Advises That 891027 Response to Generic Ltr 88-20 Re Individual Plant Exam Approach,Methodology & Schedule Acceptable
ML20006B201
Person / Time
Site: Dresden, Byron, Zion, 05000000
Issue date: 01/24/1990
From: Shemanski P
Office of Nuclear Reactor Regulation
To: Kovach T
COMMONWEALTH EDISON CO.
References
GL-88-20, TAC-74382, TAC-74383, TAC-74405, TAC-74406, TAC-74492, TAC-74493, NUDOCS 9002010089
Download: ML20006B201 (5)


Text

.

January 24, 1990 3 NRC & Local PDRs Docket Nos. 50-454, 50-455, PD111-2 r/f LLuther 50-237, 50-249, PShemanski L01shan I

50-295, 50-304 CPatel BSiegel OGC EJordan Thomas J. Kovach ACRS(10)

Plant File Nuclear Licensing Manager MBoyle Jflack i

Commonwealth Edison Company OPUS West 111 1400 OPUS Place, Suite 300 Downers Grove, Illinois 60515

)

Dear Mr. Kovach:

SUBJECT:

REVIEW Of 60-DAY RESPONSE TO GENERIC LETTER 88-?0, INDIVIDUAL PLANTEXAMINATIONS(IPE)(TACNOS. 74382, 74383, 74405, 74406, 74492,74493)

Re:

Byron 1/2, Dresden 2/3 Zion 1/2 Generic Letter 88-20 requires, in part, that each operating reactor licensee and construction permit holder: (1) identify the approach and method selected for performing the IPE, (2) describe the method to be used, and (3) identify the schedule for performing the IPE and submitting the results to the NRC.

This information was to be submitted to the NRC within 60 days of issuance of Supplement 1 of the generic letter.

We have reviewed your letter dated October 27, 1989, submitted in response to the reporting requirements of the generic letter. We conclude that your IPE approach, methodology and schedule are acceptable. We anticipate that any possible additional analysis or reporting requirements, such as those from external events or from the Containment Performance Improvement Program, will not have any adverse effect on your schedule.

However, if your schedule should change, please notify the NRC of the proposed change and the reason for the change.

should you have any questions concerning the requirements of the generic letter, please contact Paul Shemanski at (301)492-3101.

Sincerely, C

Paul C. Shemanski, Project Manager Project Directorate 111-2 Division of Reactor Projects - III, IV, Y and Special Projects cc:

See next page OFFICIAL RECORD COPY

/0 Document Name:

IPE2 g

PD111-2:PM PDij gJV gg PShemanski:ta JCr 900201oce9 900124 1/0/90 1/a] /90 PDR ADOCK c5000237 p

PDC g

i

[ f UNITf3 STATES I

3 n,

NUCLEAR REGULATORY COMMISSION q.

WASHINGTON, D. C. 20H6

.... /

i January 24, 1990 i

j Docket Nos. 50-454, 50-455, 50-237, 50-249, 50-295, 50-304 Thomas J. Kovach Nuclear Licensing Manager Commonwealth Edison Company OPUS West 111 1400 OPUS Place, Suite 300 i

j Downers Grove, Illinois 60515

Dear Mr. Kovach:

SUBJECT:

REVIEW OF 60 DAY RESPONSE TO GENERIC LETTER 88-20, INDIVIDUAL PLANT EXAMINATIONS (IPE) (TAC NOS. 74382, 74383, 74405, 74406, l

7a492.74493)

Re:

Byron 1/2, Dresden 2/3, Zion 1/2 Generic Letter 88-20 requires, in part, that each operating reactor licensee l

and construction per: nit holder: (1) identify the approach and method selected for performing the IPE, (2) describe the method to be used, and (3) identify the schedule for performing the IPE and submitting the results to the NPC.

This information was to be submitted to the NRC within 60 days of issuance of l

Supplement 1 of the generic letter.

We have reviewed your letter dated October 27, 1989, submitted in response to the reporting requirements of the generic letter. We conclude that your IPE approach, methodology and schedule are acceptable. We anticipate that any possible additional analysis or reporting requirements, such as those from external events or from the Containment Performance Improvement Program, will i

not have any adverse effect on your schedule.

