ML20031B937

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-289/81-19 on 810701-0831.No Noncompliance Noted.Major Areas Inspected:Plant Operations During long-term Shutdown,Logs & Records,Safety Limits & LERs
ML20031B937
Person / Time
Site: Crane 
Issue date: 09/11/1981
From: Fasano A, Haverkamp D, Troskoski W, Young F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20031B931 List:
References
50-289-81-19, NUDOCS 8110060250
Download: ML20031B937 (15)


See also: IR 05000289/1981019

Text

1

.

.

U.S. NUCLEAR REGULATORY COMMISSION

50289-810507

0FFICE OF INSPECTION AND ENFORCEMENT

50289-810702

Region I

Report No.

50-289/81-19

Docket No.

50-289

l

1

License No.

DPR-50

Priority

--

Category _

c

Licensee : Metropolitan Edison Company

P.O. Box 480

Middletown, Pennsylvania 17057

Facility N.xie: Three Mile Island Nu.. ear Station, Unit i

Inspection at: Middletown, Pennsylvania

Inspection conduc ed: July 1,1981 - August 31, 1981

M/w

4////8/

Inspectors -

,-

averkamp, Senior pident Inspector (TMI-1)

date signed

~

D.

l

4 ///E-y

+-

W. Troskoski, Reactor IdlIspector

date signed

0)//f?!

n

s---

M F. Young, Rerident Inspe Mor (TMI-1)

date signed

Approved by:

b

9

18 EI

A. Fasano, Thief, Three Mile Island Resident

dat signed

Section, PB#2

Inspection Summary:

Inspection on July 1,1931 - August 31,1981 (Report Number 50-283/81-19)

'

Areas Inspected:

Routine safety inspection by resident and regional based

inspectors (216 hours0.0025 days <br />0.06 hours <br />3.571429e-4 weeks <br />8.2188e-5 months <br />) of plant operations during long term shutdown including

,

l

facility tours and log and record reviews; review of safety limits, limiting

safety system settings and limiting conditions for operation; hot functional

l

testing program and procedure review; emergency feedwater system 48-hour pump

l

run; emergency feedwater system functional test; and, in office review of

licensee event reports.

Resul ts : No itens of noncompliance were identified.

l

t

l

8110060250 810914'

DR ADOCK 05000289

PDR

.

.

.

.

.

.

.

Detail s

1.

Person s, Contacted

General Public Utilities Nuclear Group (GPUNG)

M. Beers, Engineer Assistant Senior II, Nuclear Assurance

J. Colitz, Plant Engineering Director TMI-l

R. Harbin, Technical Analyst Senior I TMI-l

<

T. Hawkins, Manager TMI-l Startup and Test, Technical Functions

G. Miller,, Director Startup and Test, Technical Functions

I. Porter, Supervisor Startup and Test TMI-1, Technical Functions

M. Ross, Manager Plant Operatione THI-1

  • C

Stephenson, ?o: lear Licensing Engineer, Technical Functions

  • R. Toole, Operations and Maintenance Director 1MI-1

The inspector also interviewed several other licensee employees

during the inspection.

Th2y included control room operators,

maintenance personnel, ent neering staff personnel and general

i

office personnel .

  • deactes those present at the exit meeting.

2.

Plant Operations During Long Term Shutdown

a.

Plant Logs and Operating Records

The inspector reviewed the following plant procedures to

determine the licensee established requirements in this area

in preparation for a review of selected logs and records.

Administrative Procedure (AP) 1002, " Rules for the

--

Protection of Employees Working on Electrical and

Mechanical Apparatus," Revision 22

AP 1007, " Control o f Records," Revision 4

--

--

AP 1010, " Technical Specification Surveillance Program,"

Revision 18

AP 1012, " Shift Relief and Log Entries," Revision 14

--

--

AP 1013, " Bypass of Safety functions ano Jumper Control ,"

Revision 8

(

AP 1016, " Operating Surveillance Program," Revision 13

--

i

,

--

AP 1033, " Operating Memcs and Standing Orders," Revision 2

--

AP 1037, " Control of Caution and DN0 Tags," Revision 2

AP 1044, " Event Review and Reporting Requirements,"

--

Revision 2

i

, .

