Text
II
8
%
UNITED STATES
l
8
%
NUCLEAR REGULATORY COMMISSION
O
O/ /
~ y,
i
REGION V
'
g
j
o
1990 N. CALIFORNIA BOULEVARD
- ,,,*[g
SulTE 202, WALNUT CREEK PLAZA
[
d
WALNUT CREEK, CALIFORNIA 94596
N
g
h
1 m
&[E
March 24, 1981
gi
9
%
b
A&'
W lpy\\
o
/
Docket Nos. 50-508
50-509
Washington Public Power Supply System
P. O. Box 1223
Elma, Washington 98541
Attention: Mr. D. E. Dobson
Acting Program Director
Gentlemen:
Subject:
NRC Inspection at Washington Nuclear Projects
Nos. 3 and 5 (WNP-3/5)
This refers to the inspection conducted by Mr. T. W. Bishop of this
office from February 2-27, 1981, of activities authorized by NRC
Construction Permits Nos. CPPR-154 and -155, and to the discussion
.
of our findings held by Mr. Bishop with you and members of your staff
at the conclusion of the inspection.
Areas examined during this inspection are described in the enclosed
inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records,
interviews with personnel, and observations by the inspector.
No new items of noncompliance with NRC requirements were identified
within the scope of this inspection.
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter
and the enclosed inspection report will be placed in the NRC's Public
Document Room.
If this report contains any information that you
believe to be proprietary, it is necessary that you submit a written
app. :ation to this office, within 20 days of the date of this letter,
requesting that such information be withheld from public disclosure.
The application must include a full statement of the reasons why it
is claimed that the information is proprietary. The application
should be prepared so that any proprietary information identified
is contained in an enclosure to the application, since the application
without the enclosure will also be placed in the Public Document Room.
If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
810502ol55,
9
- . = _ _ _ . _
_
.
.-
--
_ _ -
- . .
'
.
.
Mr. D. E. Dobson
-2-
BAR 241981
Should you have any questions concerning this inspection, we will
be glad to discuss them with you.
i
Sincerely,
l
)
aul
B. H. Faulkenberry
Reactor Constructi
rojects Branch
Enclosure:
IE Inspection Report
Nos. 50-508/81-04
50-509/81-04
i
cc w/ enclosure:
j
R. L. Ferguson, Managing Director
M. E. Witherspoon, Quality
Assurance Director
!
'
l
>
.