ML19354D616

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/89-31 & 50-425/89-36 on 891030-1103 & 1113-17.Violations Noted.Major Areas Inspected:Inservice Testing,Complex Surveillance & Action on Previous Insp Findings
ML19354D616
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 12/11/1989
From: Belisle G, Scott Sparks, Tingen S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19354D617 List:
References
50-424-89-31, 50-425-89-36, NUDOCS 8912280244
Download: ML19354D616 (15)


See also: IR 05000424/1989031

Text

,

'

.

.

'

gNeMits,q'o,

UNITED si ATES

l:

NUCLEAR REGULATORY COMMIS$10N

~

f

-

REoloN 11

g

101 MARIETTA STREET.N.W.

't

ATLANT A, CEORGI A 30323

    • .

f

.....

Report Nos.:

50-424/89-31 and 50-425/R9-36

Licensee:

Georgia Power Company

P. O. Box 1295

Birmingham, AL 35201

Docket Nos.:

50-424 and 50-425

License Nos.:

NPF-68 and NPF-81

Facility Name:

Vogtle 1 and 2

Inspection Conducted:

October 30 - November 3, 1989 and November 13-17, 1989

Inspectors:

Mali

d

11hlM

5. Tihgen

9

Date Signed

Ae e .2 L

n<

h Io h ')

5. Sparks

Date Sig'ned

Approved by:

b

L

CT

/A[r /fT[

G. A. Belisler Chief

Date Signed

~

Test Programs Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, announced inspection was conducted in the areas of inservice

testing, complex surveillance, and action on previous inspection findings.

Results:

The licensee's RHR system IST program appeared to be adequate to ensure that

the system's components are maintained in an operational readiness state,

paragraphs 2 through 7.

A weakness was identified in the area of check valve

full stroke testing, which indicated the licensee's review of Generic Letter 89-04 was not thorough, paragraph 4.

An unresolved item was identified in the

area of pressurizer safety valve setpoint testing, paragraph 6.

A violation

was identified for inadequate complex surveillance testing, paragraph 8.

8912280244 891219

PDR

ADOCK 05000424

Q

PDC

j

.

,

,

i

-

.

.

.

.'

.

l

l

1

I

'

REPORT DETAILS

1

1.

Persons Contacted

Licensee Employees

'

  • J. Aufdenkampe, Technical Support Manager
  • G. Bockhold, Jr., General Manager. Vogtle Nuclear Operations
  • J. Churchwell, Senior Engineer
  • G. Frederick, Quality Assurance Site Manager
  • H. Handfinger, Maintenance Manager
  • M. Hickox, Senior Plant Engineer
  • M. Hobbs, Instrument and Control Superintendent
  • S. Kitchens, Assistant General Manager, Operations
  • A. Mosbaugh, Assistant General Manager, Plant Support
  • L. Noblett,

Instrument and Control foreman

  • J. Swartzwelder, Operations Manager

,

  • J. Williams, Plant Engineering Supervisor

i

Other licensee employees contacted during this inspection included

<

craftsmen,

engineers,

operators,

mechanics,

technicians,

and

administrative personnel.

NRC Resident Inspectors

R. Aiello, Resident Inspector

  • J. Rogge. Senior Resident Inspector

D. Starkey, Resident Inspector

  • Attended exit interview

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2.

Inservice Testing Introduction (73756)

10 CFR S0.55a(g) and TS Surveillance Requirement 4.0.5 require that ASME

Code Classes 1, 2, and 3 pumps and valves be inservice tested in

accordance with Section XI of the ASME Boiler and Pressure Vessel Code.

Section XI specifies rules and requirements for IST to assess operational

readiness of certain Classes 1, 2, and 3 pumps and valves which are

required to perform a specific function in shutting down a reactor to the

cold shutdown condition, in mitigating the consequences of an accident or

in providing over pressure protection.

Plant Vogtle is required to follow

the requirements of ASME Code,Section XI, 1983 Edition through the Summer

1983 Addenda.

During this inspection, the inspectors reviewed the

licensee's Inservice Test Program, implementing procedures, and test

c

.

'

I-

,.

results that accomplish Section XI pump and valve IST.

The results of

i

this review are stated in paragraphs 3 through 7.

