See also: IR 05000445/1989084
Text
s
i
'
s,
n
'
'
..' -
,
In Reply Refer To:
E 2 l 1989
Dockets:
50-445/89-84.
-50-446/89-84
-Mr.
W.-J.
Cahill, Jr.
Executive Vice President
,
TU Electric
'400 North Olive Street, Lock Box 81-
3
Dallas, Texas
75201
Dear: Mr. Cahill:
This refers to the inspection conducted by Mr. R. M. Latta and NRC
j
consultants during the period November 8 through December 5, 1989,
of activities authorized by NRC : Construction ' Permits CPPR-126 - and
CPPR-127.for the, Comanche Peak Steam Electric Station, Units 1
and 2, and to.the discussion of our findings with;you and members of
your staff at the conclusion of-the: inspection.
<
The enclosed copy of our inspection. report identifies areas examined:
during the inspection. . Within these areas, the inspection consisted.
of selective examination of procedures and. representative records,
interviews with personnel, and observations by the inspectors.c
During this inspection, it was found that certain of your activities
were in' violation of NRC requirements, as specified in the-enclosed.
A writtenLresponse to this' violation is,
required.
.
In accordance with 10.CFR 2.790 of the Commission's regulations, a
copy of this letter, the enclosures, and your response to~this.
letter will.be placed in the NRC Public Document-Room.
The response _ directed.by this letter and the accompanying: Notice is'
not subject to the clearance procedures of the office of: Management
'
and Budget as required by the Paperwork Reduction Act of 1980,
PL 96-$11.
!
Should you have any questions concerning-this inspection, we will be
pleased to discuss them with you.
Sincerely,
ORIGUTAE FIGNED E7 R. F. WARN 7Cr
R. F. Warnick, Assistant Director
for Inspection Programs:
Comanche Peak Project. Division
Office of Nuclear Reactor Regulation.
Enclosures: (See next page)
RFla &
Kph)
'
RI:CPPD:NRR
CPPD:NRR.
AD:CPPD:NRR
RLatta:
HLivermore
RWarnick
12/>#/89
12/*8/89
12 /El '/89
9001020286 891221
[Ed
.PDR
ADOCK 05000443
~
<
Q
'
,,
-
.
..-- .
- - -
-
.-
____
_
.
4
!'
- c
. -
"#'*Q
=i
,/
- #g
UNITED STATE 8
NUCLEAR REGULATORY COMMISSION
i
!
l
WASHINGTON, D. C. 20088
k**..*
DEC 21 1989
'
In Reply Refer-To:
r
Dockets:
50-445/89-84
j
50-446/89-84
,
Mr. W. J. Cahill, Jr.
[
!
Executive Vice President
TU Electric
400 North Olive Street, Lock Box 81
Dallas,: Texas
75201-
'
Dear Mr. Cahill:
This refers to the inspection conducted by Mr. R. M. Latta and NRC
consultants during the period-November'8 through December 5,:1989,
of activities authorized by NRC Construction Permits CPPR-126 and-
CPPR-127 for the Comanche Peak Steam Electric Station, Units-1
-'
-and 2, and to the discussion-of our findings with you and members:of
your staff at the conclusion of.the inspection.-
The enclosed copy of our inspection report identifies areas examined
during the inspection.
Within these areas, the inspection consisted
.'
of selective examination of procedures and representative records,-
interviews with personnel, and observations by.the inspectors.
During this inspection, it was found that certain of your activities
were in violation of NRC requirements, as specified in the enclosed.
A written response to this violation is
required.
In accordance with 10 CFR 2.790 of the-Commission's regulations, a
ccpy of this letter, the enclosures, and your response-to this
letter will be placed in the NRC-Public. Document Room.
!
The response directed by this letter and.the accompanying Notice is
L
not subject to the clearance proceduresLof the Office of Management
and Budget as required by the Paperwork Reduction Act of 1980,
PL 96-511.
Should you have any questions concerning this inspection., we will be
pleased to discuss them with you.
.
Sincerely,
RVW A
R. F. Warnick, Assistant Director
for Inspection Programs
,
Comanche Peak Project Division
Office of Nuclear Reactor Regulation
~ Enclosures:
(See next page)
,
- , - -
- - - -
sr
.--..
, , - . . -
--
.
=
.
.
. -.
-
.
--
.
. -
-
__
-
,
.
.
.
.
W. J. Cahill, Jr.
-2-
DEC 2 l 1989
Enclosures
Appendix A - Notice of Violation
Appendix B - Inspection Report 50-445/89-84s 50-446/89-84
i
cc w/ enclosures
Roger D. Walker
TU Electric
Manager, Nuclear Licensing
c/o Bethesda Licensing
TU Electric
3 Metro Center, Suite 610
Skyway Tower
Bethesda, Maryland
20814
400 North Olive Street, L.B.
81
-Dallas, TX
75201
E. F. Ottney
P. O. Box 1777
Juanita Ellis
Glen Rose, Texas
76043
President - CASE
1426 South Polk Street
Jack R. Newman
Dallas, TX
75224
Newman & Holtzinger
1615 L Street, NW
Texas Radiation Control
Suite 1000
Program Director
20036
.
Texas Department of Health-
'
1100 West 49th Street
George R. Bynog
78756
Program Mgr./ Chief Inspector
s
Texas Dept. of Labor & Standards
GDS Associates, Inc.
Boiler Division.
1850 Parkway Place, Suite 720
P.O. Box 12157, capitol Station
Marietta, GA
30067-8237
78711
Honorable George Crump
County Judge
Glen Rose, Texas
76043
Ms. Billie Pirner Garde, Esq.
Robinson, Robinson,-et al.
I
103 East College Avenue
l
Appleton, WI- 54911
Regional Administrator, Region IV
U.S. Nuclear Regulatory Commission
611 Ryan Plaza Drive, Suite 1000
Arlington, Texas
76011.