ML20010A527

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-424/81-06 & 50-425/81-06 on 810602-06 & Notice of Violation
ML20010A527
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 06/19/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML20010A513 List:
References
NUDOCS 8108110510
Download: ML20010A527 (2)


See also: IR 05000424/1981006

Text

-

__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'o

UNITED STATES

-

f

- , [$

8*

NUCLEAR REGULATORY COMMISSION

MY

REGION 11

thh*'f"' [

101 MARIETTA ST.. N.W.. SUITE 3100

ATt.ANTA. GEORGIA 30303

j-

  • ....

JUN 191981

Georgia Power Company

ATTN: Mr. J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street

Atlanta, GA 30303

Gentlemen:

Subject: Report Nos. 50-424/81-06 and 50-425/81-06

This refers to the routine inspection conducted by Mr. J. R. Harris of this

office on June 2-6, 1981, of activities authorized by NRC Construction Permit

Nos. CPPR-103 and CPPR-109 for the Vogtle facility.

Our. preliminary findings

were discussed with Mr. H. H. Gregory, III, Assistant Proj'.ct Manager, at the

conclusion of the inspection.

Areas examined during the inspection and our findings tre discussed in the

enclosed inspection report.

Within these areas, the int? action consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your license

appear to violate NRC requirements.

This item and references to pertinent

requirements are listed in the Notice of Violation enclosed herewith as Appen-

dix A.

Elements to be included in your response are delineated in Appendix A.

We have examined actions you have taken with regard to previously identified

enforcement matters and unresolved items. The status of these items is discussed

in the enclosed report.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Room.

If the report contains any information that you believe to be exempt from

!

disclosure under 10 CFR 9.5(a)(4), it is necessary that you:

(a) notify this

l

office by telephone within ten days from the date of this letter of your inten-

tion to file a request for withholding; and (b) submit within twenty-five days

from the date of this letter a written application to this office to withhold

such information. If your receipt of this letter has been delayed such that less

than seven days are available for your review, please notify this office promptly

so that a new due date may be established. Consistent with section 2.790(b)(1),

such application must be accompanied by an affidavit executed by the owner of the

information which identifies the document or part thereof sought to be withheld,

and a full statement of the reasons on the basis of which it is claimed that the

9108110510 810731'

PDR ADOCK 05000424

G

PDR

-

_ _ - _ _ - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

JUN 191981

"

Georgia Power Company

2

information should be withheld from public disclosure.

This section further

requires the statement to address with specificity the considerations listed in

10 CFR 2.790(b)(4). The information sought to be withheld shall be incorporated

as far as possible into a separate part of the affidavit.

If we do not hear from

you in this regard within the specified periods noted above, the report will be

placed in the Public Document Room.

Should you have any questions concerning this lette- we will be glad to discuss

them with you.

Sincerely,

g. c.

R. C.

awis, Acting Director

Division of Resident and

Reactor Project Inspection

.

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-424/81-06

and 50-425/81-06

cc w/ encl:

K. M. G llespie, Construction

Project Manager

E. D. Groover, QA Site Supervisor

D. E. Dutton, Project General Manager