Pumps and valves that

are in the RHR system or interface with the RHR system, pressurizer safety

valves, and PORVs were reviewed during this inspection.

3.

PumpTesting(73756)

i

The inspectors reviewed IST of RHR pumps A and B for each Unit to

determine whether testing was performed in accordance with Section XI,

Subsection IWP requirements.

The following RHR IST implementing

.

procedures and test results for the previous two year period were

,

reviewed:

14805-1, Rev. 8. Residual Heat Removal Pump and Check Valve IST

14805-2, Rev. 3. Residual Heat Removal Pump and Check Valve IST

In general, inspection results indicated that Code requirements were

i

satisfied in the areas of testing frequency, establishing new reference

values, post-maintenance testing, and evaluation of test results.

In

addition, the inspectors verified that testing was performed with

calibrated instrumentation.

The inspectors also reviewed and witnessed the performance of the

following pump IST procedures:

14801-2, Rev. 1

NSCW Transfer Pump Inservice Test

14808-2, Rev. 4,

Centrifugal Charging Pump and Check Valve

Inservice Test

14807-2, Rev. 2,

Motor Driven Auxiliary Feedwater Pump Inservice

Test

14804-1, Rev. 7

Safety Injection Pump Inservice Test

The inspectors verified that the above procedures accomplished testing in

accordance with Code requirements.

Test personnel were observed to be

knowledgeable of Section XI Code requirements, acceptance criteria,

precautions and limitations, and adhered to the appropriate procedure

during performance of the test.

Test data was measured with calibrated

instrumentation, and results were properly evaluated.

i

Within the areas inspected, no violations or deviations were identified.

4.

Check Valve Full Stroke and Reverse Flow Testing (73756)

The inspectors reviewed the full stroke and reverse flow IST methods and

,

!

results obtained during the previous two year period for the following

l

check valves for each unit:

l

1-1205-U4-122

1-1205-U4-123

1-1205-U6-001

1-1206-U6-002

1-1205-06-009

1-1205-U6-010

l

l-1204-U4-143

1-1204-U4-144

1-1204-U4-145

l

l

l

p

,

'

'

.

,

'

..

,

!

3

i

,1-1204-U4-146

1-1204-U6-079

1-1204-U6-080

1-1204-U6-081

1-1204-U6-082

1-1204-U6-128

1-1204-U6-129

1-1204-06-147

1-1204-U6-148

1-1204-06-149

1-1204-06-150

The inspectors reviewed the following Unit 1 (corresponding procedures

were reviewed for Unit 2 testing) procedures which performed IST on the

above check valves:

14896-1, Rev. 2,

ECCS Check Valve Cold Shutdown Inservice Test

14895-2, Rev. 3

ECCS Check Valve Refueling Inservice Test

14805-1, Rev. 8,

Residual Heat Removal Pump and Check Valve IST

28716-C, Rev. 5,

Westinghouse Style

"B"

Check Valves

151

Surveillance

Requirements for full stroke and reverse flow exercising check valves are

contained in Section XI, Subsection IWV-3522 of the Code.

The inspectors reviewed testing frequencies, results, and appropriate

relief requests for the above check valves.

In addition, where full

stroke testing was performed, the inspectors verified that flow rates were

specified by procedure and were greater than design accident flow rates.

GL 89-04, Guidance on Developing Acceptable Inservice Testing Programs,

dated April 3,1989, provides NRC staff positions on IST.

The licensee

stated that a review of the GL 89-04 positions had been performed, and

that current IST was in accordance with these positions.

In addition,

since an SER, dated March 1987 (and approvals of subsequent revisions to

the IST Program), had been received, current testing was considered

acceptable.

However, the inspectors identified an area where current IST

wus not consistent with the potential generic deficiencies related to IST

programs and procedures as identified in GL 89-04.

GL 89-04 addresses

full-stroking check valves, and states:

A valid check valve full-stroke exercise by flow requires that the

flow through the valve be known.

Knowledge of only the total flow

through multiple parallel lines does not provide verification of flow

rates through the individual valves and is not a valid full-stroke

exercise.

