ML19353A346
| ML19353A346 | |
| Person / Time | |
|---|---|
| Site: | Summer |
| Issue date: | 10/06/1980 |
| From: | Robert Lewis NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Nichols T SOUTH CAROLINA ELECTRIC & GAS CO. |
| Shared Package | |
| ML19353A343 | List: |
| References | |
| NUDOCS 8101080233 | |
| Download: ML19353A346 (2) | |
See also: IR 05000395/1980025
Text
'
- pa stro
o
UNITED STATES
!" 3 gf[ g
NUCLEAR REGULATORY COMMISSION
-
W-
a
REGION il
6
-kkg
f
101 MARIETTA ST N W,. sulTE 3100
- ... f
V
ATL ANTA, G EoRGI A 3o3o3
In Reply Refer To:
OCT 0 61980
RII:JLS
50-395/80-25
South Carolina Electric and Gas Company
ATTN:
T. C. Nichols, Jr., Vice President
Power Production and Systems Operations
P. O. Box 764
Columbia, SC 29218
Gentlemen:
This refers to the inspection conducted by J. L. Skolds of this office on July 21,
through August 31, 1980 of activities authorized by NRC Construction Permit No.
CPPR-94 for the V. C. Summer facility, and to the discussion of our findings
held with 0. S. Bradham at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously identified
enforcement matters.
The a are discussed in the enclosed inspection report.
During the inspection, it was found that certain activities under your license
appear to be in acacompliance with NRC requirements. Tbis item and references
to pertinent requiremeni.s are listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions.
Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure.
Any such application must
include a full statement of the reasons on the basis of which it is claimed that
the information is proprietary, and should be prepared so that proprietary infor-
mation identified in the application is contained in a separate part of the
document.
If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
.
8101080233
___
p
.
%
South Carolina Electric and
-2
OCT 0 6 iS60
Gas Company
,
Should you have any questions concerninj this letter, we will be glad to discuss
them with you.
Since rely,
. t !.
. C.
zwis, Acting Chief
Reactor Operations and Nuclear
Support Branch
Enclosure:
Appendix A, Notice of Violation
cc w/ encl:
A. A. Smith, Site QA Coordinator
T. B. Conners, Jr.
O. S. Bradham, Manager
Nuclear Operations
,