- -- -

- - --

-

-

-

--

.

-

'

.

.

.

-3-

The inspector reviewed the following plant logs and operating

records.

Shift Foreman Log and Control Room Log Book

--

Primgy Auxiliary Operator's Log-Tour Readings, Secondary

--

Auxiliary Operator's Log Sheets, and Auxiliary Operator

Log Sheets - Out-Building Tour

Unit 1 Operations Memo Book

--

Shift Turnover Checklist

--

i

Temporary Change Notic ' ~ CN) Log Book

--

Active Tagging Application Book

--

--

Locked Valve Log

'

ISI Tag Book

--

Night Ordtr Book

--

Do Not Operate and Cautton Tag Log

--

,

b.

Facility Tours

During the course of the inspection, the inspector conducted

multiple tours of the following plcnt areas.

Cor. trol Room (daily, including July 3, July 4, August 29*,

--

and August 30*)

Auxiliary Building (July 1, July 21, August 6, August 25,

--

August 29*, and August 30*)

--

Reactor Building (July 2, July 3, August b, and Augus; 31)

Fuel Handling Building (July 3, August 4, August 26,

--

August 29*, and August 30*)

Intermediate Building (July 2, July 3, July 24, August 27,

--

August 29*, and August 30*)

.

Pump House (July 24, August 25, and August 31)

--

Vital Switchgear Rooms (July 22, August 6, and August 24)

--

Diesel Generator Building (July 2, July 23, August 7,

--

August 27, and August 29*)

.-._._ _

.

._ ,_

. ..

.

.

_ _ _

_

_

. . , _ _ _ ._

-

-

_

t

.

.

.

.

-4-

Yard Area (July 1, July 28, August 7, and Acqust 27)

--

Site Perin:eter (July 1, July 28, August 7, and August ?7)

--

  • Tours conducted on 3-11 PM weekend shift to provide Oackshift

assessment of Hot Functional Testing program.

Plant logs and operating records were reviewed to verify the

following items.

Log keeping practices and log book reviews are conducted

--

in accordance with established administrative controls

Log entries involving abnormal conditions provide sufficient

--

detail to communicate equipment status, lockout status,

correction and restoration

--

Operating orders do not conflict with Technical Specification

(TS) requirements

Jumper log and tagging log entries do not conflict with

--

TS requirements

--

Problem identification reports confirm compliance with TS

reporting and LC0 requirements

--

Jumper / lifted lead / mechanical modification and tagging

'

operations are conducted in conformance with established

administrative controls

The following observations / discussions / determinations were

made.

Control room annunciators: Selected lighted annunciators

--

were discussed with control room operators to verify that

the reasons for them were understood and corrective

action, if required, was being taken.

Control room manning: By frequent observation through

--

the inspection, the inspector verified the control room

manning requirements of 10 CFR 50.54(k) and the Technical

Specifications were being met.

In addition, the inspector

observed shift turnovers to verify that centinuity of

system status was maintained.

The inspector periodically

questioned shift personnel relative to their awareness of

plant conditions and knowledge of emergency procedures.

Fire protection: The inspector verified that selected

--

fire extinguishers were accessible and inspected on

schedule, that fire alarm stations were unobstructed, and

that adequate control over ignition sources and fire

hazards was maintainzd.

[

.

.-5-

.

.

'

--

Technical Specifications : Through log review and direct

observation during tours, the inspector verified compliance

with selected Technical Specification . Limiting Conditions

during shutdown plant operation.

l

--

Plant housekeeping conaitions: Observations relative to

plant housekeeping identified no unsatisfactory conditions.

--

Monitoring instrumentation: The inspector verified that

selected instruments were functional and demonstrated

parameters within Technical Specification limits.

Valve positions: The inspector verified that selected

--

valves were in the position or condition required by

Technical Specifications for the applicable plant mode.

This verification included control board indication and

field observation of valve position.

--

Radiation controls: The inspector verified by observation

that control point procedures and posting requirements

were being followed.

