ML20028F353

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-313/82-29 & 50-368/82-27 on 820907-17.No Noncompliance Noted.Major Areas Inspected:Review of Licensee Actions & Commitments in Response to IE Bulletins, Insp repts,NUREG-0737 Items & NRC Generic Ltrs
ML20028F353
Person / Time
Site: Arkansas Nuclear  
Issue date: 11/24/1982
From: Jaudon J, Johnson E, Johnson W, Lanik G, Showe S, Showe S, Trammell C, Willis C, Young R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE), Office of Nuclear Reactor Regulation
To:
Shared Package
ML20028F352 List:
References
RTR-NUREG-0737, RTR-NUREG-737 50-313-82-29, 50-368-82-27, IEB-79-06B, IEB-79-09, IEB-79-11, IEB-79-13, IEB-79-18, IEB-79-19, IEB-79-23, IEB-79-24, IEB-79-25, IEB-79-28, IEB-79-6B, IEB-79-9, IEB-80-05, IEB-80-10, IEB-80-11, IEB-80-12, IEB-80-15, IEB-80-16, IEB-80-18, IEB-80-20, IEB-80-24, IEB-80-5, IEB-81-01, IEB-81-02, IEB-81-1, IEB-81-2, NUDOCS 8302010258
Download: ML20028F353 (14)


See also: IR 05000313/1982029

Text

_

,

.

,

U. S. NUCLEAR REGULATORY C0t#1ISSION

REGION IV

NRC Inspection Report:

50-313/82-29

50-368/82-27

Dockets:

50-313

Licenses:

DPR-51

50-368

NPF-6

Licensee: Arkansas Power and Light Company

Post Office Box 551

Little Rock, Arkansas

72203

Facility Name:

Arkansas Nuclear One (ANO), Units 1 and 2

Inspection At:

ANO Site, Russellville, Arkansas

Inspection Conducted:

September 7-17, 1982

Team Leader:

E. H. Johnson, Director of Enforcement, Region IV

Date

Team Members:

e, a

M

J/ J,3 N

Jf.P.CJapon, React'orInspector,ReactorProjects

DateI

(Sectiok C

l

%Mw

%ku

%

C. M. Trammell, Project Manager, Nuclear Reactor

Date

Regulation

!

M b=m

lu /h

% C. A. Willis, Leader, Section B, Effluent Treatment

Date

Systems Branch, Nuclear Reactor Regulation

S.N b

"l2 tl61.

D

S. K. Showe, Chief, PWR Technology Branch, NRC

Date

Reactor Training Center

l

8302010258 821202

l

PDR ADOCK 05000313

l-

O

PDR

.

.

2

5 .A. & L

%/t.s

PS'

'

G. F. Lanik, Senior Reactor Systems Engineer, Office

Date

of Inspection and Enforcement

744 6

%/a

U

R. M. Young, Reactor Systems Engineer, Office of

Date

Inspection and Enforcement

M

M

/

4

Approved:

-

W. D.[Johngon, $hief, Reinctor Project Section C

Date

Inspection Summary

Inspection conducted September 7-17. 1982 (Report 50-313/82-29, 50-368/82-27)

Areas Inspected:

Special, announced inspection to review and verify that

licensee actions taken, and commitments made,'in response to NRC

communications were carried out as indicated.

Four categories of NRC

documents, which normally require actions or commitments by licensees', were

covered by this review:

IE Bulletins, NRC Inspection Reports, NUREG-0737

items, and NRR Generic Letters.

NRC communications and corresponding

licensee responses, since April 1979, were included in thir. review. .A total of

112 man-hours was spent by six NRC staff members in reviewing NRC and licensee

correspondence in-office to identify specific commitments. An additional 246

man-hours were spent onsite in verifying that these commitments had been

completed as indicated in licensee correspondence to the NRC.

Results:

No items of noncompliance or deviations were identified to the

licensee as a result of this special review effort.

Certain items of concern

were identified which could result in future enforcement actions.