The following items were identified where check valve full stroke

exercising was not in accordance with GL 89-04:

Check valves 1204-04-143, 144, 145, and 146. The licensee describes

the alternate testing for these check valves in Relief Request RR-6,

which has been approved.

Discussions with licensee personnel

indicated that the purpose of RR-6 was to perform full stroke

exercising during refueling.

Alternate testing is performed

by procedures 14892-1 and 14892-2, in which a total flow from one

safety injection pump is compared to the system flow balance

requirements of TS to verify that these valves open to perform their

,

'

-

.,

.,

,

,

,.

.

.

4

'i

function. The licensee stated that failure of a single check valve to

full-stroke would be detected by a decrease in pump flow rate or an

. '

increase in discharge pressure.

However, the licensee could not

provide data to support the assumption that a check valve which only

partially strokes open would result in a detectable change in pump

discharge flow or pressure.

Check valves 1204-U6-147, 148, 149, and 150. The licensee describes

testing these c.eck valves in Cold Shutdown Justification CS-7.

CS-7

t

states that total flow from one RHR pump will be compared to the

,

system flow balance requirements of TS to verify that these valves

>

open to perform their function, and that inoperability of these check

valves to pass their required flow would be seen as reduced total

flow.

However, the licensee could not provide data to support the

!

assumption that a check valve which only partially strokes open would

result in a detectable change in pump discharge flow or pressure.

Based on the above two examples, the inspectors concluded that the

licensee's review of the positions and generic deficiencies related to IST

programs and procedures stated in GL 89-04 was not thorough in the area of

>

check valve full stroke exercising.

Licensee management orally committed

to perform an additinnal review of GL 89-04 and revise any implementing

procedures, as necessary, to comply with the GL 89-04 positions.

.'

The inspectors also reviewed calibration of instrumentation used to verify

check valve full stroking in which the design accident flow rate is used.

The inspectors questioned licensee personnel on the use and accuracy of a

clamp-on acoustic flow meter, used during procedures 14896-1 and 14896-2

to verify the flow rate through check valves 1204-06-128 and 1204-U6-129.

Review of the vendor manual for the acoustic flow meter indicated that the

instrument error is less than or equal to one percent.

The inspectors

,

i

consider the stated accuracy of the acoustic flow meter to be satisfactory

for verifying check valve full stroking.

The inspectors also reviewed check valve reverse flow testing, which is

,

l

required by the Code for check valves which perform a safety function in

the closed position.

Subsection IWV-3522 requires check valve testing in

!

a manner that verifies the disk travels to the seat on cessation or

l

reversal of flow.

Check valves 1204-06-079, 080. 081, and 082 are

l

disassembled and manually stroked each RF0 (one each refueling) on a

l

staggered test basis as stated in relief request RR-7.

The remaining

check valves are either PIVs, which are leak rate tested, or are

l

satisfactorily reverse flow tested in accordance with. Code requirements.

.

Within the areas inspected, no violations or deviations were identified,

i

l

I

_ _ _ _

_.

_

.. .

. . .

'

. . '

-

,;

,

5

- 5.

-PowerOperatedValveIST(73756)

The inspectors reviewed IST for the following MOVs and A0Vs in the Units 1

and 2 RHR and SI systems:

HV8804A

HV8804B

HV8716A

HV8717B

FV0610

FV0611

HV8812A

HV8812B

HV8811A

HV8811B

HV8840

HV8809A

HV8809B

HV0606

HV0607

FV0618

FV0619

4

The inspectors interviewed licensee personnel regarding the general

methods used ~ to stroke time power operated valves.

The inspectors

also reviewed appropriate relief requests, and reviewed the following

implementing procedures for IST of the previously listed valves:

14850-1, Rev. 11,

Cold Shutdown Valve Inservice Test

14825-1, Rev. 11,

Quarterly Inservice Valve Test

Criteria for IST power operated valves is contained in Subsections IWV

3412, 3413, 3415

and 3417 of the ASME Code.

These Subsections specify

stroke timing, fail-safe testing, and corrective action requirements.

The

inspectors verified that testing was performed in accordance with Code

requirements, and that testing data and subsequent corrective action was

satisfactory.

The inusctors also questioned che licensee on the need to fail-safe test

valve.

