Forwards IE Insp Rept 50-416/80-19 on 800812-15 & Notice of Violation
ML19351D942
Person / Time
Site: Grand Gulf 
Issue date: 09/11/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Stampley N
MISSISSIPPI POWER & LIGHT CO.
Shared Package
ML19351D932 List:
References
NUDOCS 8011200451
Download: ML19351D942 (2)


See also: IR 05000416/1980019

Text

_.

.

.

.

n\\ j .

-

  1. gr @ 0 9'o

UNITED STATES

0

.

$'

NUCLEAR REGULATORY COMMISSION

~

  • '

n

'

$

nE

REGION 11

o,

~f

101 MARIETTA sT., P!.W., SUITE 3100

&

ATLANTA, GEOR1lA 3o3o3

.....

SEP 111980

In Reply Refer'To:

RII:WPA

50-416/80-19

Mississippi Power and Light Company

ATTN:

N. L. Stampley

Vice President of Production

P. O. Box 1640

Jackson, MS 39205

Gentlemen:

This refers to the inspection conducted by W. P. Ang of this office on August 12

through 15, 1980 of activities authorized by NRC Construction Permit No. CPPR-

118 for the Grand Gulf Nuclear Station facility, and to the discussion of our

findings held with G. B. Rogers at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

One new unresolved item resulted from this inspection and is discussed in the

enclosed report. This item will be examined during subsequent inspections.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the provisions of Section

2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office, within 20 days of

your receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved; (2)

corrective steps which will be taken to avoid further noncompliance; and (3) the

date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice,

<< 2; Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placel in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you nake a written application within 20 days to this office to

withnold such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is claimed that

the information is proprietary, and should be prepared so that proprietary infor-

mation identified in the application is contained in a separate part of the

. document. ,If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

soils 0 0 /5I

/

.

.

4

Tennessee Valley Authority

-2-

S E P 111880

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

wW

i

f c1

C. E. IfGrphy, Chief

Reactor Construction and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-416/80-19