e Rev. 1 - 1/22/81 OPERATING DATA REPORT DOCKET NO.
50-346 DATE July 6, 1980 COMPLETED BY Bilal sarsour TELEPHONE 259-5000 ext. 251 OPERATING STATUS
- 1. Unit Name:
Davis-Besse Unit #1 Notes
- 2. Reporting Period:
June, 1980
- 3. Licensed Thermal Power IMW ):
925
- 4. Nameplate Rating (Gross MWe):
- 5. Design Electrical RatingiNet MWe):
906
- 6. Masimum Dependable Capacity (Gross MWe):
934
- 7. Maximum Dependable Capacity (Net MWe):
890
- 8. If Changes Occur in Capacity Ratings (items Number 3 Through 7) Since Last Report. Give Reasons:
- 9. Power Lese! To Which Restricted. If Any (Net MWe):
- 10. Reasons For Restrictions. If Any:
This Month Yr to-Date Cumulatise II. Hours In Reporting Period 720 4,367 24,892
- 12. Number Of Hours Reactor Was Critical 0
2,078 13,042 1l
- 13. Reactor Resene Shutdown Hours 0
0 2.875.8
- 14. Hours Generator On Line 0
2,008.7 11,883.0
- 15. Unit Reserve Shutdown Hours 0
0 1,728
- 16. Gross Thermal Energy Generated (MWH) 0 4.687.305 24,886,812
- 17. Gross Electrical Energy Generated (MWii)
O 1.583,559 8.307.070
- 18. Net Electrical Energy Generated (MWH) 0 1,483,787 7.654.365
- 19. Unit Senice Factor O
46.0 48.8
- 20. Unit Asailability Factor 0
46.0 56.4
- 21. Unit Capacity Factor (Using MDC Net) 0 38.2 37.1
- 22. Unit Capacity Factor iUsing DER Net) 0 37.5 36.4
- 23. Unit Forced Outage Rate 0
14.3 25.6
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Each):
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
July 28, 1980
- 26. Units in Test Status iPrior to Commercial Operation):
Forecast Achiesed INITIA L CRITICALITY INITIAL ELECTRICITY COMM ERCI A L OPERATION I
(4/77) 810 2 0 3 0 %g
~
-