70606, HV0607, FV0618, and FV0619.

These valves are A0Vs which

contrt

a e RHR heat exchanger discharge flow and bypass flow, and have a

'

fail-seit position.

Subsection IWV-3415 provides the requirements for

testing valves with fail-safe actuators.

The licensee stated that the

normal position of these valves is the failed position and, as such,

consider these valves to be passive valves.

There are no exercising

requirements for passive valves and thus the inspectors had no further

questions.

Within the areas inspected, no violations or deviations were identified.

6.

Safety and Relief Valve IST (73756)

The. inspectors reviewed IST for the following safety and relief valves in

-Units 1 and 2 RHR system and reactor coolant system:

PSV8708A

PSV8708B

PSV8708C

PSV8010A

PSV8010B

PSV8010C

The inspectors interviewed licensee personnel regarding the methods used

to test relief valves and reviewed the following implementing procedures

for IST of the previously listed valves:

..

.

l,_

/

,.-

.

6

28211-C, Rev. 2, RHR Suction Relief Valve Test

28215-C, Rev.1. Pressurizer Code Safety Valve Setpoint Verification

WYLE Laboratories Test Procedure No. 1032, Rev. A, Testing of Crosby

Model HB and HB-BP Safety Valves at Non-elevated Temperature

WYLE Certification Test Report 48136-01

The criteria for IST of relief valves and safety valves are contained in

-Subsections IWV 3511, 3512, and 3513 of the ASME Code, and in Performance

and Test Code ANSI /ASME-PTC 25.3-1976, Safety and Relief Valves, which

specify testing methods and frequency. TS 3/4.4.2 specifies a PSV setpoint

tolerance of 2485 plus/minus one percent psig.

Section .01 of ANSI /ASME-PTC 25.3-1976 states that if the temperature of

the medium used to test the valve differs substantially from the

temperature to which the valve is subjected while in service, the opening

and closing pressures as well as the blowdown will be different fro.n the

test pressures, and it is necessary to develop appropriate corrections for

the valve under test to account for these differences which are outside the

scope of the code.

Vogtle PSVs are installed on uninsulated loop seals. The exact

temperature of the loop seals is unknown.

Discussions with the licensee

indicated that loop seal temperatures are somewhere between 120 and 200'F,

and that ambient temperature was approximately 140*F.

Prior to Units 1

and 2 respective startups, all six PSVs were setpoint tested at WYLE

Laborat,ories.

The valves were tested with steam at approximately 650 F.

During the WYLE tests, the PSV bonnet temperature was maintained at

approximately 140 F.

The PSV body temperature was also measured with a

lower limit of 200"F required to commence testing; no upper limit for body

temperature was established.

Review of the WYLE setpoint test results

indicated that the valve's body temperature was never allowed to stabilize.

Once body temperature reached 200 F, WYLE coninenced setpoint testing.

In

all cases body temperature increased as setpoint testing progressed.

For

the six PSVs tested, body temperatures ranged from a low of 218*F to a

high of 385 F when satisfactory setpoints were obtained.

During the previous Unit 1 RF0, PSV8010A was setpoint tested in place

utilizing a pressure assist device.

In order to perform this testing the

loop seal was drained by opening the loop seal drain / fill valve for

approximately one minute.

Within two to five minutes after draining the

loop seal, the valve was setpoint tested. During the following 15 minutes,

the valve was setpoint tested a total of eight times.

During the inplace

testing, the valve and loop seal temperatures were not monitored.

The

inplace setpoint results wandered somewhat and required two adjustments to

obtain two consecutive setpoints in the middle of the tolerance band. The

initial setpoint obtained during the inplace testing (2507 psig) was close

to the WYLE as-left setpoint (2506 psig) obtained prior to Unit 1

Etartup.

-

--

,

.

.

.

'

'

'

l

7

The inspectors had the following questions regarding Vogtle PSV setpoint

test methods:

During WYLE testing, body temperatures were not allowed to stabilize.

~

During normal plant operation, the PSV's body temperature is stable.

Does WYLE testing at unstabilized body temperatures provide accurate

setpoints?

What effect does valve lower body temperature have on setpoint?