These items

were discussed with the licensee and are noted in the following paragraphs.

'.

'.

3

DETAILS

1.

Persons Contacted

Arkansas Power and Light Company

B. Baker, Operations Minager

M. Bishop, Office Services Supervisor

W. Cavanaugh III, Senior Vice President - Energy Supply

L. Duggar, Manager, Special Projects

J. Enos, Licensing Supervisor

E. Ewing, Manager, Engineering and Technical Support

J. Griffin, Assistant Vice President, Nuclear Operations

_

D. Hardin, Manager, Quality Assurance

D. Howard, Licensing Supervisor

L. Humphrey, Plant Administration Manager

J. Levine, General Manager, ANO

J. Marshall, Manager of Licensing

D. Moggenberg, Special Projects Coordinator

D. Rueter, Director, Technical and Environmental Services

L. Sanders, Maintenance Manager

L. Schempp, Manager, Nuclear Quality Control

J. Vandergrift, Training Superintendent

The NRC team also contacted other plant personnel including

administrative, clerical, document control, engineering, and operations

personnel.

2.

Re,ason for the Special NRC Review

In March 1980, the NRC issued IE Bulletin 80-06 which required the

licensee to review Engineered Safety Feature (ESF) schematics to

l

determine if the components would return to an unacceptable state upon

i

reset of the ESF signal.

Following this review, the IEB required that-

l

testing be performed to verify that the installed controls were consistent -

l

with the schematics.

In a letter dated June 18, 1980, submitted under oath

in accordance with 10 CFR 50.54(f), the licensee indicated that all required

testing had been accomplished on both units.

During NRC inspection 50-368/82-05, it was determined that the testing on

Liitt ? had not been completed.

l

l

Because of the direct safety significance of this event, the NRC is

consider *ng escalated enforcement action for the misinformation

communicated to the NRC.

In reviewing the facts of the event, and the licensee's past compliance

history, several items wherein commitments were not completed as

'

specified in the licensee's correspondence to the NRC were identified.

-.

.

_

_

._.

.

-- -

.

- _ _

..-

_-

.-

. .

-

.=

i

.

.

.

.

4

I

.

As a result of this, it was decided that an immediate review of licensee

.

!

communications with the NRC should be undertaken to determine whether'

other instances of misleading'information being sent to the NRC had

q

occurred.

This review, to cover the time frame from April 1979 to the

present, was to include the major categories of NRC correspondence with

licensee's that required actions or commitments.

These communications

are:

IE Bulletin responses, NUREG-0737 " Clarification of TMI Action Plan

Requirements" responses, responses to NRR generic letters, and responses

to NRC inspection reports.

.

A review team consisting of persons from Region IV, IE, and NRR was

'

selected to conduct this review.

3.

Review Methodology

During the week of September 7-10, 1982, the review team selected

specific licensee commitments which had been made in response to IE

,

Bulletins, NRC Inspection Reports, NUREG-0737 items, and NRR Generic

'

Letters.

These specific commitments were found by analyzing licensee

correspondence to identify clearly auditable actions that the licensee

had either stated were completed or would be completed at a future date.

The team was divided into three subgroups for the analysis of

commitments.

One subgroup reviewed both IE Bulletin responses and NRC

Inspection responses, while the other subgroups concentrated on

NUREG-0737 item responses and NRR Generic Letter responses, respectively.

During the week of September 13-17, 1982, the team visited the ANO site.

I

While onsite, team members reviewed objective evidence to determine the

status of commitments. This objective evidence included procedures,

letters, internal memoranda, design change packages, completed

surveillances and other tests, drawings, and the sighting of installed

equipment.

Discussions were also held with the Resident Reactor-

Inspectors.

The licensee was informed of the special team site visit on September 9,

1982.

Details of the inspection were not provided until September 13,

1982, when the team was onsite.

The licensee provided members of his

staff to support each subgroup by assisting in gatherin; the large volume

of requested records.