The inspeMr identified no failures

to properly post radiation and i 'gh radiation areas.

4

Fluid leaks: No fluid ' iks were observed which had not

--

been identified by station personnel and for which corrective

action had not been initiated, as necessary.

--

Piping snubbers / restraints: Selected pipe hangers and

seismic restraints were observed and no adverse conditions

were noted.

Equipment tagging: The inspector selected plant components

--

for which valid tagging requests were in effect and

verified that the tags were in place and the equipment in

the condition Specified.

Securi ty:

During the course of these inspections,

--

observations relative to protected and vital area security

requirements were made, including access controls, boundary

integrity, search, escort, and badging.

No notable

conditions were identified.

Licensee meetings: The inspector frequently attended the

--

Plan-of-the-Day (P00) meetings, held by the licensee

management and supervisory personnel .

The inspector

observed the neeting to assess licensee evaluation of

plant conditions, status and problems and to review the

licensee's plaas for conducting certain major plant

operations and nuintenance activities.

The inspector

also attended Construction Status Meetings and Engineering

Status Meetings to assess licensee progress and difficulties

i

related to plant modifications required for restart and

Hot Functional Testing.

. - -

.

.

.

-6-

Acceptance criteria for the above items included inspector

4

judgement and requirements of 10 CFR 50.54(k), Regulatory

Guide 1.114, Technical Specifications, and the following

procedures.

AP 1002, " Rules for the Protection of Employees Working

--

on Electrical and Mechanical Apparatus," Revision 22

--

AP 1008, " Good Housekeeping," Revision 7

AP 1037, " Control of Caution and DN0 Tags," Revision 2

--

No items of noncompliance were identified.

3.

Review of Safety Limits, Limiting Safety System Settings and

Limiting Conditions for Operations

The inspector reviewed documentation listed below to ascertain

whether the licensee is complying with Technical Specification

requirements.

--

Operating Procedure (0P) 1101-1, " Plant Limits and Precautions,"

Revision 12

OP 1101-2, " Plant Setpoints," Revision 17

--

--

OP 1102-1, " Plant Heatup to 525 Degrees F," Revision 46

--

OP 1102-16, "RCS Natural Circulation Cooling," Revision 6

OP 1103-4, " Soluble Poison Concentration Control," Revision 17

--

OP 1101-3, " Containment Integrity and Access Limit," Revision 2

--

OP 1103-2, " Filling and Venting the Reactor Coolant System,"

--

Revision 29

OP 1103-5, " Pressurizer Operation," Revision 19

--

OP 1103-6, " Reactor Coolant Pump Operation," Revision 21

--

OP 1104-1, " Core Flood System," Revision 10

--

OP 1104-4, " Decay Heat Removal System," Revision 31

--

Surveillance Procedure (SP) 1301 ' , " Shift and Daily Checks,"

--

Revision 34

SP 1301-9.9, " Hydraulic Shock and Sway Suppressors," Revision 13

--

-

SP 1303-4.11

"High Pressure Injection and Low Pressure

--

Injection Logic and Analog Check," R2 vision 18

-

- -

- -

- -

'

x

,

.

.

.

-7-

SP 1303-12.8A, " Fire Protection Instrumer.tation Functional

--

Test Control Building Elevation 355 ft," Revision 2

--

SP 1305-12.9, " Fire Barrier Seal Inspection," Revision 0

--

SP 3301-R1, " Fire Service Diesel Engine Inspection," Revision 1

Acceptance criteria for the above items included selected requirements

of facility operating procedures and the following Technical Specifications

(listed according to their respective systems).

Reactor Coolant System Technical Specifications 2. 2, 3.1.1.1,

--

3.1.1.3, and 3.1.12

1

Instrumentation Technical Specification 3.5.1, Table 3.5-1

--

.

--

Emergency Core Cooling Systems Technical Specification 3.5.3.1

Containment Integrity Technical Specification 3.6.1

--

Fire Protection Technical Specification 3.18

--

The items observed and reviewed by the inspector were acceptable,

unless otherwise noted below.