During the WYLE testing, body temperature was as high as 385'F. The

exact body temperature at normal operation is unknown, but could be

as low as 120-140 F.

During the inplace testing conducted on Unit 1 valve PSV8010A, was

the valve body temperature stable, and did the valve heat up after

draining the loop seal?

During the inplace testing conducted on Unit 1 valve PSV8010A, did

.the loop seal remain filled with steam in lieu of being partially

filled with water?

During the inplace testing conducted on Unit 1 valve PSV8010A, the

valve was setpoint tested eight times in approximately 15 minutes.

Was valve temperature stable during these consecutive lifts?

In response to these questions the licensee and inspectors disagreed with

the validity of the present PSV setpoints being in the TS allowed

tolerance range. The licensee considers that (1) based on discussion with

Crosby, valve bonnet temperature and not valve body temperature has the

major effect on valve setpoint, therefore WYLE setpoint testing was valid,

and (2) during the inplace testing conducted on valve PSV8010A, the valve

was at normal operating temperature; therefore, because the WYLE and

inplace test results were identical,-no temperature correction factors were

required. During the upcoming Unit 2 RF0 the licensee will be required to

perform PSV setpoint testing.

The licensee agreed to verify that no

temperature correction is required uue to the differences in temperature

between test mediums and normal service medium during this testing. This

issue was identified as URI 50-424/89-31-02 and 50-425/89-36-02.

WYLE test results contained graphs of valve inlet pressure and

corresponding disc lift versus time for each setpoint test. The inspectors

had the following questions pertaining to these graphs:

Why did set pressure occur prior to disc lift?

In some instances, prior to the full gagged disc lift, there was a

disc lift of a much smaller magnitude. What was cause of the smaller

magnitude disc lift?

How does WYLE setpoint testing and the pressure assist device

setpoint test method utilized during the previous Unit 1 RF0

differentiate between opening pressure and simmer?

i

.-

__

_. _ . _ _

_______ _ _._____________

______ _ ____

_

+

'

.

.

l

,.

.-

8

The licensee agreed to review this matter further to obtain answers to these

questions.

These questions were identified as IFIs 50-424/89-31-03 and

50-425/89-36-03, and will be followed up on during a future inspection.

Review of RHR relief valve testing indicated that IST was accomplished in

accordance with the ASME Code.

Within the areas inspected, one unresolved item and one inspector

followup item were identified.

!

7.

LeakRateTesting(73756)

The inspectors reviewed local leak rate testing for the following PIVs in

the Units 1 and 2 SI system:

1-1204-U4-143

1-1204-U4-144

1-1204-04-145

1-1204-U4-146

1-1204-U6-079

1-1204-U6-080

1-1204-U6-081

1-1204-U6-082

1-1204-U6-128

1-1204-U6-129

1-1204-U6-147

1-1204-U6-148

1-1204-U6-149

1-1204-U6-150

,

The inspectors reviewed the following implementing procedures for IST of

the above valves:

14450-1, Rev. 7, RCS Pressure Isolation Valve Leak Test

14450-2, Rev. 2, RCS Pressure Isolation Valve Leak Test

Based on a review of procedures and results, the inspectors concluded the

fcilowing:

Adequate leak rate test procedures were developed and implemented,

and PIVs were correctly identified in the IST Program.

PIV leak rate tests were performed by acceptable methods at the

!

required frequency.

Leak rates were satisfactory and were in agreement with the limits

established by TS 4.4.6.2.2 for PIVs.

PIV test data, taken at pressures below system functional pressure,

were adjusted properly in accordance with Section XI, Subsection

IWV-3423.

The inspectors identified a concern regarding procedures 14450-1 and

14450-2.

Specifically, these procedures contain a figure which is used to

correlate an indicated flow with an observed leak rate.

The inspectors

questioned the basis of the correlation,

i.e., why an indicated flow

needed to be adjusted to an observed leak rate. The licensee stated that

the leak rate is measured from flow elements 1FE-928 and 2FE-928.

An

Operations Deficiency Report, T-1-86-3320, was issued during Unit 1 pre-op

because the installation of IFE-928 did not meet ASME guidelines for

recommended minimum pipe lengths upstream and downstream of the orifice.

..

.

_ _ _ _ _ _

bi

l

'

t

..