The scope of the review was essentially all items within the selected

area except those on which there had already been extensive followup

(e.g., a special inspection) or for which no member of the team had the

required expertise (e.g., radiographic interpretation).

In the case of

findings for NRC Inspection reports, the licensee's corrective action for

these items receives individual and detciled followup by NRC inspectors;

therefore, in the context of this special review, only recurring problems

were selected.

.

. . . _ .

-

.

.

. . .

.

5

'.

.

5

,

i

Although the review covered a broad sampling.of commitment categories

over a significant period of time, the special-review group did not

attempt to verify the technical adequacy of the licensee's responses or

commitments.

The review focused, ir, stead, on whether these commitments,

had been carried out a;. indicated.

For NUREG-0737 items,.where responses

or commitments were plant specific, ANO-2 was selected as the plant for

review,

m.

A list of all items reviewed is contained in the table. ~ The' following

sections summarize tts review.

.

,

,

4.

Review of NRR Generic Letters

2

"

The scope of this review effort was NRR Generic Letters'sent to AP&L

'

during the period from April 1979 to the present.

A total' of 12 Generic :

Letters containing 22 commitments or required actions was reviewed.

Letters associated with requirements subsequently incorporated into

NUREG-0737 ware not reviewed since these were tia subject of seperate

i

review.

No items of material misinformation or failure to carry out a commitment

as described were discovered during this portion of the review.

One item requiring additional followup by the review team _was discovered,-

and was resolved to the satisfaction of the review team that it did not

I

constitute material misinformation.

In the licensee's letter to D. G. Eisenhut dated October 21, 1982,

,

responding to Generic Letter 81-04, AP&L indicated that station procedures

'

have provisions for the isolation of reactor coolant system letdown and

seal return. The purpose of this procedural _ step would be to-reduce

inventory loss from the reactor coolant system.

Because the seal return

1.ne on ANO-2 contains a relief valve, which would lift if the seal-

return line were isolated, thus allowing continued inventory loss,

the licensee did not put procedural steps in the ANO-2 procedures requiring

isolation of the seal return during a station blackout. 'Instead, an

l

analysis was performed cf the ANO-2 reactor coolant system during a station

[

blackout to assure that pressurizer level, a measure of system inventory,

l

remained at an acceptable level, taking into account the loss through

l

seal leakoff. This analysis demonstrated that pressurizer level would

remain in the operating range throeghout the event.

The special review team had no further questions on this matter.

..

.

,

r'

.

.

6

5.

Review of NUREG-0737 Items

The scope of this review effort was the licensee's responses to

NUREG-0737 items. Where responses were plant specific, the followup and

inspection of objective evidence to determine the correctness of the

response concentrated on ANO-2.

This review included 33 seperate items

with a total of 84 commitments or actions contained in AF&L responses.

No items of material misinformation were discovered.

Three items requiring additional followup to resolve were noted and are

discussed below:

a.

NUREG-0737 II.B.2, Plant Shielding

In partial response to this item, the licensee proposed in a letter

dated March 31, 1980, to have automatic isolation of letdown and

seal return flow in the event of high radiation levels.

In

addition, a warning step was to be included in the decay heat

removal procedures for ANO-1 to ensure that operators were aware of

the potential impact of using these systems, if radiation levels were

high.

In a letter dated October 27, 1980, the licensee stated that

all plant shielding items were complete, except a procedure change to

assure manual isolation of letdown and seal return when radiation

levels were high.

Although not explicitly spelled out in this

letter, the licensee had dropped the idea of'providing automatic

interlocks to isolate seal return and letdown, and would instead

rely on manual isolation.

In a letter dated December 31, 1980, the licensee addressed the

issue of how the procedural steps for isolation of seal: return and

letdown would be accoiaplished.

The letter stated that the only way

that the letdown and seal return lines could become so heavily

contaminated, as to constitute a problem for access around the

t

l

volume control tanks, would be under conditions of inadequate core

cooling.

The letter continued that the appropriate operator response

would be contained in the Inadequate Core Cooling Operator Guidelines

,

which were being prepared for another NUREG-0737 item.

