Forwards Ltr to Util & Rept Re Investigation of Allegations at Facility.Further Questions Raised Re Potential Problems W/Hvac Contractor.W/O Encls
ML20027E141
Person / Time
Site: LaSalle 
Issue date: 07/19/1982
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20027A786 List:
References
FOIA-82-328 NUDOCS 8211120126
Download: ML20027E141 (1)


Text

--

/

[

UNITE D ST ATES f.,

%[%,

NUCLEAR REGULATORY CO!M.*.lSSION

~

.' E R EGlord til u

, 8,;

C 799 RooSF.VELT ROAD

.g qq,..

'f GLE N E L LYN. ILLifiolS 60137 4.....-

July 19 1982 i

i MEMORANDUM FOR: Harold'R. Denton, Director, Office of Nuclear h!bkh l$

Reactor Regulation

[

~

xm FROM:

James G. Keppler, Regional Administrator aq'W p

p-

SUBJECT:

COMMONWEALTH EDISON COMPAh7 (LASALLE 1) - INVESTIGATION OF ALLEGATIONS DOCKET No. 50-373 We have completed our inspection of the allegations at LaSalle which were considered to have a potential effect on Unit 1 operation.

Attached is a You will note copy of my Ictter to the utility with the enclosed report.

that some further questions have been raised as to potential problems with the HVAC contractor at LaSalle. We have already begun looking into these However, based on our review to this point, we see no reason to matters.

limit the power operation any further at the LaSalle plant.

Recognizing that the plant will be involved in low power physics testing fcr several days, we will continue to look into the HVAC questions, and will inform you promptly should any potential safety issues arise.

Y o.

James G. Keppl Regional Administrator i

Attachments: As Stated cc w/o attachments:

W. J. Dircks, EDO l-V. Stello, IE

/

C. DeYoung, IE /

R.

,go 8211120126 820917

~

PDR FOIA STEPTOES2-328 PDR

~