Forwards IE Insp Rept 50-346/80-30 on 801112-14 & Notice of Violation
ML20002D674
Person / Time
Site: Davis Besse 
Issue date: 12/19/1980
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Crouse R
TOLEDO EDISON CO.
Shared Package
ML20002D675 List:
References
NUDOCS 8101210650
Download: ML20002D674 (2)


See also: IR 05000346/1980030

Text

p ' tr

.-

0

UNITED STATES

-

8

NUCLEAR REGULATORY COMMISSION

'S

$

n

e

4

O

"*

't

'

a

9 s

REGION ill

c_

'

'#

' o

799 ROOSEVELT ROAD

]

'Q

-

o

GLEN ELLYN, ILLINOIS 60137

-f:C)

.

,

r',

J-

.g$i:0

>

t

December 19, 1980

,

_ j'

2

apa

rSi

=

-=>

,;g

R

(s

d?c

Docket No. 50-346

F"

Toledo Edison Company

ATTN:

Mr. Richard P. Crouse

Vice President

Nuclear

Edison Plaza

300 Madison Avenue

Toledo, OH 43652

Gentlemen:

This refers to the inspection conducted by Messrs. N. C. Choules and

D. L. Robinson of this office on November 12-14, 1980, of activities

at the Davis-Besse Nuclear Power Station, Unit 1, authorized by NRC

Operating License No. NPF-3 and to the discussion of our findings with

Mr. T. Murray and others at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

During this inspecticn, certain of your activities appeared to be in non-

compliance with NRC requirements, as described in the enclosed Appendix A,

and a written response is required.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,

and your response to this letter will be placed in the NRC's Public Document

Room, except as follows.

If the enclosures contain information that you or

your contractors believe to be proprietary, you must apply in writing to

this office, within twenty-five days of the date of this letter, to withhold

such information from public disclosure. The application must include a full

statement of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

.

e

.

8101210 $ 70;

.

---

.

.

.

Toledo Edison Company

-2-

December 19, 1980

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

9

. F. lleishman, Chief

Reactor Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-346/80-30

cc w/encls:

T. D. Murray, Station

Superintendent

Central Files

Reproduction Unit NRC 20b

AEOD

Resident Inspector, RIII

PDR

Local PDR

NSIC

TIC

1[arold W. Kohn, Power

Siting Commission

Helen W. Evans, State of Ohio

.

h

a