Advises That Individual Plant Exam Approach,Methodology & Schedule,Provided in in Response to Generic Ltr 88-20,acceptable.Schedule Changes Should Be Reported to NRC
ML20012D022
Person / Time
Site: Salem, Hope Creek  
Issue date: 03/20/1990
From: Stone J
Office of Nuclear Reactor Regulation
To: Miltenberger S
Public Service Enterprise Group
References
GL-88-20, TAC-74421, TAC-74461, TAC-74462, NUDOCS 9003260313
Download: ML20012D022 (4)


Text

_.

t t*

March 20, 1990

?

Docket Nos. 50-354

,ESTRIBUTION 50-272 rocart.r JStone and 50-311 NRC POR ;ye; MThadani Local PDR CShirati Mr. Steven E. Miltenberger PDI-2 Reading

$ Brown Vice President and Chief Nuclear SVerga OGC Officer BBoger EJordan Public Service Electric and Gas WButler ACRS(10)

Company M0'Brien MBoyle Post Office Box 236 JFlack Hancocks Bridge, New Jersey 08038 i

Dear Mr. Miltenberger:

SUBJECT:

REVIEW OF 60-DAY RESPONSE TO GENERIC LETTER 88-20, INDIVIDUAL P'. ANT EXA!!! NATIONS (IPE) (TAC NOS. 74421,74461AND744E2)

Re:

POPE CREEK GENERATING STATION AND SALEM GENERATING STATION, UNITS 1 AND 2 Generic Letter 88-20 requires, in part, that each operating reactor licensee and construction permit holder: (1) identify the approach and method selected for performing the IPE, (2) describe the method to be used, and (3) identify the schedule for performing the IPE and submitting the results to the NRC.

i This information was to be submitted to the NRC within 60 days of issuance of Supplement 1 of the generic letter.

We have reviewed your letter dated November 1,1989, submitted in response to the reporting requirements of the generic letter. We conclude that your IPE approach, methodology and schedule are acceptable. We anticipate that any possible additional analysis or reporting requirements, such as those from external events or from the Containment Performance Improvement Program, will not have any adverse effect on your schedule. However, if your schedule should change, please notify the NRC of the proposed change and the reason for the change.

Should you have any(questionc please contact Mr. Clyde Y. Shiraki, Hope Crect Proiect Manager on 30)492-1445 or Mr. James C. Stone, Salem Project Manager onl301)492-1422.

Sincerely, James C. Stone for

/s/

Clyde Y. Shiraki, Project Manager James C. Stone, Project. Manager

. Project Directorate 1-2 Project Directorate 1,

Division of Reactor Projects 1/11 Division of Reactor Projects 1/11, Office of Nuclear Reactor Regulation Office of Nuclear Reactor Regulation.

cc: See next page

( b }JStone:mj i

PDI-2/PM PDI-G/PM PDI-2/D

^

CShiraki WButler j

A g QV90 3/3D/90 3 p /90

/

i

[,

2

}0

~ _-

i

((potes

\\

UNITED $TATES l

g NUCLEAR REGULATORY COMMISSION 5

W ASHINGTON, D. C. 70666 S.y.... +,f'.

March 20, 1990 Docket Nos. 50-354 t

50-272 and 50-311 Pr. Steven E. Miltenberger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Box 236 Hancocks Bridge, New Jersey 08038 j

Dear Mr. Miltenberger:

SUBJECT:

REVIEW OF 60-DAY RESPONSE TO GENERIC LETTER 88-20, INDIVIDUAL PLANT EXAMINATIONS (IPE) (TAC NOS. 74421,74461AND74462)

Pe:

HOPE CREEK GENERATING STATION AND SALEM GENERATING STATION, UNITS 1 AND 2 Generic Letter 88 20 requires, in part, that each operating reactor licensee and construction permit holder: (1) identify the approach and method selected for performing the IPE, (2) describe the method to be used, and (3) identify the schedule for performing the IPE and submitting the results to the NRC.

This information was to be submitted to the NRC within 60 days of issuance of Supplement 1 of the generic letter.

We have reviewed your letter dated November 1,1989, submitted in response to the reporting requirements of the gereric letter. We conclude that your IPE approach, methodology and schedule are acceptable. We anticipate that any possible additional anelysis or reporting reouirements, such as those from external events or from the Containment Performance Improvement Program, will not have any adverse effect on your schedule.