>

SP 1303-12.8A, " Fire Protection Instrumentation Functional

--

Test," data sheet referenced an incorrect Technical Speci-

fication 4.17.l A on the cover sheet as compared to the

orocedure which referenced the appropriate Technical

f peci fication 4.18.1 A.

SF 3301-R-1, " Fire Service Diesel Engine Inspection," surveillance

i

--

exception and deficiency list was rissing the shift supervisor's

initials and date.

--

SP 1303-12.9, " Fire Barrier Seal Inspection," section 4.3.11

and 4.3.14 were missing several required initials.

(Note:

The shift supervisor corrected the problem when brought to his

attention.)

'

OP 1103-6, " Reactor Coolant Pump Operation," procedure did not

'

--

require starting of associated lift pumps when starting

<

additional reactor coolant pumps.

These items were discussed with the Operations and Maintenance

Director TMI-1, who stated that appropriate measures would be

taken to correct the administrative or procedural discrep-

ancies.

The inspector considered that these items were

isolated examples of inadequate attention to detai1 regarding

procedure development and implementation. The inspector had

,

no further questions concerning this matter.

,

- - - - .

- -

. - - - - - . . - - .

. -

.

. .

. - - - - - - - - - -

.

- .

. - -

.

- - -

. - -

- - .

- . -

.

.

.

-8-

4.

Hot Functional Testing (HFT) Program and Procedure Review

a.

Program Review

The inspector reviewed the following procedures related to the

HFT program to determine overall program adequacy and to

verify that the procedures were reviewed and approved in

accordance with administrative controls.

--

Prerequisite List for HFT, Revision 0, dated May 18, 1981

Test Procedure (TP) 600/1, Controlling Procedure for HFT,

--

Revision 0, dated August 17, 1981

OP 1102-1, Plant Heatup, Revision 46 as revised for HFT,

--

dated July 10,196

OP 1102-11, Plant Cooldown, Revision 31, dated June H,1981

--

The prerequisite list for HFT prWdes the pretest requirements

for systems necessary to support nat functional testing.

The

prerequisite list is in the fonn of a signoff sheet whereby

each system and associated equipment tests (generic and functional)

are verified complete by the Startup and Test Group.

In

addition, the operability status of each system is verified by

the Startup and Test Group and the Operations Department.

(The Startup and Test Group verifies the acceptability of

design modification work necessary to support testing. The

Operations Department performs the approved operating procedures

to align apalicable plant systems for the appropriate plant

condition.'

The prerequisite list also tracks outstanding

items and exceptions that pertain to the design modifications.

The prerequisite list tracks all operating procedures, required

for milestone events and surveillance procedures needed for

heatup, and items that possibly affect the procedures.

TP 600/1 is the controlling accument that references and

sequences all operating and HFT procedures.

The procedure

controls plant mode changes from formation of the steam bubble

in the pressurizer through plant heatup to 532F and 2155 psig

and-subsequently through the plant cooldown phase to the

initial depressurized state.

The controlling test procedure

(TP 600/1) also includes a sequential logic schedule that

4

defines the tests to be performed at specified temperature and

pressure plateaus. Actual plant heatup ard cooldown operations

are performed using approved operating proceduras (OP 1102-1

and OP 1102-11) that were modified for HFT conditions.

The inspector considered that the above procedures associated

with control, coordination and conduct of the HFT program were

adequate to assure the safe and accurate performance of the

H FT' s .

'

.

.

.

.

.

.

.

. .

.

.

.

.

-9-

b.

HFT Procedure ."sview (General)

Each TP that is scheduled and controlled by TP 600/1 contains

test specific prerequisites and acceptance criteria.

Prior to

HFT each TP is reviewed and approved by the licensee.

The inspector reviewed the sequential logic schedule to determine

what testing was planned and to verify that applicable procedures

were written and approved.

The inspector planned to review

approved copies of all the referenced TP's about one week or

.less prior tc the scheduled test performance dates. Al though

several approved TP's were provided when requested for NRC

review, other TP's were available only in draft form and a fw

TP's were not yet written.

The inspector discussed this

matter with licensee representatives from the Startup and Test

Group, who were responsible for preparing the TP's.

The

licensee's representative stated that some of the originally

listed tests would not be performed during the preliminary HFT

due to tFe d' /ficulty in obtaining the necessary procedures,

and that % remaining TP's were expected to be approved

shortly

'r to performance of the tests.

The inspector

state.

6 sufficient time had not been provided for the

desired NRC review of the TP's prior to scheduled testing.

Although .uch pre-testing NRC review of the TP's was not

required, any procedural or test inadequacies identified

during subsequent NRC review of the test results would have to

be satisfactorily resolved before the test is accepted.

The

licensee acknowledged the inspector's comments.

The inspector's

findings on final approved and draft TP's, including descriptions

of the test objectives and acceptance criteria, are discussed

in the paragraphs below.

c.

Review of Individual HFT Procedures

TP 651/1, " Intermediate Closed Coeling System Flow Test,"

Revision 0, approved August 4,1981

The Intermediate Cooling System is started in accordance

with OP 1104-8, Revision 11, approved February 20, 1981.

After t se system is in operation, TP 651/1 is conducted

to veri fy system performance.

The following items were

verified or performed by TP 651/1.

.

Low Intermediate Closed Cooling Water (ICCW) flow

--

I

interlock to Control Rod Drive Breakers

l

Ability to satisfactorily cool plant equipment at

--

250F, 400F, and 532F temperature plateaus

Adequate cooling to Reactor Coolant Letdown Coolers

--

l

during normal and maximum letdown, and to Control

l

Rod Drive Stators during hot shutdown conditions

i

!

-..- - - _ - _ _ _ _ _ - _ _ _ _ _ _ _ - _ - _ _ - _ _ _ _ _ _ _ _ - _ - - _ _ _ - _ _ - _ _ _ _ - _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ - - _ _ - - - - _ _ _ _ _ . _ - . - _ - . _ _ = _ _ - - _ _ _ _ _ _ _ - _ - _ - - _ _ _ - - _ _ _ - - _ ,

.

.

.

.

-10-

ICCW heat load and flow rate calcula;;ons while in

--

het shutdown

The inspector reviewed TP 651/1 to verify that the test

was reviewed and approved per applicable administrative

prot.edures, that test objectives were clearly stated and

addressed in the body of the test, that acceptance

criteria wa; defined, and that appropriate Quality

Control (QC) holdpoints were identified.

Findings were

acceptable.

TP 654/1, " Main Steam Safeties Acoustic Monitor-Functional

Test" (Draft)

TP 654/1 provides instructions to verify the proper

operation of the acoustic monitors installed by the ltain

Steam Safety valves.

The test procedure contains details

that (nables verification that both the computer and

indicator lights on the audio monitoring cabinet correctly

identify which group of safety valves has lifted. Baseline .

data will also be obtained for noise levels in each

chamber.

The actual lift of the safety valves will be

performed in accordance with SP 1303-11.3, " Main Steam

Safety Valves," Revision 6.

The inspector reviewed the draft copy of TP 654/1 to

compare the assigned test objectives with the acceptance

criteria.

Findings were acceptable, pending the review

and final approval of the TP by the licensee.

TP 655/1, "High Pressure Injection System Functional

Test" (Draft)

The inspector reviewed the draft copy of TP 655/1 and

compared the proposed test objectives and acceptance

criteria to the following technical reports.

System Design Description for High Pressure Injection

--

Cross Connect, System Design Document (SDD) 211 A,

Revision 2

--

TMI-l Restart Report, Section 8.3.15, Small Break

LOCA

TMI'l Restart Report, Supplement 1, Part 3, ResNnse

--

to Questions 1, 2, and 3, Amendment 25

Constricting venturies were added to the high pressure

injection (HPI) discharge lines to prevent inadverteni.

pump runout and cavitation of the pump without the w.J

to throttling the individual discharge valves (MU-V16A/B/C/D).

l

.

_.

_

_

.

.

.

_

_

- _ _ -

_ _ _ _ _ _ _ _ _

.

.-11-

.

.

l

l

TP 655/1 provides instructions to test the HPI system

l

with installed cross connects for the minimum flow split

of 70%/30% for all ca:5inations of three HPI. legs in both

the cavitating regime (Reactor Coolant System (RCS)

pressure less than 600 psig) and the non-cavitating

regime (RCS pressure approximately 1200 psig).

The test

i

hiso verifies total flow for all four legs under both of

the previous pressure conditions.

The reviewed acceptance

criteria in the procedure reflects the values reported in

SDD-211 A and Response to Questions 1, 2, and 3 of the

Restart Report, Supplement 1. Part 3.

The test additionally

verifies the flow rate through the bypass valve, MU-V217,

which was installed to limit thermal shock to the "D" HPI

nozzle.

Findings were acceptable, pending a final review

and approval by the licensee.

TP 674/1, " Reactor Coolant Pump Operation and Flow Test,"

Revision 0, approved August 4,1981

The test provides instructions to obtain baseline operating

data for each reactor coolant pump (RCP) during initial

pump startup and at various temperature plateaus up to

and including hot shutdown conditions.

The RCP's are

started and operated in accordance with OP 1103-6,

" Reactor Coolant Pump Operation," Revision 21.

The inspector reviewed TP 674/1 for administrative review

and approval, test objectives, prerequisite conditions,

and acceptance criteria.

Findings were acceptable.

TP 677/1, "RCS Post-Accident Sampling Functional Test"

( Draft)

TP 677/1 was written to allow for documenting the time

required for three technicians to perform specific actions

in order to obtain an RCS sample during postulated post-

acciaont conditions.

Each action is to be timed and

witnessed by a QC inspector.

The estimated exposure is

then calculated and compared to a 5 rem upper limit.

The

assumed post-accident dose :<te used fc" the test is

199 rem /hr.

This exposure eate value p.aoduces a conservative

result when compared to the 180 rem /hr dose rate listed

in TMI-1 Restart Report, Se: tion 2.1.2.4.1, Amendment 25

findings were acceptable, pending final review and

approval of this TP by the licensee.

5.

Emergency Feedwater System - 48-Hour Pump Run

i

a.

References

TP 233/2, " Emergency Feeuwater Pumps 4b-Hour Run,"

--

Revision 0, approved July 20, 1981

>

1

~-

..

.

.

..

o

.

-12-

--

SP 1300-3F, " Motor-driven Emergency Feedwater Pump

Functional Test," Rev:sion 6

SP 1300-3G A/B, " Turbine-driven Emergency Feedwater Pump

--

Functional Test and Valve Operability Test," Revision 6

TMI-l Restart Report, Supplement 1, ~ Part 2, Question 7,

--

Amendment 25

b.

Test Scope

A 48-hour endurance test was conducted in accordance with

TP 233/2 on the turbine-driven emergency feedwater (EFW) pump

and both motor-driven ErW pumps.

Parameters measured during

the test included pump f'ow . pump suction, and discharge

pressure, bearing temperatures, EFW temperature, turbine /

motcr/ pump vibrations, motor tempe.ature and current, ard pump

room temperature and humidity.

After completion of the 48-ho.r

test run, the pumos were allowed to remain idle for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />,

until the bearing temperatures ceoled to within 20F of the

value at the start of the test.

The pumps.were then restarted

and run for an additional I hoar before being secured and

returned to standby service.

>

c.

Inspection Scope _ and Findings

The inspector reviewed -TP 233/2 for proper review and approval

by the licensee.

The acceptance criteria specified for the

measured operating parameters in section 11.0 of the test were

compared to those in the normal plant surveillance procedures,

SP 1300-3F and SP 1300-3G A/B.

No discrepancies were observed.

The inspector witnessed endurance tests conducted for all

tnree EFW pumps to ve rify that test procedures and :dministrative

controls were be;ag adhered to by test personnal .

Data measuring,

recording, and review were also verified on a sampling basis.

Discussions were held with the startup test engineer on several

occasions during the test to ascertain that jurisdictional

controls were being exercised.

No items of noncompliance were

identified during the conduct of toe endurance test.

Data taken and plotted for trend analysis were reviewed by the

inspector and compared to the test acceptance criteria.

