l OPERATING DATA REPORT DOCKET NO. 50-346 DATE November 7, 1980 COMPLETED BY Bilal Sarsour 1
TELEPHONE (419) 259-5000, Ext. 251 OPERATING STATUS
- 1. Unit Name:
Davis-Besse Unit 1 Notes
- 2. Reporting Period:
Oc tober, 1980
- 3. Licensed Thermal Power (51Wt):
2772
- 4. Nameplate Rating (Gross SlWe):
925
- 5. Design Electrical Rating (Net SlWe):
906
- 6. Maximum Dependable Capacity (Gross SlWe):
934
- 7. Maximum Dependable Capacity (Net MWe):
890
- 8. If Changes Occur in Capacity Ratings (!! cms Number 3 Through 7) Since Last Report. Give Reasons:
- 9. Power Level To Which Restricted. If Any (Net SlWe):
- 10. Reasons For Restrictions. If Any:
)
This Month Yr to-Date Cumulative
!!. Hours in Reporting Period 745 7,320 27,845
- 12. Number Of Hours Reactor Was Critical 0
2.078 13.042 gl
- 13. Reactor Resene Shutdown liours 0
0 2,875.8
- 14. liours Gencrator On-Line 0
2.008.7 11.883
- 15. Unit Reserve Shutdown Hours 0
0 1,728
- 16. Gross Thermal Energy Generated (MWil) 0 4,687,305 24,886,812 l
- 17. Gross Electrical Energy Generated (MWil) 0 1,583,559 8,307,070
- 18. Net Electrical Energy Generated 15thil) 0 1.483.787 7.654.365
- 19. Unit Senice Factor 0
27.4 43.2
- 20. Unit Availability Factor 0
27.4 49.9
- 21. Unit Capacity Factor tUsing MDC Net) 0 22.8 32.9
- 22. Unit Capacity Factor (Using DER Net) 0 22.4 32.3
- 23. Unit Forced Outage Rate 0
14.3 25.6
- 24. Shutdowns Scheduled Oser Next 6 Months IT pe. Date.and Duration of Each):
3
- 25. If Shut Down At End Cf Report Period. Estimated Date of Startup:
November 6.1980
- 26. Units In Test Status iPrior to Commercial Operation):
Forecast Achiesed INITIA L CRITICALITY INITITL ELECTRICITY CO\\tMERCI \\ L OPER ATiON 810 2 0 3 0 G.86 -