Forwards IE Insp Rept 50-267/80-21 on 801001-31 & Notice of Violation
ML19353A117
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 11/14/1980
From: Madsen G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Millen C
PUBLIC SERVICE CO. OF COLORADO
Shared Package
ML19353A118 List:
References
NUDOCS 8101070215
Download: ML19353A117 (2)


See also: IR 05000267/1980021

Text

CEtlTRAL FILES

POR:HQ

g m,'er

UNITED STATES

(pDR

g

[.~

+- $

NUCLEAR REGULATORY COMMISSION

M

1

i

k^

dh!f

REGION IV

1 'r

E

?,

-

511 RYAN PLAZA DRIVE. SUITE 1000

I

STATE

%,, ,,#

ARLINGTON. TEXAS 76011

Novemoer 14,198u

)

,-i

In Reply Refer To:

1

Occket No. 50-267/80-21

~

>

U

~,

v

1

,

m

J

k

Public Service Company of Coloraco

Attn:

Mr. C. X. Millen

Senior Vice President

P. G. Box 840

Cenver, Colorado 80201

Gentlemen:

This refers to the inspection conducted under the Resident Inspection Program

by Messrs. M. W. Dickerson and R. E. Collins of this office during the period

October 1-31, 1980, of activities authori::ed by NRC Operating License No. CPR-3a

and to their discussions of the findings with members of your staff at the

conclusion of the inspection.

Areas examined during this inspection are described in our report, which is

enclosed with this letter.

Within these areas, the inspection consisted of

selective examination of procedures and representative records, interviews

with cersonnel, and observations by the inspectors.

During this inspection it was found that certain of your activities were not

conducted in full compliance with NRC requirements, as set forth in the Notice

of Violation enclosed herewith as Enclosure (1).

Pursuant to the provisions

of 10 CFR 2.201, you are required to submit to this office within 25 days of

the date of this Notice, a written statement or explanation in reply, including:

(1) admission or denial of the alleged items of noncomoliance; (2) the reasons

for tne items of noncomoliance if acmitted; (3) One corrective steos wnicn have

been taken and the results achieved; (4) corrective steos wnich will be taken

to avoid further items of noncomoliance; and (5) the date wnen full compliance

will be achieved. Under the authority of Section 182 of the Atcmic Energy Act

of 1954, as aroenced, this response shall be submitted under oath of affirmation.

  • n ac::oreance witn Iection 2.790 of the NRC's ' Rules of Practice,' ? art 2,

Title 10, Coce of Feceral Regulations, a copy of 2is letter anc .he enclosed

inspection report will be placed in the NRC's Public Document Rocm.

If this

report contains any information that you or your contractors believe to De

proprietary, it is necessary that you submit a written aoplication within 20

days of the date of this letter to this office to withhold such information

from public disclosure. Any such application must include a full statement

of the reasons on the basis of which it is claimed tnat the infomation

8101070 Q$

.

_

-

.

.

?ublic Service Company of Colorado

2

November 14, 1980

identified in the application is contained in a separate part of the document.

If we do not hear from you in this regard within the specified period, the

report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be cleased

to discuss them with you.

Sincerely,

f b k a h A -v 0

G. L. Madsen, Chief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Notice of Violation

2.

IE Inspection Report No. 50-267/80-21

cc w/ enclosures: