, p 'nsc,
ua t
UNITED STATES 2L
.j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 g
/
'APR 2 81994 Docket 70-1113 License SNM-1097 Mr. Preston T. Winslow, Manager Emergency Preparedness, Security &
Material Control Accountability GE Nuclear Energy General Electric Company Nuclear Energy Production P.O. Box 780 Wilmington, NC 28402
Dear Mr. Winslow:
SUBJECT:
BUILDING CONSTRUCTION REQUEST This refers to your letter dated April 15, 1994, regarding the proposed construction of a building to be located within the controlled access area at the General Electric (GE) Nuclear Fuel and Components Manufacturing facility in Wilmington, North Carolina. The proposed building will be approximately 50 feet wide by 100 feet long with an adjacent storage pad. The design will be metal construction with insulated roof, walls, and a concrete floor.
The building will include heating, ventilation, air conditioning, sprinkler systems, electrical and water services, rest rooms, and a change room.
Construction will meet or exceed all State and local codes.
Activities in the new building and area will consist of decontamination, refurbishment and storage of reactor fuel examination equipment.
These activities will be licensed by the State of North Carolina under GE's existing agreement state license.
Special nuclear material will'not be used in this building or storage area. Therefore, no changes to GE's NRC Materials License SNM-1097 will be required.
It is our understanding that the construction will require excavation of soil.
Prior to construction, soil survey results must be obtained by GE to determine if the soil is contaminated.
If contaminated soil is discovered, the soil survey results must be submitted for Nuclear Regulatory Commission review and confirmation.
All contaminated soil must be removed prior to construction.
If no contamination is discovered, GE may proceed with the construction.
Results from the soil sampling should be maintained in the decommissioning file required by 10 CFR Part 70.25(g).
NRC FlLE SENTER COPY 9405050186 940428 i
PDR ADOCK 07001113 0
C PDR i
M 2
The staff has determined that construction of this building will not significantly affect the quality of the environment.
Therefore, the staff has no objection to GE constructing this building.
Sincerely, ORGNAL5iGNEDBY CharlesW.Emeigh i
Robert C. Pierson, Chief Licensing Branch Division of Fuel cycle Safety and Safeguards, NMSS DISTRIBUTION:
Docket 70-1113 PDR NRC File Center P.cgion II NMSS r/f FCSS r/f FCLB r/f FCLSI r/f GTroup, RII
[EFlack-A:\\ BUILDING.))
0FC FCLB F
FCLB f)FCLB FCLB,a O FC LB,'
M emn-
-0 g
- ps v NAME EFlack EKeegan~
h,pDAHoadley CEmelgh n3pRPierson I