However, if your schedule should change, please notify the NRC of the proposed change and the reason for the change.

Should you have any(questions please contact Mr. Clyde Y. Shiraki i

Hope Creek Project Manager on 30)492-1445 or Mr. James C. Stone, Salem Project Manager on(301)492-1422, i

Sincerely, y

@ Clyde Y. Shiraki, Project Manager James C. Stone, Project Manager Project Directorate 1-2 Project Directorate 1-2 Division of Reactor Projects 1/11 Division of Reactor Projects 1/11 Office of Nuclear Reactor Regulation Office of Nuclear Reactor Regulation cc: See next page i

l 1

e

-m

-vm,-

~wnr+. - - - - - -.

-e.e

,+--

~--,,--w m

e e,->-

,e

~

Mr. Steven E. Miltenberger Hope Creek Generating Station Public Service Electric & Gas Co.

i e

ec.

i M. J. Wetterbahn, Esquire Conner & Wetterhahn Mr. Scott B. Ungerer Manager Suite 1050 Joint Generation Projects Departrent 1747 Pennsylvania Avenue Atlentic Electric Company Post Office Box 1500 Keshington. 0.C.

20006 Pleasantville, New Jersey 08232 R. Fryling, Jr., Esquire Law Department - Tower SE 80 Park Place Newark, New Jersey 07101 Resident inspector U.S. Nuclear Regulatory Commission P.O. Box 241 Hancocks Bridge, New Jersey 08038 Mr. S. LaBruna Vice President - Nuclear Operations Nucitar Department P.O. Box 236 i

Hancocks Bridge, New Jersey 08038 Mr. J. J. Hagan General Manager - Hope Creek Operations Hope Creek Generating Station P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. B. A. Preston, ManPger Licensing and Regulation Nuclear Department P.O. Box 236 Hancocks Bridae, New Jersey 08038 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 Dr. Jill Lipoti, Ph.D New Jersey Department of Environmental Protection Radiation Protection Program State of New Jersey CN 415 Trenton, New Jersey 08625 t

9 Mr. Steven E. M11tenberger Public Service Electric & Gas Company Salem Nuclear Generating Station Cc:

Mark J. Wetterhahn, Esquire Richard B. McGlynn, Comission Conner and Wetterhahn Suite 10F0 Department of Public Utilities 1747 Pennsylvania Avenue, NW State of New Jersey 101 Commerce Street k'ashington, DC 20006 Newark, NJ 07102 Richard Fryling, Jr., Esquire Law Department - Tower SE Regional Administrator, Region 1 80 Park Place U. S. Nuclear Regulatory Comission 475 Allendale Road Newark, NJ 07101 King of Prussia, PA 19406 Mr. L. K. Miller General Manager - Salem Operations Lower Alloways Creek Township Saler Generating Station c/o Mary O. Henderson, Clerk P.O. tox 236 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. S. 1.aBruna Mr. Bruce A. Preston, Manager Licensing and Regulation Vice President - Nuclear Operations Nuclear Department Nuclear Department P.O. Box 236 P.O. Box 236 Hancocks Bridge, NJ 0B038 Hancocks Bridge, New Jersey 03038 Mr. David Wersan Mr. Themas P. Johnsen, Senior Pesident Assistant Consumer Advocate Inspector salem Generating Statien Office of Consumer Advocate 1425 Strawberry Square U.S. Nuclear Regulatory Comission Harrisburg, PA 17120 Orawer I Hancocks Bridge, NJ 08038 Mr. Scott B. Ungerer Dr. Jill Lipoti, Ph.D MGR. - Joint Generation Projects Atlantic Electric Company New Jersey Departnent of Environmental P.O. Box 1500 Protection 1199 Black Horse Pike Division of Environmental Ouality Pleasantville, NJ 08232 Radiation Protection Programs State of New Jersey Mr. Jack Urban CN 415 General Manager, Fuels Department Trenton, NJ 08625 Delmarva Fower & Light Company 800 King Street Maryland People's Counsel Wilmington, DE 19899 American Building, 9th Floor 231 East Baltimore Street Public Service Commission of Maryland Baltimore, Maryland 21202 Engineering Division ATTN: Chief Engir.eer Mr. J. T. Robb, Director Joint Owners Affairs 231 E. Baltimore Street Baltimore, MD 21202-3486 Philadelphia Electric Company 955 Chesterbrook Blvd., 51A-13 Wayne, PA 19087 1