.

.

F

.*

.

9

1

Interim resolution consisted of a special test of passing known flow rates

of water through 1FE-928 and observing the indicated flow. Data collected

would be used to develop a correction curve of actual versus indicated

flow rate.

The inspectors reviewed the results of the special test

and verified that the correction was incorporated into procedure 14450-1.

The licensee properly installed 2FE-928 (Unit 2); however, the same

correction was incorrectly used in procedure 14450-2.

The correction

factor was in the conservative direction, which added a maximum amount of

approximately 1.5 gpm to the indicated leak rate.

The correction for

small leak rates (less than 1 gpm) was less than 0.5 gpm.

The licensee

agreed to revise the Unit 2 procedure to remove the correction factor due

to the fact that no correction in the indicated flow rate as provided by

2FE-928 is needed.

Request for Engineering Review 87-0287 recommended

long term corrective action to rework flow element 1FE-928 to conform to

ASME guidelines, which the licensee will follow under Design Change

Request 90-047.

Within the areas inspected, no violations or deviations were identified.

8.

Complex Surveillance (61701)

TS Surveillance Requirement 4.4.4.1 required that each pressurizer PORV be

demonstrated oper ble at least once every 18 months by perfonning a

channel calibration and operating the valve through one cycle of full

travel.

The inspectors reviewed the following procedures that

accomplished this surveillance requirement:

VEGP 14861-1, Rev. 1,

PORV Cold Shutdown Inservice Test

VEGP 14600-2, Rev. 2,

ESFAS Slave Relay and Final Device Train A

Block Test

VEGP 24526-2, Rev. 1

Pressure Protection Channel II 2P-456 Analog

Channel Operational Test and Channel

Calibration

VEGP 24518-2, Rev. 1,

Reactor Coolant Pressure (Wide Range)

Protection

II

2P-403 Analog Channel

Operational Test and Channel Calibration

VEGP 24539-2, Rev. 2,

Pressurizer Pressure Control 2P-455 Channel

Calibration

The pressurizer PORV channel calibration was accomplished by performing a

series of overlapping procedures.

Results of the inspectors' review of

l

.the PORV channel calibration procedures was that the channel calibration

was not being properly performed, in that not all components in the

channels were tested.

NAS card 0936, K713 relay, and the contacts and

wiring that actuate when the K713 relay is energized were not tested.

These components are required to actuate to automatically open and close

the PORVs on high pressurizer pressure.

Failure to adequately test the

PORV circuitry in accordance with TS Surveillance Requirement 4.4.4.1 was

identified as Violations 50-424/89-31-01 and 50-425/89-36-01.

By

l

l

-

-

-

-

- -

-

-

.

,

4

, . -

.-

10

November 17, 1989, the licensee had satisfactorily tested the PORV channel

components that had previously been omitted.

The inspectors also reviewed procedure 24524-1, Rev. 10, RCS Wide Range

Pressure IP-418 Channel Calibration, which the licensee uses to satisfy TS

surveillance requirement 4.5.2.d.1.

This procedure verifies automatic

isolation and interlock action of the RHR system from the RCS.

The

inspectors verified that the procedure adequately tests and calibrates

each component in the loop such that with a pressure signal greater than

or equal to 377 psig, the interlocks prevent RHR valve HV8702A from being

opened, and with a pressure signal less than or equal to 750 psig, the

interlocks will cause HV8702A to automatically close.

Within the areas inspected, one violation was identified.

9.

Action on Previous Inspection Findings (92701, 92702)

a.

(Closed) Inspector Followup Item 50-424/88-51-01, The Effect of

Temperature and Steam in Lieu of Water on PSV Setpoint.

This' item was discussed in paragraph 6 of this Inspection Report and

upgraded to an URI.

b.

(Closed) Inspector Followup Item 50-424/88-10-01, Torque Switch

Replacement.Due to Potential Roll Pin Failure.

During a previous inspection, the licensee committed to replace the

,

l

torque switch on the Unit 1 RER cold leg isolation valve 1HV8716B.

The commitment to replace the torque switch was primarily based on a

torque switch roll pin failure that occurred on 1HV8716B in October

L

1987 and a. subsequent failure of 1HV8716A in February 1988. The pin

l

failures were attributed to high unseating thrusts discovered during

'

the February outage, due to thermal binding.

