last T00 tests at least once per 7 days and implement diesel generator Reliability Improvement Program #

unless requalification just completed REQUALIFICATION TEST FREQUENCY

. > 15 of last 20 tests or > 89 of perform diesel generator last 100 tests requalification**

\\

l l

  • Criteria for determining valid test and failures shall be in accordance l

with Regulatory Position C.2.e of Regulatory Guide 1.108.

l

    • Requalification of the diesel generator shall consist of repair, manu-facturer's recommended run-in and successful completion of 7 consecutive l

tests (Initial Requalification) within 45 days from time of inoperability and an additional 7 consecutive successful tests on a once a week test frequency. Subsequent to 14 consecutive successful tests', the test frequency for that diesel shall be determined by Table 4.8-1.

Section 4.8.1.1.2.a.4 defines a successful test.

-# Report a description of the Reliability Improvement Program which includes recommendations of NUREG/CR-0660 and its implementation to the comission.

I FARLEY UNIT 2 3/4 8-6

o.

ELECTRICAL POWER SYSTEMS

~

-SHUTDOWN LIMITING CONDITION FOR OPERATION i

3.8.1.2' As a minimum, the following A.C. ~ electrical power sources shall be OPERABLE f

a.

One circuit from the offsite transmission network to the switchyard and from the switchyard to the onsite Class 1E distribution system, and b.

Diesel Generator 1-2A or 1C or diesel' generator-2 B 'each with:

1. ' A day tank containing a minimum volume of 900 gallons of fuel for the 4075 kw diesel generator and 700 gallons of fuel for the 2850 kw diesel 9enerator.
2. JL fuel storage tank containing a minimum volume of 25,000 gallons of fuel, and.

3.

A fuel transfer pump.-

APPLICABILITY: MODES 5 and 6.

-ACTION:

With less than the above minimum required A.C. electrical power sources OPERABLE, suspend all operations involving CORE ALTERATIONS or positive l

reactivity changes until the minimum required A.C. electrical power sources are restored to OPERABLE status.

SURVEILLANCE REQUIREMENTS 4.8.1.2 The above required A.C. electrical power sources shall be demonstrated OPERABLE by the performance of each of the Surveillance Requirements of 4.8.1.1.1 'and 4.8.1.1.2 except for requirement 4.8.1.1.2.a.5.

l l

i l

FARLEY-UNIT 2 3/4 8 7

~

-