!

In a letter dated November 30, 1981, the licensee furnished the NRC

the reasons for the apparent differences in the letters of March 31

and October 27, 1980. This letter indicated that the idea of

automatic isolation had been abandoned in favor of manual

isolation.

The letter further states that the position relative to

item II.B.2 remains as spelled out in the letter of December 31, 1980.

At the time of the special review, these guidelines were still in

preparation.

The November 30, 1981, letter further states that the other procedural

changes (without being specific) as noted in nrevious letters (without

.

..

-

-

- . .

-

-.

.

_-

_.

- . _

__

_

__ _

.

.

,

1

7

specifying which letters) had been completed.

An NRC Region IV

4

I

. inspection of June 21-25, 1982, had idertified that station

procedures for Unit Two did not contain steps requiring the: isolation

of letdown and seal return under accident conditions involving core

damage. A careful review of the letters dated March 31, 1980,

October 27, 1980, and December 31, 1980, by Region IV personnel

determined that the isolation of letdown and seal return was to be

accounted for in a review of the Inadequate Core Cooling Operator

,

l

Guidelines and that the procedure that was actually deficient was

I

the Unit One decay heat removal procedure which lacked a warning

statement to caution operators if. activity levels were high.

As a

result of this deficiency a Notice of Deviation was issued (NRC

Report 50-313/82-14, 50-368/82-11).

At the time of the special review, it was learned that both Unit One

i

and Two decay heat removal procedures, were revised on September 8,

'

1982, to include the required cautions.

In addition, the emergency

procedure for high activity in the reactor coolant system for both

units was revised on the same day to provide caution notes to

operators concerning the use of decay heat removal.

The NRC special review team had no further questions on this matter,

b.

NUREG-0737 Item II.B.3.-Post-Accident Sampling System (PASS)

I

In a letter dated March 9, 1982, AP&L stated that, notwithstanding

the problems encountered with the boron analysis equipment, it would

not prevent use of the PASS in an emergency.

In a ?etter dated

l

May 7, 1982, AP&L stated that "the ANO . . . PASS is now installed-

and capable of obtaining a sample of primary coolant for ANO-1 and

'

ANO-2."

On May 19, 1982, during an emergency drill, manual block valves

l

located in the lower level of the Auxiliary Building were closed.

.

They were closed because of a solenoid valve failure downstream.

l

Under the specific assumptions of the drill (a highly radioactive

l

water leak into Auxiliary Building), access to the valves to reopen

l

and take a PASS sample would have been very difficult.

These developments led to a letter from Region IV to AP&L dated

June 4, 1982, asking AP&L to review its prior statements regarding

PASS operability.

l.

l

l

l

--

-.

. , - . . . . _ - , . . , ,

. _ , , , . . _ - . . . - _ - . . .

--

- - . . . .

. - - , . . - - .

- , - ,

-. .

.

,

'

'.

.

8

AP&L responded in a letter dated June 18, 1982, indicating that

although some difficulties were being experienced with the on-line

analysis equipment, the system was capable of drawing a sample.

The

letter outlined the status of the PASS system.

Region IV is responding to this letter.

The special review team had no further question on this matter.

c.

NUREG-0737. Item II.F.1.2, Handling Highly Radioactive Samples

In a letter dated November 30, 1981, AP&L stated that the procedures

for removal, transportation, and analysis of sample filters that

could be highly radioactive were being developed and would be

completed by June 1, 1982.

The review team discovered that only low

level samples from normal operations were addressed in procedures

and not the highly radioactive samples, as stipulated.

The review team determined that the necessary procsdures were being

developed when the above letter was written.

Development stopped,

however, when an erroneous calculation (discovered later by the

review team member) indicated that the equipment that had been

purchased could not cope with the radioactive source term that was

specified in NUREG-0737.

AP&L personnel had discussed this matter

with the NRC staff who indicated that the equipment was satisfactory.

