Notice of Violation from Insp on 891108-1205.Violation Noted:Cable Grip Improperly Suspended from End of Electrical Penetration Assembly E-76 Module Located Inside of Isolation Tank for motor-operated Valve 1-HV-4782
ML20011D908
Person / Time
Site: Comanche Peak 
Issue date: 12/21/1989
From: Warnick R
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20011D904 List:
References
50-445-89-84, NUDOCS 9001020296
Download: ML20011D908 (2)


Text

. - _.

0

~

APPENDIX ~A NOTICE OF VIOLATION TU-Electric Docket:

50-445/89-84 Comanche Peak Steam Electric Station Permit:

CPPR-126 Unit 1, Glen Rose, Texas During an NRC inspection conducted on November 8 through December 5, 1989,.a violation of NRC requirements was identified.

In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2 ~,: Appendix. C (1989), the violation is listed below:

Criterion V of' Appendix D to 10 CFR Part 50 as implemented by Section 5.0 of the TU Electric Quality Assurance Manual. requires that activities affecting quality shall be prescribed by and accomplished in accordance with documented instructions, procedures, or drawings.

Paragraph 3.2.3.1 of Electrical. Installation Specification 2323-ES-100, Revision 6,-requires that cable support systems shall be installed in accordance-with the engineer's drawings and Appendix N of this specification.

Contrary to the-above, the NRC inspector observed a cable grip which l

was improperly suspended from the end of electrical. penetration.

I assembly E-76_ module located inside the' isolation tank for the.

containment spray motor operated valve: 1-HV-4782.

The improperly suspended cable grip bail was located at the module polymer seal which could have damaged the penetration seal and/or the Kapton insulated wires associated with the penetration.

The' observed cable-support configuration was contrary to the requirements of the applicable Design Change Authorization 59365, Revision 1.

,j This is a Severity Level IV violation (Supplement II) j l

(445/8984-V-01).

1 Pursuant co the provisions of 101CFR 2.201, TU Electric is hereby j

required to submit a written statement or explanation to;the U.

S.

4 L

Nuclear Regulatory Commission,157N: Document Control Desk, j

l Washington, DC, 20555, with a copy to the Assistant Director for-i l

Inspection Programs, Comanche Peak Project Division, Office of j

Nuclear Reactor Regulation, within 30 days of the date of the letter transmitting this Notice.

This reply should be clearly marked as a.

j

" Reply to a-Notice of Violation" and should include for the violation:

(1) the reason for the violation if admitted, (2) the corrective steps that have been taken and the results achieved,-

)

f 9001020296 891221 l

PDR ADOCK 05000445 O

PDC

  • (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.

If an adegaate reply is not received within the time specified in this Notice, an order may be issued to show cause why the license should not be modified, suspended, or revoked or why suen othen action as may be proper should not be taken.

Where good cause is shown, consideration will be given to extending the response time.

FOR THE NUCLF.Jdt REGULATORY COMMISSION RF ID A Dated at Comancho Peak Site this 21st day of December 1989 I