_

L L

APPENDIX A NOTICE OF VIOLATION Carolina Power & Light Docket No. 50-400 Harris Unit 1 License No. CPPR-158 As a result of the inspection conducted on May 20 - June 20, 1982, and in accordance with the NRC Enforcement Policy, 47 FR 9987 (March 9, 1982), the following violation was identified.

10 CFR 50, Appendix B, Criterion V as implemented by PSAR section 1.8.5.5, CP&L's Corporation QA Program section 6.2.5 and site construction procedures TP-28 and WP-105 require that the QA program be carried out in accordance with procedures or instructions.

Contrary to the above, on June 2,1982 and on lune 4,1982, the CP&L procedures for the installation and inspection of class IE switchgear were not carried out, in that on June 2, 1982 switchgear 1A-SA cubicles were being anchor welded prior to first receiving the required equipment setting inspection, and on June 4,1982 three of four cubicles checked were found not to be plumb or level as required by the manufacturer's requirements, even though the equipment traveler for 1A-SA had been signed by the responsible millwright personnel sometime between June 2 and June 4 showing acceptance for equipment setting.

This is a Severity Level IV Violation (Supplement II.D.).

Pursuant to the provisions of 10 CFR 2.201, you are hereby required to submit to this office within thirty days of the date of this Notice, a written statement or explanation in reply, including:

(1) admission or denial of the alleged viola-tion; (2) the reasons for the violation if admitted; (3) the corrective steps which have been taken and the results achieved; (4) corrective steps which will be taken to avoid further violations; and (5) the date when full compliance will be achieved. Consideration may be given to extending your response time for good cause shown.

JUL 0 71982 Date:

8209160545 820903 i

PDR ADOCK 05000400 G