Pending the final review and approval of the test results by

the licensee to comply with restart commitments for the EfW

endurance test, the inspector had no further questions on this

matter.

!

>

-

- - - .

-

.

~

.

.

. .

.

.

-13-

6.

Onergency Feedwater System - Functional Test

a,

.Re ferences

TP 233/1, " Emergency Feedwater System Functional Test,"

--

Revision 0, dated July 23, 1981

Design Modification Task RM-13E

--

TMI-l Restart Report, Section 2.1.1.7, Anendment 25

--

b.

Test Scope

TP 233/1 was prepared to test the following design features /

modifications described in the TMI-l Restart Report.

Automatic start logic of all three EFW pumps on simulated

--

loss of both main feeduster pumps or trip of all four

RCP's

.

Ability of manual loader stations to control EFW valves

--

EF-V30 A and B

Valves EF-V30 A and B fail open on loss of instrument a.ir

--

Control room annunciation of all automatic start conditions

--

(

of EFW systems

Instrumentation and indicators for EFW flow to the Once

--

Through Steam Generators (OTSG)

i

c.

Inspection Scope and Findings

TP 233/1 was reviewed by the inspector to verify that it was

reviewed and approved by the licensee in accordance with

administrative controls, that test objectives were clearly

stated, acceptance criteria were consistant with the test

'

objectives, and that appropriate prerequisities were defined.

The inspector held discussions with the cognizant test engineer

on the technical content of the test.

Items discussed by the

inspector included (1) test or automatic loading to the diesel

generators for the motor driven pumps, (2) calibration and

setpoints of engineering safeguard (ES) contacts, and (3) power

,

supply source of the OTSG flow instrume.: Lation.

The licensee's

representative stated that the dietel load test (to be conducted

at a later date) incorporated a verification of the motor-

driven' pumps automatically loading on to the diesel generator

in less than 30 seconds.

The ES contacts in question were

scheduled to be checked under design modification Task PM-5C,

.

!

4

4

t

.

.

>

.

.

..

-14-

which was being conducted at this time by another startup

engineer. A review of the applicable drawings indicated that

the OTSG instrumentdion power was supplied by the 120V vital

busses GBC and GBB.

The inspector had no further questions

about the content of the test procedure at this time.

The inspector reviewed the approved field copy of TP 233/1 to

determine test progress and procedure adherence.

The licensee

nad successfully completed those sections of the test per-

taining to the EFW pump automatic start, contro! of valves

EF-V30 A and B, valves EF-V30 A and B tail open on loss of

air, and control room annunciation of all EFW automatic start-

conditions.

Due to late arrival of the Controlatron instruments

for EFW flow indication to the OTSG, sections 9.5 and 9.6 of

this test procedure were postponed to a later date.

TP 233/1

remained incomplete and could not be concluded until the above

modifications were finished.

The inspector had no further

questions at this time.

7.

In-Office Review of Licensee Event Reports (LEO.'s)

The inspector reviewed the LER's listed below, which were submitted

to the NRC Region I office, to verify that the details of the event

'

were clearly reported, including the accuracy of the description of

cause and the adequacy of corrective action.

The inspecMr dHermined

whether further information was required from the' licensee, whether

the information involved with the event should be submitted to

Licensing Boards, whether generic implications were indicated, and

whethe. the event warranted onsite followup.

The following LER's were reviewed:

LER 81-006/3L-0, dated June 10,1981 (Fire Service Diesel

--

Engine Surveillance Procedure 3301-R1 was not performed within

the allowable time limit due to data being improperly entered

into the computer data base for scheduling)

--

LER 81-007/99X-0, dated July 8,1981 (Inspections resulting

from IEB 79-14 determined that numerous pipe supports had been

located or oriented improperly when installed)

The above LER's were closed based on satisfactory in-office review.

8.

Exit Interview

Meetings were held periodically with senior facility management

during the course of the inspection to discuss the inspection scope

and findings.

The inspectors met with the licensee representatives

(denoted in paragraph 1) at the conclusion of the inspection on

September 2,1981, and summarized the purpose and scoge of the

inspection and the findings.

The licensee representatives acknow-

ledged the findings.

. _