ML20024C047
| ML20024C047 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 07/01/1983 |
| From: | Parsons R CAROLINA POWER & LIGHT CO. |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| References | |
| CON-NRC-95, REF-PT21-83 10CFR-050.55E, 10CFR-50.55E, NUDOCS 8307120207 | |
| Download: ML20024C047 (5) | |
Text
,
{ N O lA ~d
.M kMird..............._wer & Light Company
}
P. O. Box 101, New Hill, N. C.
27562 July 1, 1983 Mr. James P. O'Reilly NRC-95 United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite 2900)
Atlanta, Georgia 30303 CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT 1986 900,000 KW - UNITS 1 & 2 SHOP WELDING DEFICIENCIES IN SEISMIC I PIPE HANGERS SUPPLIED BY BERGEN-PATERSON, ITEM 95 UNDERSIZE SKEWED TEE FILLET WELDS ON SEISMIC I PIPE HANGERS, ITEM 72
Dear Mr. O'Reilly:
Attached is an interim report on the subject items which were deemed reportable per the provisions of 10CFR50.55(e) and 10CFR, Part 21, on August 13, 1982 (Item 95) and November 5, 1982 (Item 72).
Carolina Power and Light Company is pursuing this matter, and it is currently projected that corrective action and submission of the final report will be accom-plished by October 3, 1983.
Thank you for your censideration in this matter.
Yours very truly, 979 W R. M. Parsons Project General Manager Shearon Harris Nuclear Power Plant RMP/sh Attachment cc: Messrs. G. Maxwell /R. Prevatte (NRC-SHNPP)
Mr. V. Stello (NRC)
%FFICIAL COPY 830712O207 830701 gDRADOCK05000 gA ll1
T '
CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT UNIT NOS. 1 AND 2 INTERIM REPORT SHOP WELDING DEFICIENCIES IN SEISMIC I PIPE HANGERS SUPPLIED BY BERGEN-PATERSON ITEM 95 and UNDERSIZE SKEWED TEE FILLET WELDS ON SEISMIC I PIPE HANGERS ITEM 72 JULY 1, 1983 I
REPORTABLE UNDER 10CFR50.55(e)
REPORTABLE UNDER 10CFR21
SUBJECT:
Deficient shop welds on pipe hangers previously accepted by Bergen-Paterson (B-P) and Ebasco Welding Inspectors.
ITEM:
Seismic Pipe Hangers SUPPLIED BY:
Bergen-Paterson Pipe Support Corporation, Laconia,-
New Hampshire NATURE OF DEFICIENCY:
1.
Poor workmanship 2.
Missing and undersized welds 3.
Cosmetic weld defects 4.
Undersized skewed tee welds 5.
Deficient welds accepted by B-P inspectors and Ebasco Vendor Quality Assurance (VQA) inspectors.
DATE PROBLEM OCCURRED:
Prior to October 1, 1982 DATE PROBLEM REPORTED:
On August 13, 1982 CP&L (Mr. N. J. Chiangi) notified the NRC (Mr. A. Hardin) that this item (Item 95) was reportable under 10CFR50.55(e) and 10CFR, Part 21.
In our November 5, 1982 letter, CP&L (Mr. R. M. Parsons) notified the NRC (Mr. J. P. O'Reilly) that this item (Item 72) was reportable under 10CFR50.55(e) and 10CFR, Part 21.
SCOPE OF PROBLEM:
Seismic Category I pipe hangers which were inspected at the source of fabrication prior to October 1, 1982.
4!-
SAFETY IMPLICATIONS:
Deficient welds could cause a safety-related pipe hanger to fail under seismic conditions. As a result, if not corrected, could adversely affect the safe operation of this facility.
REASON THE DEFICIENCY IS REPORTABLE:
The conditions reported in Item 95 and Item 72 represent breakdowns in B-P and Ebasco QA programs which allowed supports to be shipped with welds which were not in accordance with design criteria. This mandated that the incident be identified as reportable under 10CFR50.55(e) and 10CFR, Part 21.
CORRECTIVE ACTION:
1.-
Hangers with shop weld deficiencies were identified during the following processes:
A.
Receipt Inspection..
B.
Inspection in the warehouse prior to hanger issuance to the field.
C.
Inspection in the field of installed hangers which had not been_previously inspected by CP&L for shop weld deficiencies (does not include those hangers that were in Reinspection -
See D)
D.
Reinspection of pipe hangers that were installed or partially installed and inspected prior to June 26, 1982. The June 26, 1982 date was selected because the QC weld inspection program for installed hangers was expanded to include shop welds. The reinspection included measure-meat of skewed-tee fillet welds for undersize
.(refer to Item 72). Those 349 hangers previously reinspected as part of the corrective action to NRC Report 50-400/82-03 were not included in
~
this reinspection.
Inaccessible welds were encountered during the reinspection.
These are under evaluation by Engineering.
2.
695 hangers with defective shop welds were identified by processes A, B & C (see above) and some were not-reworked at the time of reinspection. The rework will be performed during the normal erection sequence.
3.
3,458 hangers were reinspected (i.e. Process'D).
Some hangers were not reworked at the time of-reinspection due_to the hangers being on engineering hold for.various reasons, including redesign, re-analysis, pending later drawing revision, voided
. drawing, etc.
These hangers will be reworked when the engineering holds are released.
4.
Instruction measures have-been established to control pipe hangers which have not been-installed but were received prior to October 1, 1982. We have taken the option to inspect shop welds prior to issue from-the warehouse or to inspect shop welds at the same time field welds are inspected. Defective welds will be identified on DDR's for control and evaluation.
PREVENTIVE MEASURES TAKEN TO AVOID FURTHER NONCOMPLIANCE:
1.
Field Change Request (FCR) H-979 was developed and issued to provide weld inspection acceptance criteria for both field and shop welds based on the AWS Dl.1 code and B-P design criteria.
4 2.
Ebasco VQA began performing in-process j
inspections and 100%' inspection of hanger 1
welds on October 1, 1982. This is to be performed throughout the remainder of the-B-P purchase order.
3.
Ebasco VQA management regularly visits the B-P Laconia facility to confer with the Ebasco VQA representative and to witness the VQA-inspector'c activities.
1 4.
B-P welders and inspectors and Ebasco VQA inspectors have received additional training in weld acceptance criteria.
5.
100% shop weld inspection is presently i
being performed on site for-hangers I
received from B-P to ensure this problem does not reoccur.
i FINAL REPORT:
The above corrective action and preventive e
measures are considered adequate to close'this item. However, to ensure all hangers installed prior to the start of the reinspection (Process D) were identified, the. pipe hanger work package transmittals are being checked against the hanger-reinspection log to ensure all appropriate hangers were considered for reinspection. The i
accept / reject status of hangers in the reinspec-tion log is being double checked.
Finally, to ensure that no hangers subject to the reinspection were overlooked, measures will I
be established to ensure a further check is done when the hanger work packages are reviewed during subsequent installation and inspection phases.
Any hanger inadvertently missed during the initial reinspection effort will be reinspected and appropriately dispositioned.
A final report will be issued once the measures described above have been completed.
It is currently projected that the submittal date will be October 3, 1983.
1 1
1 4
e
_., _