Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-508/80-10 & 50-509/80-10.Addl Info Requested Re Incorporation of ANSI Equipment Storage Requirements
ML20003G711
Person / Time
Site: Satsop
Issue date: 01/08/1981
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Mcelwee F
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML20003G631 List:
References
NUDOCS 8104300576
Download: ML20003G711 (2)


See also: IR 05000508/1980010

Text

{{#Wiki_filter:'o UNITED STATES ef . -

'! NUC EAR REGULATORY COMMISSION g

  • ,*[[-

e. s REGION V i.[4 [ 1000 N. CALIFORNIA BOULEVARD e SUITE 202, WALNUT CREEK PLAZA '

  • ,,,e

WALNUT CREEK, CALIFORNIA 94596 V .iiun E "r" ' Docket flos. 50-508, 50-509 Washington Public Power Supply System P. O. Box 968 Richland, Washington 99352 Attentio.i: Mr. F. D. McElwee HilP-3/5 Program Director References: (1) WPPSS Letter from F. D. McElwee to G. S. Spencer dated Novemoer 21, 1980,110. G03-80-2965 (2) IIRC Letter from G. S. Spencer to R. L. Ferguson dated Octooer 21,1980 Gentlemen: Thank you for yoin letter, Reference (1), responding to the item of noncompliance provided to you by Reference (2). Cur review of the information presented in your letter indicates that there may oe a misunderstanding concerning the cause of the item of noncompliance. Consequently, we need additional information to permit our assessment of your corrective actions. According( pursuant to Section 2.201 of the ilRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, you are required to submit to this office, within twenty-five (25) days of the date of this letter, a written statement or explanation addressing the following questions regarding the finding and the incorporation of AtiSI equipment storage requirements into contractor procedures. 1. As indicated in IE Inspection Report flo. 50-508, 509/80-10 which accompanied the subject flotice of Violation, site records showed that the charging pump storage requirements detailed by Peter Kiewit , Sons' procedure were being met. However, this procedure failed to - establish adequato measures to maintain final location storage conditions within the standards invoked by the contract specification; namely, the A!!SI il45.2.2-1972 standard. Uhat specific actions have been taken to ensure that the Peter Kiewit Sons' maintenance procedure , f adequately incorporates the specific storage requirements of l AflSI !!45.2.2-19727 l 2. What specific actions have been taken, or will be taken, to ensure that l other contractors responsible for the storage and maintenance of Quality i l l , t 8104300fh ' -. - -

. - - y ,_ ~ Washington Public Power -2- JAj; g ,,,, Supply System -- Class 1 equipment have procedures which adequately incorporate the specific requirements of industry standards invoked by the contract specification? Please contact us if you have any questions regarding the above. Your cooperation is appreciated. < Sincerely, LLL- G. S. Spencer, Chief P.eactor Construction and Engineering Support Branch cc: . M. E. Witherspoon, Division Manager Quality Assurance, WFPSS D. E. Dobson, Division Manager WNP-3/5,WPPSS . --w w,, -y - , , , - -,-- - ---7, , .~ .g,-g - -- +-----n-- }}