ML20010A527
| ML20010A527 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 06/19/1981 |
| From: | Robert Lewis NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | John Miller GEORGIA POWER CO. |
| Shared Package | |
| ML20010A513 | List: |
| References | |
| NUDOCS 8108110510 | |
| Download: ML20010A527 (2) | |
See also: IR 05000424/1981006
Text
-
__
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
'o
UNITED STATES
-
f
- , [$
8*
NUCLEAR REGULATORY COMMISSION
MY
REGION 11
thh*'f"' [
101 MARIETTA ST.. N.W.. SUITE 3100
ATt.ANTA. GEORGIA 30303
j-
- ....
JUN 191981
Georgia Power Company
ATTN: Mr. J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street
Atlanta, GA 30303
Gentlemen:
Subject: Report Nos. 50-424/81-06 and 50-425/81-06
This refers to the routine inspection conducted by Mr. J. R. Harris of this
office on June 2-6, 1981, of activities authorized by NRC Construction Permit
Nos. CPPR-103 and CPPR-109 for the Vogtle facility.
Our. preliminary findings
were discussed with Mr. H. H. Gregory, III, Assistant Proj'.ct Manager, at the
conclusion of the inspection.
Areas examined during the inspection and our findings tre discussed in the
enclosed inspection report.
Within these areas, the int? action consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
During the inspection, it was found that certain activities under your license
appear to violate NRC requirements.
This item and references to pertinent
requirements are listed in the Notice of Violation enclosed herewith as Appen-
dix A.
Elements to be included in your response are delineated in Appendix A.
We have examined actions you have taken with regard to previously identified
enforcement matters and unresolved items. The status of these items is discussed
in the enclosed report.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be exempt from
!
disclosure under 10 CFR 9.5(a)(4), it is necessary that you:
(a) notify this
l
office by telephone within ten days from the date of this letter of your inten-
tion to file a request for withholding; and (b) submit within twenty-five days
from the date of this letter a written application to this office to withhold
such information. If your receipt of this letter has been delayed such that less
than seven days are available for your review, please notify this office promptly
so that a new due date may be established. Consistent with section 2.790(b)(1),
such application must be accompanied by an affidavit executed by the owner of the
information which identifies the document or part thereof sought to be withheld,
and a full statement of the reasons on the basis of which it is claimed that the
9108110510 810731'
PDR ADOCK 05000424
G
-
_ _ - _ _ - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
JUN 191981
"
Georgia Power Company
2
information should be withheld from public disclosure.
This section further
requires the statement to address with specificity the considerations listed in
10 CFR 2.790(b)(4). The information sought to be withheld shall be incorporated
as far as possible into a separate part of the affidavit.
If we do not hear from
you in this regard within the specified periods noted above, the report will be
placed in the Public Document Room.
Should you have any questions concerning this lette- we will be glad to discuss
them with you.
Sincerely,
g. c.
R. C.
awis, Acting Director
Division of Resident and
Reactor Project Inspection
.
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-424/81-06
and 50-425/81-06
cc w/ encl:
K. M. G llespie, Construction
Project Manager
E. D. Groover, QA Site Supervisor
D. E. Dutton, Project General Manager