The torque switch for

1HV8716A was replaced, holes drilled in the discs of valves 1HV8716A

and B to alleviate thermal binding, and 1HV8716B torque switch was

~

proven operable through diagnostic testing.

The most recent

diagnostic test again showed 1HV8716B torque switch to be operable;

therefore, the licensee does not intend to replace the torque switch

as previously committed,

c.

(Closed) Inspector Followup Item 50-425/89-11-01, M0V Fasteners with

less Than Full Thread Engagement.

This item identified M0V adapter to actuator and motor to actuator

fasteners that did not have full thread engagement.

The licensee

reviewed the valves identified with a thread engagement problem on

the adapter to actuator fasteners and actuator to valve fasteners and

determined that the bolting configurations were installed correctly.

The bolt lengths were verified based on vendor part numbers and field

walkdowns. The bolts that were threaded into the actuator housing or

adapter flanges did not utilize nuts.

The bolts had thread

,

3

(, _

.V

11

engagement equal to or greater than the thread engagement when using

a nut.

The licensee also reviewed the motor to actuator fasteners

using studs and nuts and determined that full thread engagement had

not been achieved.

To correct the situation the licensee added a

step to the maintenance checklist to check for full thread engagement

on Limitorque operators during the next maintenance cycle.

Within the areas inspected, no viciations or deviations were identified.

10. Exit Interview

The inspection scope and results were summarized on November 17, 1989,

with those persons indicated in paragraph 1.

The inspectors described the

areas inspected and discussed in detail the inspection results listed

above.

Proprietary information is not contained in this report.

Dissenting comments were received from the licensee in the area of PORV

logic circuitry testing, and PSV setpoint temperature correction factor.

The licensee stated that TS 4.4.4.1 did not require the PORV automatic

function to be verified as part of the performance of a channel

calibration, therefore, they were not in violation of TS 4.4.4.1.

In

addition, the licensee stated that based on inplant testing data for

their PSVs, the PSV setpoint temperature correction factor was a one to

one relationship, therefore, their setpoint test method was not a code

violation.

Subsequent to the inspection, the inspectors informed licer.see management

via telephone on November 29, 1989, that the issue of the PSV setpoint

temperature correction factor would be identified as an unresolved item in

lieu of a code violation.

The licensee management committed to an additional review of GL 89-04 and

revision of any implementing procedures, as necessary, to comply with the

GL 89-04 positions regarding IST.

Item Number

Description and Reference

424/89-31-01

Violation - Failure to Adequately Test

425/89-36-01

PORV Circuitry in Accordance with

TS 4.4.4.1

424/89-31-02

Unresolved Item - PSV Setpoint

425/89-36-02

Temperature Correction Factor

424/89-31-03

Inspector Followup Item - Questions

425/89-36-03

regarding WYLE Test Results

Licensee management was informed that the following items were closed:

IFI 50-424/88-51-01, paragraph 9.

IFI 50-424/88-10-01, paragraph 9.

IFI 50-425/89-11-01, paragraph 9.

!

r

-,

? 45

,4

,.

,

12

!

,-

11. Acronyms and Initialisms

!

'

ANSI

American National Standards Institute

A0V

Air Operated Valve

ASME

American Society of Mechanical Engineers

CFR

Code of Federal Regulations

CS

Containment Spray

'F

Degrees Fahrenheit

ECCS

Emergency Core Cooling System

i

ESFAS

Engineered Safety Features Actuation Signal

!

GL

Generic Letter

i

GPM

Gallons per Minute

IFI

Inspector Followup Item

ISI

Inservice Inspection

IST

Inservice Testing

LOCA

Loss of Coolant Accident

MOV-

Motor Operated Valve

NRC

Nuclear Regulatory Commission

NSCW

Nuclear Service Cooling Water

.

'

PIV

Pressure Isolation Valve

PORY

Power Operated Relief Valve

4

PSIG

Pounds per Square Inch, Gage

PSV

Pressurizer Safety Valve

i

'

RCS

Reactor Coolant System

RHR

Residual Heat Removal

!

