Application to Amend CPPR-39 & CPPR-69 Extending Const Completion Date to 760701 & 770731,respectively
ML20028D967
Person / Time
Site: Diablo Canyon, 05000000
Issue date: 05/19/1975
From: Worthington J
PACIFIC GAS & ELECTRIC CO.
To:
Shared Package
ML20028D960 List:
References
FOIA-82-556 ISSUAANCES-OL, NUDOCS 8301200175
Download: ML20028D967 (2)


Text

r O

~

O UNITED STATES OF AMERICA NUCLEAR REGUIATORY COMMISSION In the Matter of )

)

PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-2 75-OL

) 50-303-OL Units 1 and 2 )

)

Diablo Canyon Site )

-) ,

Pursuant to 10 CPR 50.55 (b) Pacific Gas and Electric Company i '- r requests the Commission to extend the completion date of Con-

_uction Permit No. CPPR-39 from July 1, 1975 to July 1, 1976, and to extend the complotion date of Construction Permit No. CPPR-69 from July 31, 1976 to July 31, 1977.

Units 1 and 2 at the Diablo canyon site have been delayed approximately six months by construction craft strikes during 1974.

The project was essentially shut duwn from July 1, 1974 to November 11, 1974. When the striko terminated, only approximately forty percent of the original wvtk fvAve was available to return to work. It took approximately five weeks to remobilize tho work force back to the pre-strike level. This five-week period was used for recruiting

, replacement craft labor, retraining, and requalification of welders.

In addition, future uncertainties including potential delays in licensing arising out of protracted public hearings, electrical construction craft labor negotiations, and unanticipated delays in the Jatter stages of construction and preoperational testing make 8301200175 821213 PDR FOIA STECKEL82-556 PDR

i I

h / 4 e u;,;

it desirable to extond the completion dates of the Diablo Canyon construction permits for the one year herein requested.

Subscribed in San Francisco, California, this 19th day of May, 1975.

, Rospectfully submitted, PACIFIC CAS AND ELECTRIC COMPANY By J. D. WORTHINGTON J . 'D . Worthington Senior Vice President JOHN C. MORRISSEY PHIT.IP A. CRANE, JR.

DT.NtI18 C. SUT.LIVAN Attorneys for Pacific Gas and Electric Company By PHILIP A. CRANE, JR.

Philip A. Crane, Jr.

. Subscribed and sworn to before me this 19th day of May, 1975 THEODORA COOKE (q vg,)

Theodora Cooke, Notary Public in and for the City and County of San Francisco, State of California My Commission expires January 28, 197/

t i.

h

, . . )

Commonwealth Edison ~

' ( hj One First PJat.cnal Plata, Chic a ,., lHinois 1N Address Repfy Io: Post Othce Box 767 N. . Ctdcago, finnois 60G90 September 24, 1979 Mr. 11 . R. Denton, Director office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

LaSalle County Station Units 1 and 2 Construction Permit Extension Request NRC Docket Nos. 50-373 and 50-374 References (a): V. A. Moore letter to B. Lee, Jr. dated September 10, 1973 transmitting Construction Permit Nos. CPPR-99 and CPPR-100 (b): R. S. Boyd letter to B. Lee, Jr. dated '

May 31, 1978 transmitting extension to Construction Permit Nos. CPPR-99 and

_ @ l00_

V (c) : C. Reed letter to O. D. Parr dated b -, February 2, 1979 ..-y

Dear Mr. Denton:

Commonwealth Edison Company requests an amendment to che LaSalle County Station Construction Permits CPPR-99 and ~

CPPR-100, as issued by Reference (a) and amended by Reference (b).

This request is made pursuant to the provisions of 10 CFR 50.55(b) .

For the reasons delineated below, we reauest that the " latest com-pletion dates" be revised to June 30, 1981 and March 31, 1982 for

_ Units 1 and 2 respectively. This amendment does not, in the judgement of the applicant, involve a si'gnificant hazard con-sideration. The revised completion dates reflect a conservative construction schedule allowing some margin for potential future l delays, as well as for the installation of additional lateral reinforcing braces between downcomers and additional piping supports in the suppression pool volume tequired by the Mark II containment studies.

N

1. The construction schedule has been adversely affected by a labor strike and woJk stoppage _

from September 5, 1978 to September 22, 1978 -

(3 weeks) by the Boilermaker's Union and jurisdictional work stoppages totaling 6 days i since June 1, 1978. (