Evidently, AP&L concluded that they need not be prepared to handle

high level samples.

When this was discussed with the licensee during the review, this

misunderstanding was acknowledged, and it was indicated to the NRC

review team member that the required procedures would be developed

as soon as possible.

In turn, the NRC review team member agreed to

provide additional information concerning the NRC's position on this

matter.

i

The lack of these procedures is ameliorated by the ' interim method'

of post-accident sampling developed under NUREG-0578.

This method

is capable of providing a gaseous effluent sample until the long

cange procedures of Item II.F.1.2 nre ready.

l

!

There were no further questions on this item.

l

6.

Retiew of IE Bulletin Responses and Responses to NRC Inspection Reports

.

The scope of this review effort was the licensee's responses to IE

'

Bulletins and NRC inspection reports.

As in other areas, the review of

l

objective evidence to determine the accuracy of the licensee's responses,

concentrated on, but was not limited to ANO-2.

A total of 32 commitments

or required actions were included in this area of the review.

i

L

-

'

.' .

.

9

No items of material misinformation were" discovered in this area of the

review.

One item was noted wherein the licensee failed to carry out a committed

activity as indicated.

This item will be the subject of a Notice of

Deviation.

Item 6 of IEB 79-19 required licensees to develop a training program for

all personnel involved in radioactive waste handling, packaging, and

transport.

In the licensee's letter dated November 30, 1979, the NRC was-

informed that this program would be in place by July 1980.

In

November 1979, the licensee contracted to have this training program, and

the other related actions required by this IEB, prepared.

In the spring

of 1980, the contractor delivered the first parts of the prepared program

(not including the training program).

In October 1980, the contractor

informed the licensee that the June 1980 contract date had been missed

for the delivery of the training program, since the two contractor employees

who were solely responsible for writing it, had left the company.

At about this same time, the f.N0 manager, who had been assigned

responsibility for following this project, left the site.

Apparently, no

turnover was made on this commitment and the contractor did not pursue

-

the matter of completing the training program.

During 1981, the licensee's training department, independent of the

requirements of IEB 79-19, prepared a radwaste training program that

meets some, but not all of the elements in the IEB.

This program has

already been implemented.

The review team had no other questions in this area.

7.

Conclusions

Based on the broad sample of commitments selected and reviewed, the

following conclusions were reached by the NRC special review team:

a.

No new items of material misinformation were discovered.

l

l

b.

There does not appear to be a deliberate attempt to not carry out

l

commitments.

c.

There have been failures to identify specific commitments made, and

to track them to ccmpletion.

d.

The licensee's audit mechanisms apparently have not been effective

in identifying the failure to complete commitments either in the

specific instances noted above or as a general failing.

l

!

_

_

.

_ _

.

.

10

e.

Internal licensee communications regarding NRC responses and the

i

tracking of commitments, in the past, have been poor.

i

8.

Exit Interview

There was no formal exit interview conducted as the overall conclusions-

I

had not been reached by the review team at the completion of the site

visit.

9.

Additional Inforuation

During the site visit, the NRC review team leader was briefed on the

l

licensee's plans, both immediate and long range, to improve

communications among the licensee's organizational units and with the

i

NRC, and to improve the tracking of commitments.

Tnis program has been

described in more detail in the licensee's letter dated September 29,

1982, to the NRC Region IV Regional Administrator.

The steps outlined in

this letter are generally responsive to the conclusions of the special

review team.

I

t

l

{

t-

. _ _ _

_ _ _ _

.

,

. * -

s.

.

'

-

.

.

,

>

,

.

.

.

.

-

TABLE 1

LICENSEE COMMITMENTS REVIEWED

NUREG-0737 " Clarification of TMI Action Plan Requirements"

NUREG-0737 Item

Subject

I . A.1.1

Shift Technical Advisor - Training

l

I.A.1.3

Shift Manning

I.C.1

Inadequate Core Cooling Procedures

I.C.5

Feedback of Operating Experience

I.C.6

Verify correct Performance of Operating.

