Advises That Util 810528 Request for Extension of Implementation Date for Automatic Initiation of Auxiliary Feedwater Flow at Facility Is Unnecessary.Application for Tech Spec Change Re Surveillance Requirements Required
ML20004D216
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 05/29/1981
From: Clark R
Office of Nuclear Reactor Regulation
To: Lundvall A
BOSTON EDISON CO.
References
NUDOCS 8106080615
Download: ML20004D216 (2)


Text

.i ym

"'g))

4

_S UNITED STATES 3 %j% e( [,gy ' " f,4 y NUCLEAR REGULATORY COMMISSION WASHINGTO N, D. C. 20555

  • NM

[. *#g

,,\\

May 29, 1981 A'Ni Docket tios. 50-317 N

[y //

and 50-318 6

mgy 4

%l%;'fjg /

1lgg

3 Mr. A. 5. Lundvall, Jr.,

3, Vice President - Supply Baltimore Gas & Electric Company P.O. Box 1475 W'

r\\'\\

Baltimora, Maryland 21203

Dear Mr. Lundvall:

By letter dated May 28, 1981, you requested an extension of the implementa-

. tion date for automatic initiation of auxiliary feedwater (AFW) flow at Calvert Cliffs iluclear Power Plant, Units fio, 1 and 2.

The requested ex.

tension is from.the effective date of Amendments 54 and 37 for Units fio. I and 2, respectively, from June 1, 1981 to June 15, 1981.

Your requesting letter and conversations with your staff indicate the schedular problem has been the analysis necessary to determine the specific position of the AFW steam generator throttling valves needed to provide the correct AFW flow as a function of system parameters.

It is cur under-standing that the AFW pumps have been set to automatically start for con-siderable time. The. control room operator needs only to open the remotely operated thrntling valves to get AFW into a steam generator. We further understand that the Surve'illance Requirements (SR) imposed by Amendments 54 and 37 will be fully implemented by June 1, 1981.,.,

After careful review of the Technical Specifications (TS), we find no re-quirement for a specific AFW flow or for any SR to insure the proper setting of the AFW throttle valves. We consider this a deficiency in the TS for your facility in light of the effort required to determine the correct AR!

l flow to each steam generator.

Therefore, you are re:;uested to provide an application for TS changes to specify LC0(s) and SR(s) as needed within 60 days after receipt of this letter.

9ased en the above, we hereby declare your request for an extension of the subject implementation date unnecessary. This declaration was discussed with your Mr. W. Holston at 8:30 a.m. on May 29, 1981.

It has also been dis-cussed with and agreed to by the IE Resident Inspector.

Sincerely,

[RobertA. Clark, Chief Lu Operating Reactors Branch #3 Division of Licensing gggn gngpg cc:

See next page FUUH Unlu! da 8106 0 80le/5

k Baltimore Gas and Electric Company cc:

James A. Biddison, Jr.

Ms. Mary Harrison, President Calvert County Board of County Commissioners ieneral Counsel Saltimore Gas and Electric Company Prince Frederick, MD 20768 P. O. Box 1475 U. S. Environmental Protection Agency Baltimore, MD 21203 Region III Office George F. Trowbridge, Esquire Attn:

EIS Coordinator Shaw, Pittman, Potts and Trowbridge Curtis Building (Sixth Floor) 1800 M Street, N. W.

Sixth and Walnut Streets Washington, D. C.

20036 Philadelphia, PA 19106 Mr. R. C. L. Olson, Principal Engineer Mr. Ralph E. Architzel Nuclear Licensing Analysis Unit Resident Reactor Inspector Baltimore Gas and Electric Company NRC Inspection and Enforcement Room 922 - G&E Building P. O. Bos 437 P. O. Box 1475 Lesby, MD 20657 Baltimore, MD 21203 Mr. Charles B. Brinkman Manager - Washington Nuclear O'perations Mr. Leon B. Eussell.

4 Plant Superintendent Combustion Engineering, Inc.

Calvert Cliffs Nucledar Power Plant 4853 Cordell Avenue, Suite A-1 Maryland Routes 2 & 4 Bethesda, MD 20014 Lusby, MD 20657 Mr. J. A. Tierman, Manager Bechtel Power Corporation Nuclear. Power Department Attn:

Mr. J. C. Judd Calvert Cliffs Nuclear Power Plant Chief Nuclear Engineer Maryland Routes 2 & 4 Lusby, MD 20657 15740 Shady Grove Road e

Gaithersburg, MD 20760 Director, Griteria and Standards Division Combustion engineering, Inc.

Office of Radiation Programs ( ANR-460)

Attn:

Mr. P. W. Kruse, Manager U. S. Environmental Protection Agency Engineering Services Washington, D. C.

20460 P. O. Box 500 Windsor, CT 06095 Mr. W. J. Lippold, Supervisor Nuclear Fuel Management Public Docunent Room Baltimore Gas and Electric Company Calvert County Library Calvert Cliffs Nuclear Power Plant Prince Frederick, MD 20678 P. O. Box 1475 Baltimore, Maryland 21203 Director, Department of State Planning 301 West Preston Street Mr. R. E. Jenton, General Supervisor Baltimore, MD 21201 Training & Technical Services Calvert Cliffs Nuclear Power Plant Mr. R. M. Douglass, Manager Maryland Routes 2 & 4 Quality Assurance Department-Lusby, MD 20657 Fort Smallwood Road Complex P. O. Box 1475 h

Baltimore, MD 21203 n

P.r. T. L. Syndor, General Supervisor Administrator, Power Plant Siting Procram Operations Quality Assurance Energy and Coastal Zone Administration R.,;. : Cli f f 3.:aclue N.iar Plant Departmen', Of *?ataral Rescarces Maryland Routes 2 & 4 Tawes State Office Building Lusby, MD 20657 Annapolis, MD 21204

.