Forwards IE Insp Repts 50-413/81-09 & 50-414/81-09 on 810519-22.No Noncompliance Noted
ML20005B552
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 06/10/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML20005B553 List:
References
NUDOCS 8107080363
Download: ML20005B552 (2)


See also: IR 05000413/1981009

Text

,

e

,

UNITED STATES

8% '

'$

NUCLEAR REGULATORY COMMISSION

c

REGION 11

g

.., [

101 MARIETTA ST., N.W., SUITE 3100

p

ATLANTA, GEORGIA 30303

JUN 10 ism

"***

D([

'

Duke Power Company

ATTN:

Mr. W. O. Parker, Jr.

{

9

191 b-(.

h

Vice President, Steam Proauction

Charlotte, NC 28242

-

g O'I Op. S--

P. O. Box 2178

,

Si

Gentlemen:

S

6

h

,j

Subject: Report Nos. 50-413/81-09 and 50-414/81-09

O

This refers to the routine safety inspection conducted by Mr. J. R. Harris of

this office on May 19-22, 1981, of acti'.ities authorized by NRC Construction

Permit Nos. CPPR-116 and CPPR-117 for the Catawba facility and to the discussion

of our findings held with Mr. D. G. Beam, Project Manager, at the conclusion of

the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no violations or deviations were disclosed.

We have examined actions you have taken with regard to previously reported unre-

solved items. The status of these items is discussed in the enclosed inspection

report.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this

letter and the enclosed report will be placed in the NRC's Public Document Room.

If the report contains any information that you believe to be exempt from disclo-

sure under 10 CFR 9.5(a)(4), it is necessary that you: (a) notify this office by

telephone within ten days from the date of this letter of your intention to file

a request for withholding; and (b) submit within twenty-five days from the date

of this letter a written application to this office to withhold such information.

If your receipt of this letter has been delayed such that less than seven days

are available for your review, please notify this office promptly so that a new

due date may be established. Consistent with section 2.790(b)(1), such applica-

~

tion must be accompanied by an affidavit executed by the owner of the information

which identifies the document or part thereof sought to be withheld, and a full

statement of the reasons on the basis of which it is claimed that the information

should be withheld from public disclosure.

This section further requires the

statement to address with specificity the considerations listed in 10 CFR 2.790-

(b)(4). The information sought to be withheld shall be incorporated as far as

T 60 !

.s

7 8107080363 810610

OPDR ADOCK 05000413

dG

PDR

,

..

>

.

J':N 10 test

Duke Power Company

2

possible into a separate part of the affidavit. If we do not hear from you in

this regard within the specified periods noted above, the report will be placed

in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

.

T. [.S. .

C

s, Acting Director

Divis en of Resident and

Rear. tor Proje::t Inspection

- Enclosure:

Inspection Report Nos. 50-413/81-09

and 50-414/81-09

-

cc w/ encl:

- J. W. Hampton, Station Manager

D. G. Beam, Project Manager

.

.