However, if your schedule should change, please notify the NRC of the proposed change and the reason for the change.

Should you have any questions concerning the requirements of the generic letter, please contact Paul Shemanski at (301)492-3101.

Sincerely, h(.E

/r.s Paul C. Shemanski, Project Manager Project Directorate 111-2 Division of Reactor Projects - 111, IV, Y and Special Projects cc:

See next page

i Mr. Thomas J. Kovach Byron Station Comonwealth Edison Company Units 1 and 2 cc:

Mr. Jack Tain Regional Administrator Atomic Power Distribution U. S. Nuclear Regulatory f

Westinghouse Electric Corporation Comission Post Office Box 355 799 Roosevelt Road Bldg. (4 Pittsburgh, Pennsylvania 15230 GlenEllyn, Illinois 60h37 l

Michael Miller, Esq.

1111nois Department of Sidley and Austin Nuclear Safety One First National Plaza Office of Nuclear Facility Safety Chicato, Illinois 60690 1035 Outer Park Drive Springfield, Illinois, 62704 Mrs. Phillip B. Johnson Joseph Gallo, Eso.

1907 Stratford Lane Hopkins end Sutter Rockford, Illinois 61107 888 16th Street, N.W.

Suite 700 Ps. Lorraine Croek Rt. 1. Bcx 182 Douglass Cassel Esq.

Manteno, Illinois 60950 109 N. Dearborn Street Suite 1300 Dr. Bruce von Zellen Chicago, Illinois 60602 Departnent of Biological Sciences Northern Illinois University Ms. Pat Morrisnn DeKalb, Illinois 61107 913 N Main Street 0 07 Rockford, Illinois 61103-7058 Hr. Edward R. Crass Nuclear Safeguards & Licensing Attorney General Sergent & Lundy Engineers 500 South 2nd Street 55 East Monroe Street Springfield, Illinois 62701 Chicate, Illinois 60603 Chairman, Ogle County Board V. S. Nuclear Regulatory Commission Post Office Box 357 Byron / Resident inspectors Offices Oregon, Illinois 61061 4448 North German Church Road Byron, Illinois 61010 EIS Review Coordinator Environnental Protection Agency Region V 230 S. Dearborn Street Chicago, Illinois 60604 Comonwealth Edison Company Byron Station Manager 4450 North German Church Road Byron, Illinois 61010

l o

i

..'t'.r. Thomas J. Kovach Dresden Nuclear Power Station t

Comonwealth Edison Company Units 2 and 3 I

I cc.

i Michael 1. Miller, Esq.

Sidley and Austin One First National Plaza Chicago, Illinois 60690 Mr. J. Eenigenburg i

Plant Superintendent Dresden Nuclear Power Station Rural Route il Morris, Illinois 60450 U. S. Nuclear Regulatory Comission Resident Inspectors Office Dresden Station Rural Route il j

Morris, Illinois 60450 Chairman Board of Supervisors of Grundy County Grundy County Courthouse i

Morris, Illinois 60450 Regional Administrator Nuclear Regulatory Comission, Region !!!

799 Roosevelt Road Bldg. #4 Glen Ellyn, Illinois 60137 1111nois Department of t!uclear Safety Office of Nuclear Facility Safety 1035 Outer Park Drive Springfield, Illinois 62704 h

5 1

I I

. ~

o

- N'r' Thomas J. Kovach Zion Nuclear Power Station Commonwealth Edison Company Units 1 end 2 1

l CC:

Robert J. Vollen Esquire 109 North Dearborn Street l

Chicago, Illinois 60602 l

Dr. Cecil Lue-Hing Director of Research and Development Metropolitan Sanitary District l

of Greater Chicago 100 East Erie Street Chicago, Illinois 60611 1

Phillip Steptoe, Esq.

Sidley and Austin One First National Plaza Chicago, Illinois 60603 Mayor of Zion Zion, Illinois 60099 1111nois Department of Nuclear Safety Office of Nuclear Facility Safety 1035 Outer Park Drive Springfielo, Illinois 62704 U.S. Nuclear Regulatory Comission Resident inspectors Office 105 Shiloh Blvd.