Activities

II.B.1

RCS Vents

II.B.2

Plant Shielding

II.B.3

Post-Accident Sampling

II.B.4

Training of Mitigating Core Damage

II.D.1

Relief and Safety Valve Testing

II.E.1.1

AFW System Evaluation

II.E.1.2

AFW Auto Start and Flow indication

II.E.4.2.5

Containment Pressure Setpoint

II.E.4.2.6

Containment Isolation - Purge Valves

II.E.4.2.7

Containment Isolation - Radiation

Signal

II.F.1.1

Noble Gas Monitor

II.F.1.2

Iodine /Particular Sampling

a

-

. _ . +

,--

,

.

.

2

NUREG-0737 Item

Subject

II.F.1.3

Containment Hi-range monitor

II.F.1.4

Containment Pressure

II.F.1.5

Containment Waste Level

II.F.1.6

Containment Hydrogen

II.F.2

Instrumentation for Detection of

Inadequate Core Cooling

'

II.K.2.13

Thermal-Mechanical Report

II.K.2.17

Voiding in the Reactor Coolant System

II.K.2.19

Sequential Auxiliary Feedwater Flow

,

6

II.K.3.3

Report on Safety / Relief Valve Failures

-

and challenges

II.K.3.5

Automatic Trip of RCP During a LOCA

,

II.K.3.17

ECC System Outages

II.K.3.25

Power on Pump Seals

II.K.3.30

Small Break LOCA Methods

III.A.1.2

Upgrade Emergency Support Facilities

III.D.3.3

Inplant Radiation Monitoring

III.D.3.4

Control Room Habitability

Within these 33 line items, a total of 84 commitments or statements were verified.

NRR Generic Letters

Letter Date or Number

Subject

September 21, 1979

Followup of Multiple Equipment Failures

and Surveillance Testing Errors

October 17, 1979

Lessons Learned from Release at North

Anna

,

November 9, 1979

Fuel Clad Swelling

!

February 23, 1980

Containment Isolation Valves

__

.

.

3

Letter Date or Number

Subject

June 11, 1980

Decay Heat Technical Specifications

July 31, 1980

Staffing Requirements

December 15, 1980

FSAR Update

81-04

Station Blackout

81-14

Seismic Qualification of Auxiliary Feed

81-19

Thermal Shock to Reactor Pressure Vessel

81-21.

Natural Circulation Cooldown

,

81-28

'

Steam Generator Overfill

Within these 12 generic letters, a total of 22 commitments or statments were

verified.

-

IE Bulletins-

Bulletin

Subject

79-06B

_

TMI Issues

79-09

GE Circuit Breakers

79-13

Cracking in Feedwater System Piping

79-11

Westinghouse Relays

79-18

Audibility of Evacuation Alarr.s

79-19

Radioactive Waste Management

79-23

Diesel Generator Field Exciter

Transformer

79-24

Frozen Lines

79-25

Westinghouse Relays

79-28

Namco Switches

80-05

Vacuum Conditon in Tanks

l

80-10

Contamination of Nonradioactive System

80-11

Masonry Wall Design

.

-

-

- -

.

.

4

Bulletin

Subject

80-12

Decay Heat Removal Operability

80-15

Possible Loss of Emergency

Notification System

80-16

Rosemount Pressure Transmitters

80-18

Minimum Flow Through Centrifugal

Charging Pumps

80-24

Flooding of Containment Sump

80-20

Westinghouse Switches

81-01

Mechanical Snubbers

81-02

Failure of Gate Values to Close

Against Differential

Of the 21 IEB's contained in this review, a total of 29 specific commitments

or statements.

NRC Inspection Reports

Item

50-313/80-03, 50-368/80-03

Notice of Violation

50-313/80-05

Notice of Violation

50-313/80-06, 50-368/80-06

Notice of Violation

50-313/80-10, 50-368/80-10

Notice of Violation

50-313/80-15, 50-368/80-15

Notice of Violation

'.

i

iisi