REV

Revision

RF0

Refueling Outage

RR

Relief Request

SER

Safety Evaluation Report

SI

Safety Injection

TS

Technical Specifications

URI

Unresolved Item

,

!

VEGP

Vogtle Electric Generating Plant

i

,

....,,,,o..._

1e:42

m it. r uni n-si

......

..

t pape9

^

,

ENCLOSURE 3

'. ., 4

Novembec 15, 1989

MEMORANDUM FOR: D. 8. Matthews. Project Director (14H 25)

Pro'ett Ofrectorate 81 8

-

Div sten of Reacter Projects - t/!!

l

Robert C. Jones.BranchActing Chief

PROM:

Reactor Systems

Division of Systems Technology

V00118 UNIT 1 INTERPRITATION OF 78 3.4.4 LINITIN8

SUBJECT:

ett!0N FOR. OPERATION. AtLIEF VALVES

Plant Name

Vogtle Unit !

TACNe(s).:

728?1

DocketNe(s):

80-42d

Pro,4ect Directorate

ProjectDirectorate!!3

4ect Nanager:

J. NeDkins

Revlow Bronch:

SRX8/D87

'

Review Status:

Complete

In tele $one discussion en November 9.1989 the NRC Region !! Vogtle Unit 1

Senior tesident Inspector ($RI) and the licensee (Georgia Power Company)

requested an NRR position with regard to surveillance requirement 4.4.4

eddressing PORV testing. The issue is whether or not the automatic function of

the PORY need be testes in order to satisfy the requirements of TS 4.4.4.

In addition, the licensee stated its intent to pursue the ' automatic *

surveillance mode in January 1990 et their next block valve surveillance

intervs1.

PORY surveillance testing at the required

The licensee performed the 'menua18

interval. Nowever, the SRI interpreted the surveillance requirement to mean

The difference of the

that the ' Automatic" function should also be included.

two approaches means that a small portion of the circuitry is not tested.

(The valve is stroked in the manual mode.) However. if tne surveillance

requirement is intended to include the automatic sode and the estomatic

function is not tested then the PORVs should be declared inoperable. For

causes of inoperability other than excessive seat leekage, action statement "b'

epplies and the plant must shut down.

The licensee's interpretation is that the manual mode is adequate because:

action statement 'e' of this LC0 (if there was excessive seat leakage)

1.

would allow indefinite plant operation with both block valves closed

1.e.. without the PORY automatic function.

the langvege of the Vogtle FSAR Chapter 15 which does not require (nor

2.

use) the PO.RY automatie actuation and

Contact:

L. Lois. SRXB/ DST. x20890

.

I

. . . . - -. .-

. . . _ _ _ _ _ _ _ _ _ _ _ _ _

,y-.

11/16/e9

1e:43

HITE FLINT P1-37

to,003

003

o? g\\hh

.

.s

.

s

y

p. 8. Matthews

-

8-

'

3.

the fact that under severe accident conditions the p0RVs will be used in

the manual mode.

'

The reasons for their present avoidance of this test are:

(1)toavoidanother

PORV. streking, and (t) because the part of the circuit which has not been

tested is a passive circuit of very high reliability.

The staff's interpretation of the surveillance requirements are that the

eetonatic function of the PORVs must be assured oncept for esses of excessive

PORY seat leakage. This is because of the following safety considerations

-

associated with the automatic function:

(1)assurancethatthevalveswill

not open at er below normal primary system pressure (thus causing a small break

LOCA) and (t) sinialaing challenges to the pressuriser code safety valves.

With regard to the licensee's plan to continue operation satil January 1990

prior to testing the automatic function, we find this acceptable because:

11) the block valves are operable and can be closed in the event of an

onadvertentPORVepening.lt5thePORVsarenotdirectlycreditedinthe

..

licensee's safety analyses. (3) identical components have been recently

successfullytestedattheotherVogtleUnit,(4)theportionofthe

surveillance test performed covered the major parts of the cirevitry and the

mechanteel portion of the valve including the setpoints,llances.and(6)theItcensee

plans to include the automatic function in future survei

/s

Robert C. Jones.BranchActing Chief

Reactor Systems

Division of Systems Technology

.

k

.

.