ML20024H751
| ML20024H751 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 06/04/1991 |
| From: | Fay C WISCONSIN ELECTRIC POWER CO. |
| To: | Samworth R NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation |
| References | |
| CON-NRC-91-051, CON-NRC-91-51 TAC-79388, TAC-79389, VPNPD-91-178, NUDOCS 9106100375 | |
| Download: ML20024H751 (2) | |
Text
_ _ - _ _ _ -
i
,f 4 s Wisconsin Electnc POWER COMPANY 231 W Mchgart Po Box 2046. Mawaukee. Wi 53?04 (414)2207345 VPNPD-91-178 NRC-91-051 June 4, 1991 U.
S.
NUCLEAR REGULATr COMMISSION Document Control Des)
Mail Station P1-137 Washington, D..C.
2,55 Attention:
Mr. Robert B. Samworth, Project Manager Project Directorate III-3 Gentlemen:
DOCKETS 50-266 AND 50-301 10 CFR 50 DEDICATED SHUTDOWN CAPABILITY (TAC'S 79388 AND 79389)
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 This is to advise you, in accordance with your request, that the-switchgear bypass modification for our Point Beach Nuclear Plant has been completed within the schedule committed to in our letter of December 21, 1990.
Onl December 21, 1990, Wisconsin Electric Power Company, licensee for the Point Beach Nuclear Plant, Units 1 and 2, submitted a request-for a schedular exemption to Regulation 10 CFR
- 50. 4 8 (d) (4 ) in accordance with the_ provisions of 10 CFR 50.12.
Paragraph 50.48(d) (4) specifies that, "Those fire protection features involving dedicated shutdown capability requiring new buildings and systems shall be implemented within 30 months of NRC approval."
Under the provisions of.that regulation,.the dedicattd shutdown modifications at our Point Beach Nuclear Plant were to have'been completed by January 27, 1991.
Our December 21 letter-cited certain implementation problems and committed to completion by June 1, 1991.
On January 31, 1991, a meeting was held at Point Beach with Messrs. Hannon and Samworth_of the NRR staff; Mr. Vanderniet, the NRC Senior Resident Inspector for Point Beach;1and other NRC Region III personnel to discuss the details of'our exemption request.
At the meeting we were informed that the exemption request would likely be denied; however, our schedular noncompliance was not considered a plant operability _ concern.
We were cubsequently_ advised in a letter dated March 14, 1991, that our request for a schedular exemption was, indeed, denied.
We were requested to notify you when we had complied with Paragraph 50.48(d;.
$c'/
I 9106100375 910604 fDR ADOCN 0500 6
,g,g,yinrdukwer Dm arepuuhrw
~
<4 e
NRC Document Control Desk June 4, 1991 Page 2 On May 6, 1991, we sent you a letter updating you on the progress of the installation of the switchgear bypass modification at Point Beach Nuclear Plant.
At that time we informed you that all major equipment, including transformer /switchgear, motor control conters, control panel, and local transfer switches, had been installed.
Completion of the remaining work was proceeding on schedule.
We are now informing you that, as of May 31, 1991, all the equipment necessary for dedicated remote shutdown is operable.
Procedures and operator training necessary to familiarize the operators with use of this modification have been completed.
He have also provided dedicated hand-held battery lanterns demonstrated to have greater than eight-hour capacity for interin emergency lighting.
No that equipment locations are finalized, a lighting survey will be performed and additional fixed emergency lighting will be installed if necessary.
We expect to complete this survey and installation of the necessary emergency lighting units by the end of 1991.
As a result of completing these dedicated shutdown capability modifications to bypass the 4160 volt vital switchgear room for those systems necessary to achieve plant shutdown, we are now in compliance with the requirements of 10 CFR 50 Appendix R, Section III.L.
Accordingly, we have suspended those compensatory measures discussed in the attachment to our letter dated December 21, 1990.
Please note that the vital switchgear room remains under the protection of a dedicated Halon fire suppression system which is actuated by permanently installed temperature and/or smoke detectors.
Please contact us if you have any questions regarding our efforts in this matter.
Very truly yours, t2# / 4:
il C. W.
Fay Vice President Nuclear Power Copies to NRC Regional Administrator, Region III NRC Resident Inspector
.-